Struewing v. Village of Yellow Springs

2014 Ohio 1864
CourtOhio Court of Appeals
DecidedMay 2, 2014
Docket2013 CA 21
StatusPublished

This text of 2014 Ohio 1864 (Struewing v. Village of Yellow Springs) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Struewing v. Village of Yellow Springs, 2014 Ohio 1864 (Ohio Ct. App. 2014).

Opinion

[Cite as Struewing v. Village of Yellow Springs, 2014-Ohio-1864.]

IN THE COURT OF APPEALS FOR GREENE COUNTY, OHIO

KENNETH L. STRUEWING, et al. :

Plaintiffs-Appellees : C.A. CASE NO. 2013 CA 21

v. : T.C. NO. 09CV1048

VILLAGE OF YELLOW SPRINGS : (Civil appeal from Common Pleas Court) Defendant-Appellant :

:

..........

OPINION

Rendered on the 2nd day of May , 2014.

ARTHUR R. HOLLENCAMP, Atty. Reg. No. 0020528, 130 W. Second Street, Suite 2107, Dayton, Ohio 45402 Attorney for Plaintiffs-Appellees

JOHN C. CHAMBERS, Atty. Reg. No. 0029681 and TERENCE L. FAGUE, Atty. Reg. No. 0018687 and SASHA ALEXA M. VANDEGRIFT, Atty. Reg. No. 0080800, 33 W. First Street, Suite 600, Dayton, Ohio 45402 Attorneys for Defendant-Appellant

FROELICH, P.J.

{¶ 1} The Village of Yellow Springs appeals from a judgment of the Greene

County Court of Common Pleas, which adopted the magistrate’s ruling (with one 2

modification) and held that a 1974 written easement granted by Howard Kahoe to the

Village to construct, maintain, and operate sanitary sewer and water lines on his property

was valid and enforceable. The trial court ordered specific performance under the terms of

the easement and that the Village pay $10,244 plus statutory post-judgment interest to

Kenneth and Betheen Struewing, the current owners of the property, for the cost of digging a

well on their property.

{¶ 2} The Village raises six assignments of error. It claims that the easement is

void because it violated R.C. 2921.42 and the Village did not adopt the easement, that the

trial court erred in denying the Village’s easement by estoppel claim, that the trial court erred

in finding that the Struewings had a right to tap into the water line, that the trial court erred

in ordering the Village to pay for the installation costs for a well, and that the Struewings’

claims were barred by their respective statutes of limitations. For the following reasons, the

trial court’s judgment will be affirmed.

I.

{¶ 3} In September 2009, Kenneth and Betheen Struewing brought suit against the

Village of Yellow Springs due to the Village’s denial of the Struewings’ request for a free

water and sewer tap-in for their property. The Struewings alleged that, in 1974, the Village

had received an easement to construct, maintain, and operate sanitary sewer lines and water

lines on and through the real property now owned by them, that the easement entitled them

to one free water and sewer tap, that the Village had installed the sanitary and water lines

pursuant to the easement, and that such lines have been in continuous use since installation.

The Struewings sought a declaratory judgment regarding the validity of the easement (Count 3

One) and specific performance of the easement (Count Two). As alternatives to their

specific performance claim, the Struewings also alleged equitable estoppel, breach of

contract, trespass, and ejectment. With permission of the trial court, the Struewings later

added a claim for damages, stating that the denial of their water tap-in request forced them to

dig a well in order to provide water service to the main residence on the property.

{¶ 4} In its answer, the Village denied that it had received and accepted the grant

of the easement in 1974, and it denied that it had provided or agreed to provide water and

sewer tap-ins to either the Struewings or their predecessors. The Village raised numerous

affirmative defenses, and it asserted three counterclaims: (1) a declaratory judgment as to the

rights of the parties concerning the water and sewer tap-ins, (2) quiet title as to the Village’s

easement interest, and (3) a preliminary and permanent injunction to enjoin the Struewings

from altering or removing the sewer and/or water lines.

{¶ 5} In June 2011, the Village moved for summary judgment, arguing, among

other things, that the Struewings’ claims were barred by the statutes of limitations and that

the easement was void because it had not been authorized by the Village Council. The trial

court denied the motion.

{¶ 6} A magistrate conducted a bench trial on July 21-22, 2011. On April 6,

2012, the magistrate issued a decision, concluding that the Struewings were entitled to

specific performance on the easement and to damages of $10,244, representing the cost to

dig the well. In so holding, the magistrate made detailed factual findings. Given our

standard of review (¶10-12, infra), we quote those findings extensively:

Facts [Cite as Struewing v. Village of Yellow Springs, 2014-Ohio-1864.] Howard Kahoe was the Village of Yellow Springs Manager from the

1950s to 1974. As Manager, he was integrally involved with the everyday

operation of the Village. In the late 1950s, early 1960s, the Village of

Yellow Springs was experiencing problems with its water and sewer systems

in that it could not keep up with demand. The problem needed to be

addressed so Woolpert Consultants (Woolpert), Dayton, Ohio, a company

who designed sanitary systems for governmental agencies, was hired by the

Village to consult and design what would later become known as the South

Side Sewer Project.

John Eschliman was employed as an engineer by Woolpert from

1948-1978 (he actually knew Village Manager Howard Kahoe). Mr.

Eschliman was enlisted to help design the new sanitary sewer system. He

was deposed by counsel and gave his best recollection of the events related to

the South Side Sewer Project. Mr. Eschliman stated that at the time most of

the Village of Yellow Springs’ water came from the north part of town. In

order to increase the water supply for the Village water had to be piped in

from the southeast part of the Village, outside the village actually. See

deposition of John Eschliman, p.19. He testified that the most cost-effective

design would be gravity-based as opposed to one utilizing a pump station.

He also opined that flow rate was important because of the use of the system

by the fire department and other enterprises other than homeowners. It can

also affect the amount you pay for insurance. Although Mr. Eschliman did

discuss the need for cost effective easements for the Project and how future 5

connections were customary consideration for easements, he was unable to

comment on the easement given to the Village by Mr. Kahoe (he did

comment on the fact that Mr. Kahoe did not want the sanitary sewer system to

cross his property unless it was cheaper for the Village.) Moreover, it was

agreed that in order to hold down the cost of the system, the Village, rather

than purchasing the necessary land for the South Side Sewer Project, would

have to seek alternative means, such as easements. See Deposition of Bruce

Rickenbach, Assistant Village Manger to Howard Kahoe/Village Manager in

1974, who testified in order to reduce cost, it was customary to grant property

owners tap-ins to the property owners [sic] in exchange for the easement.

Ultimately, by 1963 the South Side Sewer Project was built, at least in part,

on land owned by Howard Kahoe. See Defendant’s Exhibit A, an as-built

drawing of sanitary sewer line. However, at the time, no easement was

recorded with regard to the Kahoe property.

The Kahoe Easement

Howard Kahoe remained the Village Manager until 1974 when he was

succeeded by his assistant Bruce Rickenbach. At around the same time

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Proctor v. Proctor
548 N.E.2d 287 (Ohio Court of Appeals, 1988)
Randall v. Randall, 1739 (5-1-2009)
2009 Ohio 2070 (Ohio Court of Appeals, 2009)
City of Dayton v. Whiting
673 N.E.2d 671 (Ohio Court of Appeals, 1996)
State v. Boles
2010 Ohio 278 (Ohio Court of Appeals, 2010)
Blakemore v. Blakemore
450 N.E.2d 1140 (Ohio Supreme Court, 1983)
Berk v. Matthews
559 N.E.2d 1301 (Ohio Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ohio 1864, Counsel Stack Legal Research, https://law.counselstack.com/opinion/struewing-v-village-of-yellow-springs-ohioctapp-2014.