StructSure Projects, Inc.

CourtArmed Services Board of Contract Appeals
DecidedAugust 7, 2023
Docket62927
StatusPublished

This text of StructSure Projects, Inc. (StructSure Projects, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
StructSure Projects, Inc., (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) StructSure Projects, Inc. ) ASBCA No. 62927 ) Under Contract No. W9127S-17-D-6004 )

APPEARANCE FOR THE APPELLANT: Michael S. Alfred, Esq. Hallett & Perrin, PC Dallas, TX

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Michael T. Geiselhart, Esq. Engineer Trial Attorney U.S. Army Engineer District, Jacksonville

Allen S. Black, Esq. Engineer Trial Attorney U.S. Army Engineer District, Little Rock

OPINION BY ADMINISTRATIVE JUDGE EYESTER PURSUANT TO BOARD RULE 11

The U.S. Army Corps of Engineers (government or USACE) awarded StructSure Projects, Inc. (StructSure) a task order to perform design and alteration services at the David Grant Medical Center, Travis Air Force Base. After StructSure began work, and due to the COVID-19 pandemic, the agency designated the task order non-mission essential and precluded StructSure and its subcontractors from any on-site activities for a period of 44 days.

StructSure has filed this appeal alleging it is owed money because the government changed the task order requirements when it continued to use the temporary phasing facilities and other services provided by StructSure during the 44 days the task order was designated non-mission essential. The parties elected to waive a hearing and submit the appeal on the record pursuant to Board Rule 11. For the following reasons, we grant StructSure’s appeal. FINDINGS OF FACT

1. On July 14, 2017, USACE awarded multiple award task order contract (MATOC) No. W9127S-17-D-6004 to StructSure 1 for design-build construction services (R4, tab 1 at 2-3). 2 The MATOC incorporated by reference Federal Acquisition Regulation (FAR) 52.233-1, DISPUTES (MAY 2014); FAR 52.243-4, CHANGES (JUN 2007); and FAR 52.249-10, DEFAULT (FIXED-PRICED CONSTRUCTION) (APR 1984) (id. at 8-9). The MATOC incorporated in full FAR 52.243-7, NOTIFICATION OF CHANGES (APR 1984) (id. at 26-28). All orders issued were subject to the terms of the MATOC (id. at 32).

2. Subsequently, on September 27, 2018, USACE issued order No. W9127S-18-F-0112 to StructSure in the amount of $35,106,355 (R4, tab 2 at 46). The order contained several contract line item numbers (CLINs) for various services, including design and alteration services for the David Grant Medical Center, Travis Air Force Base (id. at 46, 48-52). Each CLIN set forth a fixed-price amount (id. at 48-52). StructSure was to complete the work by March 12, 2021 (id. at 56).

3. As relevant here, CLIN 0006 required StructSure provide temporary phasing facilities for use at the medical center during the alteration services and was awarded in the fixed amount of $2,437,055 (id. at 50). There were two temporary phasing facility sites--one for the Joint Radiation Oncology Center (JROC) and one for all others, including pediatrics (see R4, tab 13 at 158; Request for Proposal (RFP) Statement of Work, attach. 01 10 10 SOW D-Drawings (23May18).pdf at 13). StructSure’s subcontractor for the temporary phasing facilities was Sustainable Modular Management (Sustainable Modular) (see R4, tab 13 at 158).

4. On March 21, 2020, the government issued its first of several notices to StructSure stating that the Wing Leadership designated the task order award as non- mission essential and therefore StructSure and its subcontractors could not continue on-site construction activity until later notified (R4, tab 4). The notice advised StructSure that the government may excuse a contractor’s performance delay pursuant to FAR 52.249-10 and/or FAR 52.249-14 due to the COVID-19 public health emergency and StructSure might be entitled to non-compensable days (id.). Several similar notices followed in March and April (R4, tabs 7-9).

1 The MATOC was awarded to United Excel Corporation (R4, tab 1 at 3). However, on July 1, 2019, the government issued a modification changing the contractor’s name to StructSure Projects, Inc. on the MATOC and all task order awards (R4, tab 3 at 116). 2 Citations to the Rule 4 file are to the government’s Bates-stamped numbers. Citations to the briefs are to the PDF page numbers.

2 5. On April 29, 2020, the government informed StructSure that it could recommence on-site construction activities (R4, tab 10). The parties both acknowledge that due to COVID-19 and the task order’s designation as non-mission essential, StructSure was unable to perform on site for 44 days (app. br. at 5; gov’t reply br. at 4).

6. Two weeks later, StructSure submitted a request for equitable adjustment (REA) regarding the impacts of the suspension of work, mostly relating to schedule (R4, tab 11 at 135-36). Some impacts included supply chain issues, remobilization time, and revised site procedures (id. at 135). In response, on May 19, 2020, the agency issued bilateral Modification No. A00008, changing the task order completion date to June 19, 2021, and thereby adding 92 calendar days to the period of performance (R4, tab 12 at 152-53). The modification did not increase the order price and explained the delay was due to the COVID-19 pandemic, which required stoppage of work on the project (id. at 153). The modification, issued pursuant to the default clause, only accounted for the “non-compensatory time extension” as it was the government’s “understanding that the contractor plan[ned] to submit an REA for costs incurred due to the Government’s actions dealing with COVID-19” which would be reviewed once received for merit (id. at 154).

7. On July 2, 2020, StructSure submitted another REA stating that the temporary phasing facilities and associated rental furniture and equipment were in use by the government during the time the project was classified as non-mission essential and StructSure could not perform on site (R4, tab 13 at 155). As a result, StructSure stated it incurred extended rental costs for the facilities, furniture and equipment because originally, these items were to be on site for only 13 months (id.). However, due to the stoppage of work at the job site, and per the modification, the temporary phasing facilities were on site for 16 months (id.). StructSure attached an itemized sheet of cost impacts for the temporary phasing facilities, furniture rental, medical gas rental, and initial outfitting services for three months, at a total cost of $278,227 (id. at 157). In addition, StructSure attached documents showing the rental costs for two temporary phasing facilities (one for JROC and one for pediatrics), rental furniture, increased storage of items at the warehouse, and oxygen bottle refills (id. at 158-60). The agency denied the REA stating that pursuant to FAR 52.249-10, the government may grant extra time in response to a pandemic or quarantine, but not additional money (R4, tab 14).

8. StructSure next submitted an uncertified claim on September 4, 2020, seeking reimbursement for the same costs (R4, tab 15). According to the claim, because the government occupied the temporary phasing facilities and utilized the rental furniture/equipment during the stoppage of work, StructSure did not have the opportunity to demobilize the facilities from the jobsite to prevent incurring these

3 additional costs (id.). The claim was later certified by StructSure on February 3, 2021 (R4, tab 18 at 190).

9. On March 30, 2021, USACE issued a contracting officer’s final decision (COFD) denying the claim for two reasons (R4, tab 19). First, the agency stated that the exclusion from the work site was not a change as it was considered a sovereign act of the government and therefore pursuant to FAR 52.249-10, the contracting officer could issue a non-compensable extension for days lost, which the agency did (id. at 191).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horowitz v. United States
267 U.S. 458 (Supreme Court, 1925)
CONNER BROS. CONST. CO., INC. v. Geren
550 F.3d 1368 (Federal Circuit, 2008)
Century Exploration New Orleans, LLC v. United States
110 Fed. Cl. 148 (Federal Claims, 2013)
Century Exploration New Orleans, LLC v. United States
745 F.3d 1168 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
StructSure Projects, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/structsure-projects-inc-asbca-2023.