Structure & Design, Unlimited, Inc. v. Contemporary Concepts Building & Design, Inc.

151 S.W.3d 904, 2004 Mo. App. LEXIS 1983, 2004 WL 3016274
CourtMissouri Court of Appeals
DecidedDecember 28, 2004
DocketWD 63682
StatusPublished
Cited by8 cases

This text of 151 S.W.3d 904 (Structure & Design, Unlimited, Inc. v. Contemporary Concepts Building & Design, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Structure & Design, Unlimited, Inc. v. Contemporary Concepts Building & Design, Inc., 151 S.W.3d 904, 2004 Mo. App. LEXIS 1983, 2004 WL 3016274 (Mo. Ct. App. 2004).

Opinion

PAUL M. SPINDEN, Judge.

The parties to this lawsuit are disputing a mechanic’s hen that Structure and Design Unlimited, Inc., attached to an apartment building in Miller- County. As the contractor overseeing the building’s relocation 800 yards to a new tract, Contemporary Concepts Building and Design, Inc., contracted in 2001 with Structure and Design to split the building into three units for the move and to reattach the units after the move. Contemporary Concepts terminated the contract before the project was complete on the ground that Structure and Design breached the contract by overcharging for labor.

After deciding that Structure and Design was over-charging, Contemporary Concepts refused to pay it the final two installments under the contract. Structure and Design filed a mechanic’s hen for $71,059.23 on the building, owned by Ozark Gardens Apartment, L.L.C. Structure and Design also sued Contemporary Concepts, Ozark Garden, Central Bank of the Lake of the Ozarks, which held a mortgage interest in the building, and John Curran, trustee. Structure and Design dismissed its action against Central Bank and Cur-ran, and, after trial, the circuit court entered judgment for Structure and Design but assessed damages at $34,151.23. The circuit court vitiated Structure and Design’s hen on the building because the hen did not contain a “just and true account,” and the circuit court rejected Structure and Design’s request for attorney fees and interest.

Structure and Design appeals. We affirm the portion of the circuit court’s judgment vitiating Structure and Design’s hen. We reverse the circuit court’s judgment and remand for it to enter a proper assessment of damages for breach of contract.

1. “Just and True Account”

The circuit court vitiated Structure and Design’s hen on the ground that the hen did not contain a “just and true account.” For Structure and Design to obtain a hen on the building, Section 429.080, RSMo 2000, required it to file *907 with the circuit court clerk, “within six months after the indebtedness shall have accrued[,] ... a just and true account of the demand due [it] after all just credits have been given[.]” The circuit court concluded that Structure and Design’s hen did not contain a just and true account:

[Structure and Design] included within its lien statement charges for rental property, which are not lienable items. (429.080 RSMo) In addition, the uncon-tradicted testimony at trial was that there were overbilled hours of $4,082.00 that were not related to this ... project (the work was actually done for Prew-itt’s Highway 54 Enterprises); that all hours shown on the lien statement were not correct ([Structure and Design’s employee,] Diana Hamson[,] testified that she just didn’t write in the correct name but put “new laborers” hours under “prior laborers” names[) ]; that [Structure and Design] had agreed not to charge for any work done after September 21, 2008, [sic] and in fact did charge for work performed September 24, 2001-September 28, 2001.

Competent and substantial evidence supports the circuit court’s judgment. In reviewing a decision concerning mechanic’s liens, we are obligated to affirm the circuit court’s judgment “unless there is no substantial evidence to support it, unless it is against the weight of the evidence, or unless it erroneously declares or applies the law.” Commercial Openings, Inc. v. Mathews, 819 S.W.2d 347, 349 (Mo. banc 1991) (quotation omitted).

The circuit court correctly focused on whether or not Structure and Design’s lien set forth a just and true account of the $71,059.23 that it claimed for the project. Without a just and true account, a lien claimant has no rights. See Sears, Roebuck and Company v. Seven Palms Motor Inn, Inc., 530 S.W.2d 695, 698 (Mo. banc 1975). The General Assembly did not define “just and true,” and the courts have not been exacting in explaining their interpretations of the term. This court’s Eastern District has set out the most definitive definition: “A lien statement may be regarded as just and true if it contains mistakes or errors of omission, as long as those inaccuracies are unintentional and are the result of honest inadvertence, accident, or oversight, and do not result from deliberate intention or design.” Dave Kolb Grading, Inc. v. Lieberman Corporation, 837 S.W.2d 924, 933 (Mo.App.1992). Including nonlienable items does not necessarily vitiate the entire lien so long as the nonlienable items were included by honest mistake and can be separated from the lienable items. Sears, 530 S.W.2d at 698-99. The lienor bears the burden of proving that mistakes or omissions were “due to an honest mistake.” City-Wide Asphalt Company, Inc. v. Industrial Paving, Inc., 838 S.W.2d 480, 482 (Mo.App.1992).

Rental equipment is not subject to a mechanic’s lien. Bush Construction Machinery, Inc. v. Kansas City Factory Outlets, L.L.C., 81 S.W.3d 121, 126 (Mo.App.2002). Structure and Design acknowledges that it wrongly included rental equipment in its mechanic’s lien, but it argues that its lien should be enforced because no one established that it had acted intentionally. Structure and Design misperceives the law. As the mechanic’s lien claimant, Structure and Design had the burden of proving that it included rental equipment by honest mistake. City-Wide Asphalt, 838 S.W.2d at 482. Structure and Design did not produce any evidence that its error resulted from honest inadvertence.

Structure and Design failed to carry its burden. Because substantial evidence supported the circuit court’s determination *908 that Structure and Design’s lien did not contain a just and true account, we affirm that portion of the judgment vitiating Structure and Design’s lien.

2. Damages

Structure and Design next argues that substantial evidence did not support the circuit court’s assessment of only $34,151.23 in damages, rather than granting its prayer for $68,771.23. The circuit court explained that it reduced the award because Structure and Design had charged too much.

First, the circuit court reduced the judgment by $12,903 because Structure and Design had billed laborers at $26 an hour rather than the agreed-upon rate of $23 an hour. Byno Davidson, who was Structure and Design’s lead carpenter during this project and who supervised workers on the job site, testified that, based on his knowledge of the workers’ knowledge and skill levels, several of the workers billed as carpenters were laborers or less skilled than others billed at the carpenter rate. In addition, Structure’s lien claim provided hourly totals billed for each individual worker. This was enough evidence to support the circuit court’s decision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
151 S.W.3d 904, 2004 Mo. App. LEXIS 1983, 2004 WL 3016274, Counsel Stack Legal Research, https://law.counselstack.com/opinion/structure-design-unlimited-inc-v-contemporary-concepts-building-moctapp-2004.