Storm Kings, L.L.C. v. Shumaker

2025 Ohio 5845
CourtOhio Court of Appeals
DecidedDecember 31, 2025
Docket31437
StatusPublished

This text of 2025 Ohio 5845 (Storm Kings, L.L.C. v. Shumaker) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Storm Kings, L.L.C. v. Shumaker, 2025 Ohio 5845 (Ohio Ct. App. 2025).

Opinion

[Cite as Storm Kings, L.L.C. v. Shumaker, 2025-Ohio-5845.]

STATE OF OHIO ) IN THE COURT OF APPEALS )ss: NINTH JUDICIAL DISTRICT COUNTY OF SUMMIT )

STORM KINGS LLC C.A. No. 31437

Appellant

v. APPEAL FROM JUDGMENT ENTERED IN THE RICHARD SHUMAKER COURT OF COMMON PLEAS COUNTY OF SUMMIT, OHIO Appellee CASE No. CV-2023-08-2949

DECISION AND JOURNAL ENTRY

Dated: December 31, 2025

SUTTON, Judge.

{¶1} Plaintiff-Appellant Storm Kings, LLC (“Storm Kings”) appeals the judgment of the

Summit County Court of Common Pleas. For the following reasons, this Court affirms.

I.

Relevant Background Information

{¶2} This appeal arises from a contract between Storm Kings and Richard Shumaker

regarding the replacement of Mr. Shumaker’s roof on his home in Tallmadge, Ohio. The roof

replacement occurred over the span of three days in October of 2022. In March of 2023, Storm

Kings placed a mechanic’s lien on Mr. Shumaker’s property which wrongly alleged the last day

of work occurred on January 19, 2023. The mechanic’s lien also alleged Mr. Shumaker owed

Storm Kings $4,617.81 for work done on replacing the roof. Upon receiving a letter regarding the

mechanic’s lien from Mr. Shumaker’s attorney, Storm Kings removed the lien. 2

{¶3} Storm Kings then filed a lawsuit against Mr. Shumaker alleging breach of contract

and unjust enrichment. The complaint alleged Mr. Shumaker owed Storm Kings $4,617.81. Mr.

Shumaker filed an answer and counterclaim alleging Storm Kings negligently installed the

shingles on the roof, damaged one of his air conditioning units, siding, screens, and driveway

during the roof installation, and filed a mechanic’s lien with false information causing Mr.

Shumaker to incur attorney fees.

{¶4} The matter proceeded to a bench trial before a magistrate of the trial court. After a

two day trial, wherein several witnesses testified for both Storm Kings and Mr. Shumaker, the

magistrate issued a decision stating, in part:

On Counts One and Two of Defendant Richard Shumaker’s Counterclaim, the Magistrate finds in favor of Defendant Richard Shumaker and awards $17,194.62. On Count One of Plaintiff Storm Kings’ Complaint, the Magistrate finds in favor of Storm Kings and awards $4,617.81. Count two of Plaintiff’s Complaint is dismissed. [Judgment] is granted in favor of Defendant Richard Shumaker and against Plaintiff Storm Kings, LLC in the amount of $12,576.81, with interest at the statutory rate from the date of judgment. Costs to Plaintiff Storm Kings, LLC.

{¶5} Storm Kings filed timely objections to the magistrate’s decision, and the trial court

overruled each of Storm Kings’ 15 objections. In so doing, the trial court stated, in relevant part:

The court has taken an independent review as to the Magistrate’s Decision and all objected matters, and finds that the Magistrate has proper[ly] determined the factual issues and appropriately applied the law. The court finds all of the Magistrate’s findings of fact to be reasonable and supported by the evidence. The court further finds all of the legal conclusions to be correct.

The trial court then issued judgment in favor of Mr. Shumaker and against Storm Kings in the

amount of $12,576.81, plus interest and costs.

{¶6} Storm Kings appealed raising nine assignments of error for this Court’s review.

We group certain assignments of error and discuss certain assignments of error out of order to

facilitate our analysis. 3

II.

Standard of Review

{¶7} “Although the trial court must conduct an independent review of objections to a

magistrate’s decision, see Civ.R. 53(D)(4)(d), this Court’s standard of review is more deferential.”

Wilson v. Wilson, 2008-Ohio-6431, ¶ 12 (9th Dist.). This Court generally reviews the trial court’s

ruling on objections, and its decision to adopt the magistrate’s decision, for an abuse of discretion.

Id. Under this standard, we must determine whether the trial court’s decision was arbitrary,

unreasonable, or unconscionable. Blakemore v. Blakemore, 5 Ohio St.3d 217, 219 (1983).

{¶8} In reviewing a trial court’s ruling on objections to a magistrate’s decision, “we

consider the trial court’s action with reference to the nature of the underlying matter.” Tabatabai

v. Tabatabai, 2009-Ohio-3139, ¶ 18 (9th Dist.).

ASSIGNMENT OF ERROR I

THE TRIAL COURT ERRED AS A MATTER OF LAW BY NOT AWARDING [STORM KINGS] PREJUDGMENT INTEREST PURSUANT TO R.C. 1343.03 ON THE COMPANY’S BREACH OF CONTRACT CLAIM.

{¶9} In its first assignment of error, Storm Kings argues the trial court erred as a matter

of law in failing to award Storm Kings prejudgment interest on its breach of contract claim.

Specifically, Storm Kings claims it should have received prejudgment interest on the trial court’s

award of $4,617.81 for its breach of contract claim, which offset Mr. Shumaker’s award of

$17,194.62 for his counterclaims, for an aggregate judgment in favor of Mr. Shumaker in the

amount of $12,576.81. For the following reasons, we are not persuaded by Storm Kings’

arguments. 4

{¶10} In L.A. Gross & Sons, Inc. v. Parisi, 66 Ohio App.3d 697, 700 (9th Dist. 1990), this

Court explained the interplay, regarding prejudgment interest, between an award of damages to a

plaintiff and a counterclaimant in the same lawsuit. This Court stated:

While an unliquidated counterclaim does not denude the primary claim of its liquidity, it can reduce the amount upon which the interest is calculated. A counterclaim reduces the amount due on the primary claim when the counterclaim is based upon defective workmanship or other defective performance by the plaintiff of the contract on which the liquidated claim is based. Such a counterclaim is regarded as constituting either a reduction in the amount due the plaintiff or a payment to him. The plaintiff receives interest on the balance only, for he was deprived of this amount during the pendency of the litigation.

(Internal citations omitted.)

{¶11} Here, in denying Storm Kings’ objection to the magistrate’s decision on this

issue, the trial court stated, “[t]he court agrees with Mr. Shumaker[.] The Magistrate did

not issue a net judgment in favor of Storm Kings. Therefore, [prejudgment] interest is not

appropriate.”

{¶12} As such, because the award to Mr. Shumaker of $17,194.62 reduced the net

award in favor of Storm Kings to $0.00, with a net judgment in favor of Mr. Shumaker in

the amount of $12,576.81, the trial court did not err in awarding no prejudgment interest

to Storm Kings.

{¶13} Accordingly, Storm Kings’ first assignment of error is overruled.

ASSIGNMENT OF ERROR II

THE TRIAL COURT ERRED AS A MATTER OF LAW DETERMINING THAT [STORM KINGS] WAS NOT A “PREVAILING PARTY.” 5

ASSIGNMENT OF ERROR III

THE TRIAL COURT ABUSED ITS DISCRETION BY NOT DETERMINING THAT THE MAGISTRATE’S DECISION WAS AMBIGUOUS STATING “COSTS TO PLAINTIFF STORM KINGS, LLC.”

Prevailing Party and Costs

{¶14} The premise of Storm Kings’ second and third assignments of error is that as a

“prevailing party” in this lawsuit, it should have been awarded costs.

{¶15} Civ.R. 54(D) states, “[e]xcept when express provision therefor is made either in a

statute or in these rules, costs shall be allowed to the prevailing party unless the court otherwise

directs.” In Vance v. Roedersheimer, 64 Ohio St.3d 552, 555 (1992), the Supreme Court of Ohio

discussed its interpretation of Civ.R. 54(D) regarding costs. The Vance Court stated:

Our interpretation of Civ.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hutta v. Hutta
2011 Ohio 3041 (Ohio Court of Appeals, 2011)
Waugh v. Chakonas
2011 Ohio 2764 (Ohio Court of Appeals, 2011)
L.A. Gross & Sons, Inc. v. Parisi
586 N.E.2d 142 (Ohio Court of Appeals, 1990)
Wilson v. Wilson, 24245 (12-10-2008)
2008 Ohio 6431 (Ohio Court of Appeals, 2008)
Hagemeyer v. Sadowski
621 N.E.2d 707 (Ohio Court of Appeals, 1993)
Rieger v. Giant Eagle, Inc. (Slip Opinion)
2019 Ohio 3745 (Ohio Supreme Court, 2019)
O'Brien v. Angley
407 N.E.2d 490 (Ohio Supreme Court, 1980)
Blakemore v. Blakemore
450 N.E.2d 1140 (Ohio Supreme Court, 1983)
Vance v. Roedersheimer
597 N.E.2d 153 (Ohio Supreme Court, 1992)
Roth v. Tokar Tower Office Condominiums Unit Owners' Assn. Inc.
2023 Ohio 279 (Ohio Court of Appeals, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2025 Ohio 5845, Counsel Stack Legal Research, https://law.counselstack.com/opinion/storm-kings-llc-v-shumaker-ohioctapp-2025.