Stout v. North American Rail Group, Ca2006-10-286 (9-24-2007)

2007 Ohio 4971
CourtOhio Court of Appeals
DecidedSeptember 24, 2007
DocketNo. CA2006-10-286.
StatusPublished
Cited by1 cases

This text of 2007 Ohio 4971 (Stout v. North American Rail Group, Ca2006-10-286 (9-24-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stout v. North American Rail Group, Ca2006-10-286 (9-24-2007), 2007 Ohio 4971 (Ohio Ct. App. 2007).

Opinion

OPINION
{¶ 1} In this breach of contract action, defendants-appellants, North American Rail Group, et al., appeal a decision of the Butler County Court of Common Pleas granting summary judgment to plaintiffs-appellees, Frederick L. Stout, et al. For the reasons outlined below, we affirm the decision of the trial court.

{¶ 2} On June 22, 2004, the parties entered into an agreement whereby appellants agreed to purchase all the issued and outstanding capital stock in three railway corporations *Page 2 owned by appellees for $1,500,000 ("Purchase Agreement"). On July 16, 2004, the parties amended the Purchase Agreement to provide an extended closing date and a revised purchase price of $1,570,000 ("Amended Purchase Agreement"). Under the Amended Purchase Agreement, $750,000 of the purchase price was to be paid at closing and the remaining $820,000 would be the subject of a promissory note payable before July 24, 2004. Appellants executed the promissory note on the same day as the Amended Purchase Agreement. Pursuant to the Amended Purchase Agreement, appellant Gabriel Hall, president of North American Rail Group, personally guaranteed the promissory note in writing.

{¶ 3} On September 3, 2004, the parties agreed to extend the due date on the promissory note. On October 13, 2004, the parties executed an agreement whereby appellants arranged to purchase two locomotives from appellees. There appears to be a dispute regarding whether appellants' deadline for payment on the promissory note was extended one more time following the September 3 extension, but the conflict is of no consequence in this appeal. Appellants do not deny that they eventually defaulted under the above agreements (collectively, "the contract") by failing to pay all monies due to appellees.

{¶ 4} After failing to receive full payment under the contract, appellees filed suit in January 2005 for breach of contract and breach of promissory note. The complaint sought damages totaling $94,000 plus interest, as well as costs and attorney fees. Appellees filed a motion for summary judgment in November 2005, which the trial court granted upon appellants' failure to timely respond. Appellants then filed a motion for relief from judgment, which the trial court granted. Appellants thereafter filed a memorandum in opposition to appellees' motion for summary judgment. In September 2006, following a hearing, the trial court again granted summary judgment to appellees in the amount sought. Appellants timely appeal, raising one assignment of error. *Page 3

{¶ 5} We review a trial court's decision on summary judgment de novo.Burgess v. Tackas (1998), 125 Ohio App.3d 294, 296. Summary judgment is proper where (1) there are no genuine issues of material fact, (2) the moving party is entitled to judgment as a matter of law, and (3) reasonable minds can only come to a conclusion adverse to the nonmoving party, construing the evidence most strongly in that party's favor. Civ.R. 56(C). See, also, Harless v. Willis Day Warehousing Co. (1978),54 Ohio St.2d 64, 66. The moving party bears the initial burden of informing the court of the basis for the motion, and demonstrating the absence of a genuine issue of material fact. Dresher v. Burt,75 Ohio St.3d 280, 293, 1996-Ohio-107. If the moving party meets its burden, the nonmoving party has a reciprocal burden to set forth specific facts showing a genuine issue for trial. Id. We are mindful of these burdens in reviewing appellants' single assignment of error:

{¶ 6} "THE TRIAL COURT ERRED TO THE PREJUDICE OF DEFENDANTS-APPELLANTS BY GRANTING PLAINTIFFS-APPELLEES' MOTION FOR SUMMARY JUDGMENT."

{¶ 7} Appellants argue that the trial court improperly awarded summary judgment to appellees because appellants were fraudulently induced into entering into the contract. Appellants claim that during the negotiation period, appellees stated that railway clients General Mills and Meridian would continue to ship their respective products by rail, when in fact appellees knew that both companies intended to discontinue rail service. Appellants also claim that appellees informed them that all old cross-ties and waste oil had been removed from the property, when this was not the case. As a result of their misled beliefs, appellants reason that there was no meeting of the minds and therefore the contract is void.

{¶ 8} Initially, we note that appellants did not properly assert any fraud claims. Appellants' answer averred that "[p]laintiffs made misrepresentations that are material to the contract and as a result of misrepresentations of material facts, the contract is null and void." *Page 4 Because allegations of fraud must be pled with particularity, this statement in appellants' answer was insufficient to establish a fraud defense. See Civ.R. 9(B).

{¶ 9} The circumstances constituting fraud normally include the time, place and content of the false representation, the fact misrepresented, and the nature of what was obtained or given as a consequence of the fraud. F J Roofing Co. v. McGinley Sons, Inc. (1987),35 Ohio App.3d 16, 17. Generally, a pleading must be sufficiently particular to apprise the opposing party of the act which is the subject of the fraud claim, and to enable the opposing party to prepare an effective defense.Smith v. Littrell, Preble App. No. CA2001-02-004, at 10, 2001-Ohio-8642. Clearly, the above-quoted portion of appellants' answer falls far short of the particularity requirement imposed by Civ.R. 9(B). Neither does the remainder of the answer provide any specific information that would sustain a fraud claim.

{¶ 10} Appellants could have set forth a fraud defense either by pre-pleading motion pursuant to Civ.R. 12(B), affirmative defense in a responsive pleading pursuant to Civ.R. 8(C), or amended answer pursuant to Civ.R. 15. See Spence v. Liberty Twp. Trustees (1996),109 Ohio App.3d 357, 362. Appellants also could have brought a counterclaim asserting fraud pursuant to Civ.R. 13. Appellants' failure to raise the issue by any of these accepted methods results in a waiver of the defense. Spence at 362.

{¶ 11} Appellants' alternate argument on appeal is that appellees' alleged misrepresentations, if not severe enough to amount to fraud, amount to negligent misrepresentation. In support, appellants' brief cites the standard for the tort of negligent misrepresentation.1 Assuming, arguendo, that the above-quoted portion of appellants' *Page 5 answer was sufficient to preserve a negligent misrepresentation claim, this argument fails because negligent misrepresentation cannot be used to disaffirm a contract in the manner attempted by appellants.

{¶ 12} The tort of negligent misrepresentation provides a vehicle by which a party may recover economic damages that arise from the breach of a contractual duty. Westfield Ins. Co. v. HULS Am., Inc. (1998),128 Ohio App.3d 270

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charlie's CDJR, L.L.C. v. Charlie's Toledo, Inc.
2026 Ohio 18 (Ohio Court of Appeals, 2026)
Turner v. Salvagnini America, Inc., Ca2007-09-233 (7-21-2008)
2008 Ohio 3596 (Ohio Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 4971, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stout-v-north-american-rail-group-ca2006-10-286-9-24-2007-ohioctapp-2007.