Storms, Inc. v. Mathy Construction Company

CourtCourt of Appeals of Minnesota
DecidedNovember 30, 2015
DocketA15-484
StatusUnpublished

This text of Storms, Inc. v. Mathy Construction Company (Storms, Inc. v. Mathy Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Storms, Inc. v. Mathy Construction Company, (Mich. Ct. App. 2015).

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA IN COURT OF APPEALS A15-0484

Storms, Inc., Appellant,

vs.

Mathy Construction Company, Respondent.

Filed November 30, 2015 Affirmed in part, reversed in part, and remanded Worke, Judge

Houston County District Court File No. 28CV13235

Scott M. Flaherty, Daniel N. Moak, Cyrus C. Malek, Jordan L. Weber, Briggs and Morgan, P.A., Minneapolis, Minnesota; and

Michael A. Murphy, Hammel & Murphy, P.L.L.P., Caledonia, Minnesota (for appellant)

Justin W. Peterson, James Naugler (pro hac vice), Moen Sheehan Meyer, Ltd., LaCrosse, Wisconsin (for respondent)

Considered and decided by Kirk, Presiding Judge; Worke, Judge; and Smith,

Judge.

UNPUBLISHED OPINION

WORKE, Judge

This is an appeal from a judgment following a court trial limited to a

determination of damages arising out of a highway construction project in which the district court found that respondent-general-contractor breached its subcontract

agreement with appellant-subcontractor. Appellant argues that the district court erred by

applying an equitable analysis to determine that appellant was entitled to no damages,

rather than awarding damages under the contract. Respondent filed a notice of related

appeal arguing that the district court erred by finding that it breached the subcontract

agreement. We affirm the district court’s finding that respondent breached the

subcontract agreement, but we reverse the district court’s order for no damages based on

equity, and remand for a determination of damages under the contract.

FACTS

In January 2011, the Minnesota Department of Transportation (MNDOT) solicited

bids for a project to repair portions of Highways 44 and 76 in Houston County. In an effort

to secure the contract, respondent Mathy Construction Company solicited bids from

subcontractors. In doing so, respondent supplied the prospective subcontractors with a copy

of MNDOT’s statement of estimated quantities, which identified the amounts of materials

that would be required to perform certain aspects of the project.

Appellant Storms, Inc. submitted a bid to respondent that was calculated based upon

the amounts of materials identified in the statement of estimated quantities, and appellant’s

bid was successful. Respondent, in turn, secured the general contract with MNDOT.

Appellant and respondent subsequently entered into a subcontract agreement on March 22,

2011.

The Highway 44 portion of the project was completed in May 2011, and the

Highway 76 portion of the project was completed in August 2011. In January 2012,

2 respondent sent two requests to MNDOT seeking payment for the work provided based on

plan dimension amounts. But because MNDOT miscalculated the amount of materials

needed for the subcontract, the planned quantity amounts for these projects exceeded the

actual amounts necessary to complete the projects. Consequently, MNDOT issued a change

order on May 11, 2012, reducing the amount owed by MNDOT to appellant by

$327,064.42.

In March 2013, appellant filed suit against respondent for breach of the parties’

subcontract agreement. In addition to its costs and attorney fees, appellant sought damages

in the amount of $327,064.42, which was the difference between the planned quantity

amounts set forth in the subcontract agreement and the amount appellant was actually paid.

Respondent denied the allegations, but admitted that appellant was not paid for the planned

quantity amounts because MNDOT “issued a change order changing the planned amounts,”

which reduced “the contract amount by $327.064.42.” Respondent also declined to implead

MNDOT.

Respondent moved for summary judgment arguing that under MNDOT

specification 1901, MNDOT had the right, at any time, to make changes to the planned

quantities that were incorrectly calculated. Respondent argued that appellant is bound by

MNDOT’s changes, therefore there was no breach of the subcontract. Appellant filed a

cross motion for summary judgment arguing that MNDOT specification 14021 was

1 Specification 1402.1 provides in relevant part: [MNDOT] may alter the details of construction as necessary for proper completion of the Project and as desired for reasons of public interest. Alterations may be made at any

3 applicable. Appellant claimed that respondent breached the subcontract agreement

because respondent failed to pay based on the original planned quantities, and failed to

follow specification 1402, which requires changes in quantities to be made during the

progress of the work. Thus, appellant argued that it was entitled to payment for the plan

dimensions as set forth in the original subcontract agreement.

Following a summary-judgment hearing, the district court determined that, under

the terms of the subcontract agreement, “any modifications [to the agreement] must be

made during the progress of the work.” The district court also determined that

MNDOT’s change order occurred nine months after completion of the project, rather than

during the progress of work, after respondent had submitted a written demand for

payment. Therefore, the district court concluded that respondent breached the

subcontract agreement and allowed appellant the “right to seek payment from

[respondent] for any amounts that MNDOT has failed to pay.” But the district court

concluded that “[a] fact question remains as to the amount of [appellant’s] damages,” and

stated that a hearing would be scheduled to determine damages “based on what is just and

equitable.”

Appellant moved for amended findings, arguing that, because there was no dispute

as to the plan dimensions, it was entitled to judgment in the amount of $327,064.42, the

amount unpaid under the original subcontract agreement. Respondent replied with a

time during the progress of the work, but will not involve added work beyond the limitations imposed by law, nor beyond termini of the proposed construction except as may be necessary to satisfactorily complete the Project. (Emphasis added.)

4 request to reconsider, supported by the affidavit of MNDOT Project Engineer Mark

Anderson. Anderson testified that MNDOT miscalculated the planned quantities and that

under specification 1901 he had the authority to summarily change the miscalculated

quantities, which he did in the May 2012 change order. Anderson also testified that such

changes are not subject to specification 1402, which “applies to situations wherein there

are unforeseen changes or abnormalities in the physical conditions at the job site that

require the contractor or its subcontractors to perform more or less work or to provide

more or less materials than originally called for.” Anderson further testified that, under

specification 1903, appellant is entitled to request its fixed costs resulting from the

miscalculation, but not its lost profits. The district court denied both parties’ motions.

At the damages hearing, Anderson testified consistent with his affidavit submitted

in support of respondent’s request to reconsider. The district court then found that the

“parties are bound by the MNDOT specifications.” But the district court found that its

“knowledge about the applicability of specification 1402.2 is limited to the testimony of .

. .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Halla Nursery, Inc. v. City of Chanhassen
781 N.W.2d 880 (Supreme Court of Minnesota, 2010)
United States Fire Insurance Co. v. Minnesota State Zoological Board
307 N.W.2d 490 (Supreme Court of Minnesota, 1981)
Star Centers, Inc. v. Faegre & Benson, L.L.P.
644 N.W.2d 72 (Supreme Court of Minnesota, 2002)
Finke v. State
521 N.W.2d 371 (Court of Appeals of Minnesota, 1994)
ServiceMaster of St. Cloud v. GAB Business Services, Inc.
544 N.W.2d 302 (Supreme Court of Minnesota, 1996)
Peters v. Mutual Benefit Life Insurance Co.
420 N.W.2d 908 (Court of Appeals of Minnesota, 1988)
Kellogg v. Woods
720 N.W.2d 845 (Court of Appeals of Minnesota, 2006)
Paine v. Sherwood
21 Minn. 225 (Supreme Court of Minnesota, 1875)
Roemhildt v. Kristall Development, Inc.
798 N.W.2d 371 (Court of Appeals of Minnesota, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Storms, Inc. v. Mathy Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/storms-inc-v-mathy-construction-company-minnctapp-2015.