Stultz Electric Works v. Marine Hydraulic Engineering Co.

484 A.2d 1008, 39 U.C.C. Rep. Serv. (West) 1186, 1984 Me. LEXIS 843
CourtSupreme Judicial Court of Maine
DecidedDecember 6, 1984
StatusPublished
Cited by24 cases

This text of 484 A.2d 1008 (Stultz Electric Works v. Marine Hydraulic Engineering Co.) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stultz Electric Works v. Marine Hydraulic Engineering Co., 484 A.2d 1008, 39 U.C.C. Rep. Serv. (West) 1186, 1984 Me. LEXIS 843 (Me. 1984).

Opinion

NICHOLS, Justice.

The Defendant, Marine Hydraulic Engineering Co., appeals from an order of the Superior Court, Cumberland County, affirming the District Court’s (Portland) order granting the motion of the Plaintiff, Stultz Electric Works, for summary judgment for the balance of a debt found owed by the Defendant. The Defendant argues that the Superior Court erred in affirming the order for summary judgment because a check issued by the Defendant to the Plaintiff contained a “settlement in full” notation which created a binding accord and satisfaction upon the Plaintiff’s deposit, notwithstanding the “reservation of rights” language added to the instrument by the Plaintiff at the time of its endorsement.

We agree with the Defendant and vacate the judgment.

On September 21, 1982, the Plaintiff had brought suit against the Defendant in District Court, claiming $14,931.99 to be due on the Defendant’s account with the Plaintiff for goods sold and delivered between March 31, 1982 and May 7, 1982. The District Court had authorized an attachment on the Defendant’s property, other than real estate, for $14,931.99 plus interest and costs, on October 20, 1982. This order had been entered in District Court on November 3, 1982, the same day that the Plaintiff had filed an amendment to its complaint which added an alternate count for the sum of $14,274.25.

During the pendency of the proceedings, the Defendant on December 13, 1982, issued a check to the Plaintiff for $10,738.04. On the back of this check the Defendant wrote the following:

“Endorse only as settlement in full all claims Stultz Electric Works verses [sic] Marine Hydraulic Engineering Co., Inc.”

The Plaintiff, however, did not endorse and deposit the check until it inscribed thereon:

“Endorsed and deposited under protest without prejudice and with a reservation of our rights to the balance of.”

The Plaintiff thereafter entered a motion for summary judgment in District Court on January 28, 1983, seeking $3,536.21, the balance that it claimed remained due after receipt of the Defendant’s check. The Defendant then filed with the District Court a memorandum of law in opposition to the Plaintiff’s motion and in support of its own motion for summary judgment. In support of the latter motion, the Defendant filed the affidavit of Robert Crowe, President of the Defendant corporation, indicating that Crowe intended the restrictive language on the check to operate as notice of full and final payment of amounts claimed to be owed by the Defendant.

Both parties submitted briefs to the District Court and following oral arguments, on February 16,1983, the Plaintiff’s motion for summary judgment was granted and the Defendant’s motion denied. The District Court concluded that the Plaintiff had preserved its rights under 11 M.R.S.A. § 1-207 (1964) and thereby prevented an accord and satisfaction when it endorsed the Defendant’s check. The Defendant promptly entered an appeal to the Superior Court.

Four months later, the Superior Court ordered the case remanded to the District Court for entry of a final judgment, the District Court having failed to specify the amount of the judgment to be entered for the Plaintiff. On remand the District Court entered an order against the Defend *1010 ant for $3,536.21 and the Defendant thereupon appealed to the Superior Court.

The Superior Court affirmed the District Court’s order and remanded the case to the District Court for entry of judgment consistent with the original order of the District Court. The Superior Court determined that the language regarding “full settlement,” inserted by the Defendant on its check, did not operate as an accord and satisfaction because the “reservation of rights” statement placed on the instrument by the Plaintiff was effective pursuant to 11 M.R.S.A. § 1-207 (1964).

The Defendant seasonably entered this appeal to the Law Court.

We have consistently found that a check bearing language that indicates “full and final payment” or “in satisfaction of all claims” creates an accord and satisfaction 1 when cashed or deposited by the payee. See e.g., Graffam v. Geronda, 304 A.2d 76 (Me.1973); Wiggin v. Sanborn, 161 Me. 175, 210 A.2d 38 (1965); Larsen v. Zimmerman, 153 Me. 116, 135 A.2d 270 (1957). It is clear that the burden is on the party asserting the affirmative defense of accord and satisfaction to show by a preponderance of the evidence that an accord and satisfaction has transpired. Wiggin, 161 Me. at 175, 210 A.2d at 38.

In analyzing the language on an instrument that allegedly creates an accord and satisfaction, we have focussed primarily on whether such language has provided the payee with sufficient notice of the pay- or’s intent. Graffam, 304 A.2d at 79-80. This case requires us to carry our analysis one step further in addressing an issue of first impression for this Court. Specifically, we must decide whether “reservation of rights” language inserted by a payee on an instrument may operate to bar an accord and satisfaction. The Plaintiff would have us find that 11 M.R.S.A. § 1-207 (1964) 2 recognizes a bar bo an accord and satisfaction under the facts presented in this case. We disagree with the Plaintiff’s interpretation of section 1-207.

A cursory reading of section 1-207 of the Uniform Commercial Code could misleadingly prompt a payee to both disregard a payor’s statement of final payment and claim a reservation of rights. At least one court has determined that a careful examination of the language of section 1-207 alone indicates that section 1-207 was not designed to apply to full payment checks. See Jahn v. Burns, 593 P.2d 828, 830 Wyo. 1979). According to the Wyoming Supreme Court, the “performance offered” is full payment, and therefore, cannot be “assented to” if the payee is held to have reserved rights to a balance of payment. 3 Id. Notwithstanding the fact that such a statutory analysis appears reasonable, we look to the relationship between sections 1-207 and 1-103, the pertinent legislative history, and public policy considerations, in order to lay to rest any contention that section 1-207 alters the common law doctrine of accord and satisfaction.

We first note that the premise set forth in 11 M.R.S.A. § 1-103 (1964) is instructive in interpreting the Uniform Commercial Code as enacted in this State. Section 1- *1011 103 provides that principles of law and equity are not to be displaced unless done so explicitly. Significantly, section 1-207 makes no mention of displacing the common law doctrine of accord and satisfaction and thus should not be interpreted to effectuate such an intent. See State Dept. of Fisheries v. J-Z Sales Corp., 25 Wash.App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Associated Builders, Inc. v. Coggins
1999 ME 12 (Supreme Judicial Court of Maine, 1999)
Greenvall v. Maine Mutual Fire Insurance
1998 ME 204 (Supreme Judicial Court of Maine, 1998)
Leonard v. Gray
686 A.2d 1079 (Supreme Judicial Court of Maine, 1996)
Kallop v. McAllister
678 A.2d 526 (Supreme Court of Delaware, 1996)
E.S. Herrick Co. v. Maine Wild Blueberry Co.
670 A.2d 944 (Supreme Judicial Court of Maine, 1996)
Acierno v. Worthy Brothers Pipeline Corp.
656 A.2d 1085 (Supreme Court of Delaware, 1995)
Painter v. Peavy
451 S.E.2d 755 (West Virginia Supreme Court, 1994)
Burke Co. v. Hilton Development Co.
802 F. Supp. 434 (N.D. Florida, 1992)
McKee Construction Co. v. Stanley Plumbing & Heating Co.
828 S.W.2d 700 (Missouri Court of Appeals, 1992)
Robinson v. Garcia
804 S.W.2d 238 (Court of Appeals of Texas, 1991)
Soucier v. Wall
581 A.2d 422 (Supreme Judicial Court of Maine, 1990)
AFC Interiors v. DiCello
544 N.E.2d 869 (Ohio Supreme Court, 1989)
John Grier Construction Co. v. Jones Welding & Repair, Inc.
383 S.E.2d 719 (Supreme Court of Virginia, 1989)
Maine Mutual Fire Insurance v. Watson
532 A.2d 686 (Supreme Judicial Court of Maine, 1987)
Pileco, Inc. v. HCI, INC.
735 S.W.2d 561 (Court of Appeals of Texas, 1987)
Nelson v. Fire Insurance Exchange
510 N.E.2d 137 (Appellate Court of Illinois, 1987)
Anderson v. Rosebrook
737 P.2d 417 (Supreme Court of Colorado, 1987)
County Fire Door Corp. v. C. F. Wooding Co.
520 A.2d 1028 (Supreme Court of Connecticut, 1987)
RMP Industries, Ltd. v. Linen Center
386 N.W.2d 523 (Court of Appeals of Iowa, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
484 A.2d 1008, 39 U.C.C. Rep. Serv. (West) 1186, 1984 Me. LEXIS 843, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stultz-electric-works-v-marine-hydraulic-engineering-co-me-1984.