Sturdy Built Homes, L.L.C. v. Carl E. Woodward L.L.C.

82 So. 3d 473, 2011 La.App. 4 Cir. 0881, 2011 WL 6217041, 2011 La. App. LEXIS 1539
CourtLouisiana Court of Appeal
DecidedDecember 14, 2011
DocketNo. 2011-CA-0881
StatusPublished
Cited by20 cases

This text of 82 So. 3d 473 (Sturdy Built Homes, L.L.C. v. Carl E. Woodward L.L.C.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sturdy Built Homes, L.L.C. v. Carl E. Woodward L.L.C., 82 So. 3d 473, 2011 La.App. 4 Cir. 0881, 2011 WL 6217041, 2011 La. App. LEXIS 1539 (La. Ct. App. 2011).

Opinion

DENNIS R. BAGNERIS, SR., Judge.

| ,This is a suit arising out of a construction project involving the construction of 460 apartments in New Orleans, Louisiana. Plaintiff, Sturdy Built Homes, LLC, (“Sturdy Built”) entered into a subcontract agreement with defendant Carl E. Woodward, LLC d/b/a/ Woodward Design + Build (“CEW”) to provide labor, materials to fabricate and install wall panels, beams and floor trusses. Upon the subcontract agreement being placed in default, Sturdy Built filed suit against defendants CEW, Ed Jorgensen, Lane Louque, and Travelers Casualty & Surety Company of America seeking damages for breach of the subcontract, unjust enrichment, tortious interference with the contract, and bad faith breach of contract. Defendants filed an exception of prematurity based on an arbitration provision contained in the subcontract agreement, which the trial court granted. After review of the record in light of the applicable law and arguments of the parties, we hereby affirm the ruling of the trial court.

FACTUAL AND PROCEDURAL BACKGROUND

On December 29, 2008, CEW, as general contractor, entered into a contract with C.J. Peete I, LLC c/o McCormack Baron Salazar, Inc., as Owner, to construct the 460 new apartments at the site of the former C.J. Peete Housing Project in New Orleans. Thereafter, on March 31, 2009, CEW entered into a contract entitled “Subcontract Agreement” with Sturdy Built to provide labor, materials to fabricate and install wall panels, beams and floor trusses on the project. This Subcontract Agreement contains a “Disputes” section, which provides:

Any controversy or claim arising out of or related to this Agreement or breach thereof shall be settled as follows:
|2A. Mediation shall be tried, utilizing a mutual [sic] agreeable mediator. Cost of the mediation shall be paid in equal parts by Contractor and Subcontractor. If the dispute is not resolved within 45 days of initial request for mediation then either party may proceed to file an arbitration demand.
B. If mediation fails, then by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. By agreement of both parties, in lieu of arbitration, the parties may select the judicial process. In such event suit shall be [475]*475filed in State of Louisiana in the Parish in which the Project is located.

On October 28, 2009, CEW notified Sturdy Built that it was terminating the Subcontract Agreement with respect to a portion of the project, specifically Blocks G and H, “for cause.” Following an unsuccessful mediation, on August 25, 2010, CEW filed an arbitration demand with the American Arbitration Association against Sturdy Built, seeking damages as a result of Sturdy Built’s failure to properly perform. On August 26, 2010, Sturdy Built filed this lawsuit seeking damages for breach of the subcontract, unjust enrichment, tortious interference with the contract, and bad faith breach of contract.

On November 24, 2010, Defendants filed a dilatory exception of prematurity and an alternative motion to stay Sturdy Built’s claims during the pendency of arbitration between CEW and Sturdy Built, arguing that the subcontract agreement mandates that any disputes are to be resolved by arbitration. At the hearing, Sturdy Built argued that the subcontract must be read together with the overall project construction contract to permit litigation of its claims. Specifically, Sturdy Built argues that the construction contract, which was entered into by CEW and C.J. Peete I, LLC c/o McCormack Baron Salazar, Inc., provides that, “[n]o claim, dispute, or other matter in question between the parties to this agreement arising |sout of the Construction contract, or the breach thereof, shall be submitted to arbitration.”

Following a hearing, the trial court granted defendants’ exception of prematurity and provided the following well-written reasons for judgment, in pertinent part:

Although the disputes section of the Construction Contract between CEW and the Project Owner provides that no issue shall be submitted to arbitration, it states that the parties further agree that no dispute between the Owner and the Contractor may be litigated unless and until the parties have first submitted the dispute to non-binding mediation pursuant to the Construction Industry Mediation Rules of the American Arbitration Association. Const. Cont. at Section 4.5. Louisiana Law provides that separate agreements as part of the same transaction are to be construed together as consistently as possible. See Neal v. Hardee’s Food, 918 F.2d 84, 37, (5th Cir.1990). As such, if the court were to read the Construction Contract together with the subcontract it is clear that both the Construction Contract and the subcontract seek to avoid litigation of matters. Even so, these were separate agreements, executed by different parties, entered into at different times, for different purposes and were not part of the same transaction. Id. Holding, “Under principles of contract law, separate agreements executed contemporaneously, by the same parties, for the same purpose, and as part of the same transaction, are to be construed together.” Thus, this Court finds that Plaintiff was not a party nor a third party beneficiary to the Construction Contract and cannot use the Construction Contract to avoid the terms of the subcontract that provide for arbitration. Furthermore, Louisiana Law provides that when the words of the contract are clear and explicit and lead to no absurd consequences, no further interpretation may be made in search of the parties’ intent. La. C.C. Art. 2046. The arbitration clause contained in the subcontract agreement is clear and explicit. Sturdy Built had the opportunity to and did in fact request numerous changes to the subcontract agreement; however, they made no changes to the arbitration pro[476]*476vision contained therein. Plaintiff Sturdy Built did not attempt to modify or delete the Arbitration Clause contained in the subcontract even though they requested and received other changes to Uprovisions of the subcontract. Plaintiff knowingly and voluntarily entered into the arbitration agreement. As such, this Court finds that a valid arbitration agreement does exist.
After determining whether a valid arbitration agreement exist, the court must next decide whether the Plaintiffs claims fall within the scope of that agreement. The Arbitration clause contained in the subcontract provides, “any controversy or claim arising out of or related to this agreement or breach thereof shall be settled as follows.... ” See Subcontract Agreement at Section 24. This language is broad and Plaintiffs claims fall within the scope of the arbitration agreement. Louisiana courts have recognized a strong presumption in favor of arbitration and any doubt as to whether a controversy is arbitrable should be resolved in favor of arbitration. Moore v. Automotive Protection Corp., 97-0623, p. 2 (La.App. 4 Cir. 5/21/97), 695 So.2d 550, 551. As such, this Court finds that the broad language of this Arbitration Clause encompasses the Plaintiffs claims.
Finally, as to the exception of Prematurity, this Court must address Plaintiffs assertion that certain parties to the litigation were non-signatories to the arbitration agreement and as such cannot be made to arbitrate their claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Traders' Mart, Inc. v. AOS, Inc.
268 So. 3d 420 (Louisiana Court of Appeal, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
82 So. 3d 473, 2011 La.App. 4 Cir. 0881, 2011 WL 6217041, 2011 La. App. LEXIS 1539, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sturdy-built-homes-llc-v-carl-e-woodward-llc-lactapp-2011.