Storms, Inc. v. Mathy Construction Company

Court of Appeals of Minnesota·Decided November 30, 2015·No. A15-484·Unpublished

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA

IN COURT OF APPEALS

A15-0484

Storms, Inc.,

Appellant,

vs.

Mathy Construction Company, Respondent.

Filed November 30, 2015

Affirmed in part, reversed in part, and remanded Worke, Judge

Houston County District Court File No. 28CV13235

Scott M. Flaherty, Daniel N. Moak, Cyrus C. Malek, Jordan L. Weber, Briggs and Morgan, P.A., Minneapolis, Minnesota; and

Michael A. Murphy, Hammel & Murphy, P.L.L.P., Caledonia, Minnesota (for appellant)

Justin W. Peterson, James Naugler (pro hac vice), Moen Sheehan Meyer, Ltd., LaCrosse, Wisconsin (for respondent)

Considered and decided by Kirk, Presiding Judge; Worke, Judge; and Smith, Judge.

UNPUBLISHED OPINION

WORKE, Judge This is an appeal from a judgment following a court trial limited to a determination of damages arising out of a highway construction project in which the

district court found that respondent-general-contractor breached its subcontract agreement with appellant-subcontractor. Appellant argues that the district court erred by applying an equitable analysis to determine that appellant was entitled to no damages, rather than awarding damages under the contract. Respondent filed a notice of related appeal arguing that the district court erred by finding that it breached the subcontract agreement. We affirm the district court’s finding that respondent breached the subcontract agreement, but we reverse the district court’s order for no damages based on equity, and remand for a determination of damages under the contract.

FACTS

In January 2011, the Minnesota Department of Transportation (MNDOT) solicited bids for a project to repair portions of Highways 44 and 76 in Houston County. In an effort to secure the contract, respondent Mathy Construction Company solicited bids from subcontractors. In doing so, respondent supplied the prospective subcontractors with a copy of MNDOT’s statement of estimated quantities, which identified the amounts of materials that would be required to perform certain aspects of the project.

Appellant Storms, Inc. submitted a bid to respondent that was calculated based upon the amounts of materials identified in the statement of estimated quantities, and appellant’s bid was successful. Respondent, in turn, secured the general contract with MNDOT. Appellant and respondent subsequently entered into a subcontract agreement on March 22, 2011.

The Highway 44 portion of the project was completed in May 2011, and the Highway 76 portion of the project was completed in August 2011. In January 2012,

respondent sent two requests to MNDOT seeking payment for the work provided based on plan dimension amounts. But because MNDOT miscalculated the amount of materials needed for the subcontract, the planned quantity amounts for these projects exceeded the actual amounts necessary to complete the projects. Consequently, MNDOT issued a change order on May 11, 2012, reducing the amount owed by MNDOT to appellant by $327,064.42.

In March 2013, appellant filed suit against respondent for breach of the parties’

subcontract agreement. In addition to its costs and attorney fees, appellant sought damages in the amount of $327,064.42, which was the difference between the planned quantity amounts set forth in the subcontract agreement and the amount appellant was actually paid. Respondent denied the allegations, but admitted that appellant was not paid for the planned quantity amounts because MNDOT “issued a change order changing the planned amounts,” which reduced “the contract amount by $327.064.42.” Respondent also declined to implead MNDOT.

Respondent moved for summary judgment arguing that under MNDOT specification 1901, MNDOT had the right, at any time, to make changes to the planned quantities that were incorrectly calculated. Respondent argued that appellant is bound by MNDOT’s changes, therefore there was no breach of the subcontract. Appellant filed a cross motion for summary judgment arguing that MNDOT specification 14021 was

1 Specification 1402.1 provides in relevant part:

[MNDOT] may alter the details of construction as necessary for proper completion of the Project and as desired for reasons of public interest. Alterations may be made at any

applicable. Appellant claimed that respondent breached the subcontract agreement because respondent failed to pay based on the original planned quantities, and failed to follow specification 1402, which requires changes in quantities to be made during the progress of the work. Thus, appellant argued that it was entitled to payment for the plan dimensions as set forth in the original subcontract agreement.

Following a summary-judgment hearing, the district court determined that, under the terms of the subcontract agreement, “any modifications [to the agreement] must be made during the progress of the work.” The district court also determined that MNDOT’s change order occurred nine months after completion of the project, rather than during the progress of work, after respondent had submitted a written demand for payment. Therefore, the district court concluded that respondent breached the subcontract agreement and allowed appellant the “right to seek payment from [respondent] for any amounts that MNDOT has failed to pay.” But the district court concluded that “[a] fact question remains as to the amount of [appellant’s] damages,” and stated that a hearing would be scheduled to determine damages “based on what is just and equitable.”

Appellant moved for amended findings, arguing that, because there was no dispute as to the plan dimensions, it was entitled to judgment in the amount of $327,064.42, the amount unpaid under the original subcontract agreement. Respondent replied with a

time during the progress of the work, but will not involve added work beyond the limitations imposed by law, nor beyond termini of the proposed construction except as may be necessary to satisfactorily complete the Project.

(Emphasis added.)

request to reconsider, supported by the affidavit of MNDOT Project Engineer Mark Anderson. Anderson testified that MNDOT miscalculated the planned quantities and that under specification 1901 he had the authority to summarily change the miscalculated quantities, which he did in the May 2012 change order. Anderson also testified that such changes are not subject to specification 1402, which “applies to situations wherein there are unforeseen changes or abnormalities in the physical conditions at the job site that require the contractor or its subcontractors to perform more or less work or to provide more or less materials than originally called for.” Anderson further testified that, under specification 1903, appellant is entitled to request its fixed costs resulting from the miscalculation, but not its lost profits. The district court denied both parties’ motions.

At the damages hearing, Anderson testified consistent with his affidavit submitted in support of respondent’s request to reconsider. The district court then found that the “parties are bound by the MNDOT specifications.” But the district court found that its “knowledge about the applicability of specification 1402.2 is limited to the testimony of . . . Anderson,” who testified that specification 1402 “only applies to situations of unforeseen or significant changes,” which did not occur in this case. Thus, the district court found that “based on the evidence presented, specification 1402 does not apply.”

Free access — add to your briefcase to read the full text and ask questions with AI

Storms, Inc. v. Mathy Construction Company, (Mich. Ct. App. 2015).

Storms, Inc. v. Mathy Construction Company (Storms, Inc. v. Mathy Construction Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Halla Nursery, Inc. v. City of Chanhassen
781 N.W.2d 880 (Supreme Court of Minnesota, 2010)
United States Fire Insurance Co. v. Minnesota State Zoological Board
307 N.W.2d 490 (Supreme Court of Minnesota, 1981)
Star Centers, Inc. v. Faegre & Benson, L.L.P.
644 N.W.2d 72 (Supreme Court of Minnesota, 2002)
Finke v. State
521 N.W.2d 371 (Court of Appeals of Minnesota, 1994)
ServiceMaster of St. Cloud v. GAB Business Services, Inc.
544 N.W.2d 302 (Supreme Court of Minnesota, 1996)
Peters v. Mutual Benefit Life Insurance Co.
420 N.W.2d 908 (Court of Appeals of Minnesota, 1988)
Kellogg v. Woods
720 N.W.2d 845 (Court of Appeals of Minnesota, 2006)
Paine v. Sherwood
21 Minn. 225 (Supreme Court of Minnesota, 1875)
Roemhildt v. Kristall Development, Inc.
798 N.W.2d 371 (Court of Appeals of Minnesota, 2011)