String v. Steven Development Corp.

307 A.2d 713, 269 Md. 569, 1973 Md. LEXIS 853
CourtCourt of Appeals of Maryland
DecidedJuly 27, 1973
Docket[No. 347, September Term, 1972.]
StatusPublished
Cited by11 cases

This text of 307 A.2d 713 (String v. Steven Development Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
String v. Steven Development Corp., 307 A.2d 713, 269 Md. 569, 1973 Md. LEXIS 853 (Md. 1973).

Opinion

Levine, J.,

delivered the opinion of the Court.

Having convinced himself that his new home would not be completed on schedule, appellant (String) declared the contract providing for its purchase “null and void.” Subsequently, he brought this action against appellee (Steven) in the Circuit Court for Montgomery County, seeking the return of his deposit and the reimbursement of a loan commitment fee paid to a savings and loan association. At the conclusion of the trial, presided over by Judge Cahoon sitting without a jury, a judgment for costs was entered in favor of Steven. This appeal followed.

On April 15, 1971, String executed a contract for the *571 purchase of a house that was to be built by Steven in its Bedfordshire subdivision of Montgomery County. String agreed to pay $45,751, of which $41,176 was to be furnished by a first trust to be placed by him with Standard Savings & Loan Association. The contract, which was accepted by Steven on April 20,1971, also provided:

“Within ISO days from date of acceptance hereof by the Seller . . . the Seller and Purchaser are required and agree to make full settlement in accordance with the terms hereof. If the Purchaser shall fail to make full settlement, the deposit herein provided for may be forfeited at the option of the Seller, in which event the Purchaser shall be relieved from further liability hereunder ... .” (emphasis added).

Beginning in May, String made frequent visits to the building site to inspect the progress of construction. Observing no evidence of activity, he checked with the county authorities, and also examined the land records at the court house. From these inquiries he learned, on June 18, that neither a building permit had been issued nor a construction loan recorded. Armed with this information, he directed his attorney to write a letter requesting the return of his deposit. On June 21, his attorney wrote to Steven as follows:

“According to the contract, the seller is to complete improvements on the lot and make settlement before August 28, 1971, which is obviously impossible because to date, there is not even a building permit issued.
“ . . . [T]he Strings obtained a mortgage loan commitment from Standard Savings and Loan Association, which commitment expires August 20, 1971, and has already cost the Strings $427.00, which the lender refuses to return.
“Since it is impossible for your principal to comply with its contract to deliver the premises on *572 or before August 28, 1971, we demand refund of the $1,000.00 deposit and declare the contract of August 28, 1971, [sic] breached and null o,nd void.” (emphasis added).

Steven’s attorney replied on July 16,1971:

“Contrary to your letter, we understand that a building permit has been issued on the premises and a foundation installed. Steven hopes to have the residence complete by the anticipated date even though there have been unforeseen delays encountered. In the event that it is not complete in time we understand Standard Savings will extend their loan commitment accordingly.
“We also understand that the purchasers have simply had a change of heart, which is not sufficient cause for cancellation of their contract. If this is in fact the case, Steven will consider forfeiture of the deposit as its sole remedy under .. . the contract and treat your letter as an anticipatory breach thereof... .”

On August 18, Steven’s attorney again wrote:

“Having received no reply to my letter of July 16, 1971, in response to yours reference the above, Steven Development Corporation has elected to treat your letter, particularly the last paragraph thereof, as an anticipatory breach of the contract between the parties.
“Accordingly, Steven hereby declares your clients’ deposit forfeited under paragraph six (6) of said contract and thereby, in consideration of such forfeiture, relieves your clients from further liability thereunder.”

It appears to be conceded that construction of the house did commence on or about July 2, the date on which the building permit was issued. Photographs taken by String at three stages during August were admitted into evidence. At *573 the beginning of the month, there existed a frame structure “under roof” and no garage. A picture taken on August 28 reflects substantial, if not dramatic, progress. For example, the house appears to have been completely “bricked up” and the garage completed.

After Steven refused to return the deposit and reimburse the loan commitment fee, the scene shifted to the circuit court. There, the evidence disclosed that following execution of the contract, which specified that the house was to be built in accordance with attached plans, String had sought a number of changes in design, including some which were structural. The only witness to testify at the trial, other than String, was George Young (Young), an officer of Steven; he was called by the plaintiff. He testified, without contradiction, that even as late as May 11, String was still “asking for changes in his home.” Young said that these changes, which he characterized as major, delayed the commencement of construction by at least one month and, thereby, Steven’s ability to complete the house in the specified period of time.

There was also testimony by Young that after receiving the letter of June 21 declaring the contract “null and void,” Steven relaxed its schedule for completing the house; and, anticipating that a substituted purchaser might not desire the changes initiated by String, diverted its immediate efforts to other houses under construction. But for the changes, according to Young, the house could have been “just about” completed by the end of August. He said that even with the delay attributable to the design changes, if there had been no “breach” by String, the house would have been completed within a reasonable time following expiration of the 130 days designated in the contract. Indeed, he testified that the house could have been built in a total of 90 days which, even with the changes and the July starting date, would have meant a delay of only one month beyond the 130 days. As evidence of Steven’s ability to do so, Young pointed to other projects in which it had completed houses within 90 days, in some cases even under unfavorable weather conditions.

*574 In his trial testimony, String revealed for the first time that the 130-day period specified in the contract:

“was very important in that it made the contract termination date or completion date within fifteen days of the time school was starting. That gave me a reasonable time to get a family in and settled, after they had been settled and having to move from California. I turned down or ceased negotiations with the other builders before this. They did not promise me occupancy by the time school started. That was the important factor in my purchase of a house.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weaver v. ZeniMax Media, Inc.
923 A.2d 1032 (Court of Special Appeals of Maryland, 2007)
8621 Ltd. Partnership v. LDG, Inc.
900 A.2d 259 (Court of Special Appeals of Maryland, 2006)
Thelen v. Massachusetts Mutual Life Insurance
111 F. Supp. 2d 688 (D. Maryland, 2000)
Choice Hotels International, Inc. v. Madison Three, Inc.
83 F. Supp. 2d 602 (D. Maryland, 2000)
Markey v. Wolf
607 A.2d 82 (Court of Special Appeals of Maryland, 1992)
Himelfarb v. American Express Co.
484 A.2d 1013 (Court of Appeals of Maryland, 1984)
Joppa Sand & Gravel Corp. v. Epstein & Sons, Inc.
382 A.2d 1086 (Court of Special Appeals of Maryland, 1978)
Stefanowicz Corp. v. Harris
373 A.2d 54 (Court of Special Appeals of Maryland, 1977)
C. W. Blomquist & Co. v. Capital Area Realty Investors Corp.
311 A.2d 787 (Court of Appeals of Maryland, 1973)
Chirichella v. Erwin
310 A.2d 555 (Court of Appeals of Maryland, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
307 A.2d 713, 269 Md. 569, 1973 Md. LEXIS 853, Counsel Stack Legal Research, https://law.counselstack.com/opinion/string-v-steven-development-corp-md-1973.