Straw v. Temple

159 P. 44, 48 Utah 258, 1916 Utah LEXIS 26
CourtUtah Supreme Court
DecidedJuly 10, 1916
DocketNo. 2858
StatusPublished
Cited by4 cases

This text of 159 P. 44 (Straw v. Temple) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Straw v. Temple, 159 P. 44, 48 Utah 258, 1916 Utah LEXIS 26 (Utah 1916).

Opinion

FRICK, J.

The plaintiff commenced this action to recover an alleged balance due him from the defendants upon an oral subcontract, wherein plaintiff agreed to and did perform certain work for the defendants. The plaintiff, as a first cause of action, alleged that on the 26th day of October, 1913, he and the defendants entered into an oral contract—

“whereby this plaintiff agreed to construct that portion of the roadbed of said Salt Lake & Utah Railroad Company lying between stations 277 and 282 in mile 26, according to the engineer’s survey of the Salt Lake and Utah Railroad Company, and to complete and make ready the said grade or roadbed for the laying of track thereon; and said Yosburg and Carlson, in consideration of the work so to be performed and completed by said plaintiff, agreed to pay to plaintiff at the time of the completion of said work, the sum of forty cents ($.40) per cubic yard, for all loose dry material removed in the execution of said work, and, if in the prosecution of said work the plaintiff should encounter wet material, then and in that event he was to prosecute said work to completion upon what is known as a force account, that is to say, the said plaintiff was to be paid at the rate of five dollars ($5) per day for each man and team, plus ten per cent for wear and tear on the tools and equipment and $2.50 for each laborer doing common labor; in other words, the plaintiff was to be paid at the rate [260]*260of $5.50 per day for each man and team and $2.50 as aforesaid, for each laborer doing common labor, the plaintiff to furnish, while doing work under the force account, supplies and food for his horses and men at his own cost and expense. ”

Plaintiff further alleged' that he commenced work on the date aforesaid and completed the work on the 10th day of December, 1913; that in completing said work he removed 10,516.5 cubic yards of dry material, and that, in addition thereto, he removed a certain quantity of wet material; that for the removal of dry material he, under the terms of the contract, was entitled to the sum of $4,206.60, and for the removal of the wet material the further sum of $1,914.00 “plus ten per cent”; that there was a balance due him at the commencement of the action, upon the contract aforesaid, amounting to the sum of $4,698.20. As a second cause of action plaintiff alleged the defendants owed him a balance of $141.30 for the use of his teams, etc. The defendants answered the complaint, and, in answer to the first cause of action, after admitting that they had entered into a contract with the plaintiff to do certain excavation work, they set forth the terms and conditions'of that contract in the following words:

“That the terms, conditions and stipulations of the contracts between the Inter-Urban Construction Company and the Reynolds-Ely Construction Company and the Reynolds-Ely Construction Company and these defendants covering the said work (the said two contracts being identical as to terms except as to price per cubic yard and amount), all of which terms, conditions and stipulations plaintiff knew and understood, were adopted and made a part of the said agreement entered into between these defendants and plaintiff herein, except that these defendants were to pay plaintiff the sum of 40 cents per cubic yard for material removed in the course of said work, and that said work so undertaken by plaintiff was to be completed by November 15, 1913. ’ ’

Defendants denied that plaintiff had removed the amount of dry material claimed by him, and averred that he had removed only 5,140.1 cubic yards of dry material, and further averred that he had removed no wet material at all as defined by the [261]*261terms and specifications of the contract. Defendants admitted that there was a balance dne npon the first canse of action amounting to $208.80 and no moré. They also admitted that there was a balance dne on the second canse of action amounting to $17.80 and no more. The defendants also set up a counterclaim against the plaintiff for damages, but that is not material here.

The defendants were subcontractors under the contractors’ names in their answer and they in turn sublet the work in question here to the plaintiff. A trial to a jury resulted in a •verdict for the plaintiff in the sum of $1,135.78 on the first cause of action, and nothing on the second cause of action. Judgment was entered in accordance with the verdict, and the defendants appeal.

While defendants’ counsel have assigned a large number of errors, yet in their brief they have grouped them all under a few heads. We shall consider only those assignments which are deemed material.

1 The assignments we shall consider first relate to alleged errors in the admission of evidence. In considering these alleged errors we shall not refer to the many questions, rulings, and exceptions, since the several rulings must all be controlled by one general principle. It will be observed that the plaintiff declared upon an oral contract, wherein he alleged that he had agreed to construct a certain portion of a certain railroad “grade or roadbed,” and that in doing that work he was to receive forty cents for every cubic yard of “loose dry material” removed by him and a fixed per diem for removing wet material, etc. No specific terms or conditions of the contract are pleaded. The defendants in their answer, however, specifically set forth that “the terms, conditions, and stipulations” of the oral contract were to be the same as those mentioned in certain contracts to which special reference was made. In other words, “the terms, conditions, and stipulations” that were contained in the contracts referred to, the defendants claimed, were in fact adopted by the plaintiff and the defendants as part of the oral contract sued on. At the trial plaintiff testified in general terms what, according to his version of the oral contract, was due him [262]*262from the defendants thereunder, both for removing' dry material and wbat he contended constituted wet material. It is, however, insisted that, under the terms and stipulations of the contracts referred to in their answer, plaintiff did not remove any material which fell within what is denominated “wet material” under those contracts, and hence was not entitled to the amount claimed by him upon that score, or to any amount. For the purpose of proving their claim in that regard counsel for defendants, in various ways, attempted to introduce the contracts and specifications pleaded in their answer. Plaintiff’s counsel, however, objected to the proffered evidence upon the ground that the contracts referred to were between other parties, and hence were “immaterial and irrelevant.” The court, it seems, adopted the view of plaintiff’s counsel and excluded the proffered evidence in whatever form it was offered.. Some idea of the theory upon which the district judge excluded the proffered evidence can best be gleaned from what is said in ruling upon the question. -He said:

“Now, this offer which is now made 'of certain matters in the document marked for identification as ‘Defendants’ Exhibit 16, ’ in the first place, could not bind the plaintiff in this case, because it could not be considered as an admission. There is an entirely different privy between the parties to this document and the parties in this action, and then the record further discloses that this witness did not read this contract and does not know what it contains. The objection is sustained.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peterson v. Sevier Valley Canal Co.
116 P.2d 578 (Utah Supreme Court, 1941)
Ward v. Ward
85 P.2d 635 (Utah Supreme Court, 1938)
Utah Lead Co. v. Piute County
65 P.2d 1190 (Utah Supreme Court, 1937)
Dashnea v. Panhandle Lumber Co., Ltd
64 P.2d 390 (Idaho Supreme Court, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
159 P. 44, 48 Utah 258, 1916 Utah LEXIS 26, Counsel Stack Legal Research, https://law.counselstack.com/opinion/straw-v-temple-utah-1916.