Sullivan County v. Ruth

106 Tenn. 85
CourtTennessee Supreme Court
DecidedNovember 1, 1900
StatusPublished
Cited by6 cases

This text of 106 Tenn. 85 (Sullivan County v. Ruth) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sullivan County v. Ruth, 106 Tenn. 85 (Tenn. 1900).

Opinion

Wilkes, J.

This is an action for damages for the breach of a contract made by. the defendants with the county of Sullivan to erect a bridge across the Iiolston river at Bluff City. The Chancellor was of opinion the defendants had substantially complied with the contract and were not liable for damages, and dismissed complainant’s bill.

There was an appeal by the county, and on a hearing before the Court of Chancery Appeals that Court modified the decree of the Chancellor and gave judgment for an item of $172, with interest from the filing of the bill in this cause, this being the cost of having the bridge piers grouted, . which the defendants should have done [87]*87"but failed, to do, and with the further sum of $569, less the value of the stones for the fallen pier, which were used in rebuilding the same .after it was thrown down, wrhich item is specified ns being two-thirds of the actual cost to complainant of rebuilding the pier, and the cause was remanded to the Chancery Court of Sullivan county for a reference to ascertain the facts and the value of the material, to be deducted from the $569, with directions that the county should recover the balance and interest from the filing of the bill. The costs of this appeal and of the Court below were equally divided between the complainants and the defendants. Both parties have appealed to this Court and assigned errors.

It appears that the County Court of Sullivan County appointed a committee, consisting of the Road Commissioner and two others, to have the bridge built, and empowered them to employ an engineer. The committee let the stone work to .Ruth & Co., entering into a written contract with them, with specifications. The contracts were reported to the Court and by it approved. The contract and specifications required the contractors to do and perform the work as specified in it, and in conformity with the instructions which shall be given from time to time by the engineer in charge for the county, the work to be paid for when completed agreeably to the specifications and to the satisfaction of the engineer.

[88]*88The Court of Chancery Appeals report that the specifications were not complied with in that the excavation for the foundation course of the middle pier was not carried down to solid or bed rock at the upper end of the pier by a depth of eight inches on one side, increasing to eighteen inches on the other and for several feet of the length of the foundation, the average being twelve or thirteen inches; that there were pockets or seams in the bed rock that had not been excavated, and as a consequence the pier was laid •in a bed of sand and small water-worn stones and gravel; that no cement was used in building the foundation course of said pier, and none of the projecting stones had been removed to make a level surface for that course, but broken stones and sprawls had been used to level the same, and that no cement was used in the backing or body of the foundation. The Court further reports that these defects or failures to follow and observe the specifications were known to Lockhart, the engineer in charge of the work; that his attention was called to the defects in the foundation before any stones were laid thereon, and that he approved building upon it as it was, and approved the laying of the foundation piers as they were laid, and that he was with the committee frequently at the work and inspecting the same, and that the manner in which the piers were built must have been known to him and to [89]*89the committee; that- after it was completed it was inspected by the committee and. approved, and on their report was by the county received and paid for in full. That Court further reports that while the work was not done in strict compliance with the specifications in the particixlars mentioned, there ivas no fraud or concealment on the part of the contractors, but that the County Court had no knowledge of the defects and failure to carry out the spcifications until after the pier was washed down, such as may be imputed to it from the knowledge of the engineer and committee of construction.

Upon the facts as thus stated the Court of Chancery Appeals was of opinion that the provisions of the Act of 1835, being Sections 1730, 1731, 1732 of Shannon’s Code, fixing the rights and duties of the contractors, and that the Act of 1859-60 (Shannon, § 1738) did not apply exclusively, the latter relating to the repair of bridges, while the former related to the erection of new bridges. The Court ivas of opinion that under Sections 1730, 1732 the engineers and commissioners must have the contract executed strictly according to the specifications, and had no power to waive any of their requirements or deviate from their provisions, and hence the contractors could not be protected in their deviations from the specifications by the directions of the engineer and the acquiesence of the committee. We [90]*90are of opinion that Court is correct in its view of tbe statutes applicable in this case, to wit, Sections 1730, 1731, 1732 of Shannon’s compilation being Section 3 of the Acts of 1835. The provisions of these statutes relate to proceedings to build bridges and causeways at the expense of tire county, and are to be distinguished from Sections 1721 to 1729, which are Sections 1 and 2 of the same Act, -which relate to 'private enterprises of more or less public convenience. Hunter v. Campbell County, 7 Cold., 55; Grant v. Lindsay, 11 Heis., 667; Railway Co. v. Wilson, 5 Pick., 602.

It ' is not meant to hold that Section 1738, Shannon’s compilation, is not also applicable, as the repair of bridges may very properly be held to embrace the erection of a new one on the site of an old one which has become defective, but the question remains whether under either Act the committee appointed to have the bridge erected can in any way deviate from the specifications laid down in the contract. It rvill be observed that the contract bound defendants to perform the work in accordance with tire contract, and, also, in accordance with the instructions to be given from time to time by the engineer in charge. Evidently some duty was intended to be imposed on the engineer and committee in the execution of the contract and performance of the work. But we do not find that any discretion is [91]*91given them to alter or change the details which had been incorporated into the contract and made part of it. The language is that the contractor was to execute the contract under the instructions of the engineer and committee. This provision was for a twofold purpose. (1) If there was any question raised as to the requirements of the contract and how it was to be executed, the engineer and committee were to instruct the contractor; and 's2) they were to see that the contract was executed according to the spcifi cations. But the language carries no warrant of power to the engineer and committee to change or alter the contract or to waive any of its requirements, and certainly not in any feature or to any extent that would lessen the stability or efficiency of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Edwards v. Maler Construction Co.
715 S.W.2d 343 (Court of Appeals of Tennessee, 1986)
Estate of Jessee v. White
633 S.W.2d 767 (Court of Appeals of Tennessee, 1982)
Hickman County v. Nashville Bridge Co.
66 F.2d 174 (Sixth Circuit, 1933)
Bauman v. Pickwick Greyhound Lines, Inc.
14 Tenn. App. 242 (Court of Appeals of Tennessee, 1931)
Columbia & Big Bigby Turnpike Co. v. English
139 Tenn. 634 (Tennessee Supreme Court, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
106 Tenn. 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sullivan-county-v-ruth-tenn-1900.