Sugar Bay Club & Resort Corporation v. Agency Project Management, LLC

District Court, E.D. Louisiana·Decided September 26, 2024·No. 2:23-cv-05480·Unknown

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

SUGAR BAY CLUB & RESORT CIVIL ACTION CORP.

VERSUS NO: 23-5480

AGENCY PROJECT SECTION: “J”(5) MANAGEMENT, LLC ET AL.

ORDER AND REASONS

Before the Court is Intervenor Green Earth Engineering Services, Corporation’s Motion for Reconsideration (Rec. Doc. 48), which Plaintiff Sugar Bay Club and Resort Corp. joins in support (Rec. Doc. 49). Defendant CRSC, LLC has filed an opposition (Rec. Doc. 50). Having considered the motions and legal memoranda, the record, and the applicable law, the Court finds that Intervenor Green Earth Engineering Services, Corporation’s motion should be GRANTED IN PART. FACTS AND PROCEDURAL BACKGROUND

As previously detailed, this matter arises from a dispute between subcontractors involved in the cleanup after Hurricanes Maria and Irma hit the U.S. Virgin Islands in 2017. Prime contractor AECOM Caribe, LLP was hired using funds from the Federal Emergency Management Agency (“FEMA”). Below AECOM were three layers of subcontractors. AECOM entered into a subcontract with Defendant CRSC, LLC, which in turn entered into a subcontract with Defendant Agency Project Management (“APM”). Finally, APM entered into subcontracts with Plaintiff Sugar Bay Club & Resort Corporation and Intervenor Green Earth Engineer Services Corp. (“GEES”). Difficulties, however, arose at the third contractual layer. APM allegedly

became insolvent at some point after entering into these agreements. Sugar Bay is now a judgment creditor of APM, and GEES is the assignee of APM’s accounts receivable. Upon receipt of funds from AECOM, and in light of the multiple claimants owed payment by APM, CRSC began a separate interpleader action in Section B of this Court. See CRSC, LLC v. Blue Elephant Financing, LLC, et al., No. 22-1315 (E.D.

La.). CRSC received $1,607,272.83 from AECOM owed to APM, but only deposited $1,366,181,91 of those funds into the registry of the Court for disbursal. CRSC retained the remaining $241,090.92. In this action, Sugar Bay and CRSC filed cross-motions for summary judgment. Sugar Bay argued CRSC illegally retained funds that should have been disbursed due to the “pay when paid” contract between APM and CRSC. CRSC countered that it is entitled to withhold these funds necessary for costs and attorney’s

fees and that Sugar Bay had not met the requirements of an oblique action. In denying Sugar Bay’s motion and granting CRSC’s, this Court determined that (1) the contract between APM and CRSC incorporated the terms of the Master Contract as a whole; (2) through the Master Contract, CRSC possessed rights that flowed to it from AECOM; and (3) CRSC thereby had the right to withhold retainage for attorney’s fees and costs relating to litigation brought by APM’s vendors and subcontractors. The Court further dismissed Sugar Bay’s oblique action and GEES’s claims based on assignment of rights because CRSC is not currently indebted to APM. GEES now requests reconsideration of that Order and Reasons because of an

error of law, namely, that CRSC did not strictly follow the retainage requirements of the Master Contract. Sugar Bay joins the motion in support. In contrast, CRSC contends the motion is merely an attempt to relitigate issues previously before the Court and, thus, should be dismissed. LEGAL STANDARD

The Federal Rules of Civil Procedure do not expressly allow motions for reconsideration of an order. Bass v. U.S. Dep’t of Agric., 211 F.3d 959, 962 (5th Cir. 2000). However, the Fifth Circuit has consistently recognized that parties may challenge a judgment or order under Federal Rules of Civil Procedure 59(e). Southern Snow Manufacturing Co, Inc. v. SnoWizard Holdings, Inc., 921 F. Supp. 2d 548, 563– 64 (E.D. La. 2013). Altering or amending a judgment under Rule 59(e) is an “extraordinary

remedy” used “sparingly” by the courts. Templet v. HydroChem Inc., 367 F.3d 473, 479 (5th Cir. 2004). A motion to alter or amend calls into question the correctness of a judgment and is permitted only in narrow situations, “primarily to correct manifest errors of law or fact or to present newly discovered evidence.” Id.; see also Schiller v. Physicians Res. Grp. Inc., 342 F.3d 563, 567 (5th Cir. 2003). Courts have noted that motions to reconsider or amend a final or partial judgment are “not the proper vehicle for rehashing evidence, legal theories, or arguments that could have been offered or raised before entry of judgment.” Templet, 367 F.3d at 478–79; SnoWizard, 921 F. Supp. 2d at 565. Also, such motions should not be used to “re-litigate prior matters that . . . simply have been resolved to the

movant’s dissatisfaction.” See Voisin v. Tetra Techs., Inc., No. 08-1302, 2010 WL 3943522, at *2 (E.D. La. Oct. 6, 2010). Thus, to prevail on a motion under Rule 59(e), the movant must clearly establish at least one of four factors: (1) the motion is necessary to correct a manifest error of law, (2) the movant presents newly discovered or previously unavailable evidence, (3) the motion is necessary in order to prevent manifest injustice, or (4) the motion is justified by an intervening change in

controlling law. SnoWizard, 921 F. Supp. 2d at 565; Schiller, 342 F.3d at 567; Ross v. Marshall, 426 F.3d 745, 763 (5th Cir. 2005). DISCUSSION

For purposes of its reconsideration, GEES accepts the subcontract between CRSC and APM fully incorporates the terms of the Master Contract. On that basis, however, GEES asserts its error of law. GEES avers three errors in CRSC’s retainage of funds: (1) its failure to provide timely notice of the reason for the fund’s withholding; (2) its retainage of 15% of funds, rather than the contractually agreed- upon 5%; and (3) its retainage of funds more than sixty days after work completion without a pending warranty claim. Within its argument, however, GEES admits some of these points were previously briefed before the Court. (See Rec. Doc. 48-1 at 4–5 (discussing the notice requirement, “Plaintiff, Sugar Bay, raised this very issue in its reply”)). Sugar Bay also previously alleged CRSC was withholding 15% of funds it was obliged to pay to APM. (See Rec. Doc. 11 at 2–3 ¶ 20; Rec. Doc. 32 at 2; Rec. Doc. 41 at 4). A previously unaddressed notice issue is presented here. In the previous

resolution, this Court noted not merely the retainage language of the Master Contract, but also broader terms within the “Payment” section: The Master Contract between AECOM and CRSC does allow AECOM to withhold payment for numerous reasons including for “claims or liens chargeable to Subcontractor, . . . monies paid by AECOM on behalf of or for the benefit of Subcontractor, . . . and any costs or liability AECOM has incurred or may incur for which Subcontractor may be responsible under any other agreement between the parties.”

(Rec. Doc. 46 at 8 (quoting Rec. Doc. 38-3 at 7 (Master Contract))). These terms, incorporated within the subcontract, are sufficient to justify CRSC’s current withholding of funds due to ongoing costs incurred and pending final payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Sugar Bay Club & Resort Corporation v. Agency Project Management, LLC, (E.D. La. 2024).

Sugar Bay Club & Resort Corporation v. Agency Project Management, LLC (Sugar Bay Club & Resort Corporation v. Agency Project Management, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bass v. United States Department of Agriculture
211 F.3d 959 (Fifth Circuit, 2000)
Schiller v. Physicians Resource Group Inc.
342 F.3d 563 (Fifth Circuit, 2003)
Templet v. Hydrochem Inc.
367 F.3d 473 (Fifth Circuit, 2004)
Ross v. Marshall
426 F.3d 745 (Fifth Circuit, 2005)
Southern Snow Manufacturing Co. v. Snowizard Holdings, Inc.
921 F. Supp. 2d 548 (E.D. Louisiana, 2013)