Stonebrook Dev., LLC v. Matthews Bros. Constr. Co.

985 So. 2d 960, 2007 WL 3037259
CourtCourt of Civil Appeals of Alabama
DecidedOctober 19, 2007
Docket2060419
StatusPublished
Cited by2 cases

This text of 985 So. 2d 960 (Stonebrook Dev., LLC v. Matthews Bros. Constr. Co.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stonebrook Dev., LLC v. Matthews Bros. Constr. Co., 985 So. 2d 960, 2007 WL 3037259 (Ala. Ct. App. 2007).

Opinion

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 962

The defendant/counterplaintiff Stone-brook Development, L.L.C. ("Stone-brook"), appeals a judgment entered following the second bench trial of this action, and the plaintiff/counterdefendant Matthews Brothers Construction Company, Inc. ("Matthews Brothers"), cross-appeals. We affirm in part, reverse in part, and remand with instructions.

This is the second time these parties have been before this court. An appeal by Matthews Brothers following the entry of a judgment after the first bench trial resulted in this court's decision in Matthews Brothers Construction Co. v.Stonebrook Development, L.L.C., 854 So.2d 573 (Ala.Civ.App. 2001), aff'd, Ex parte Stonebrook Development,L.L.C., 854 So.2d 584 (Ala. 2003).

Factual Background
On June 1, 1994, Stonebrook entered into a written contract with Matthews Brothers in which Matthews Brothers agreed to build the roads in a residential subdivision in Elmore County in accordance with plans and specifications prepared by Bill N. Sanford and Sanford, Bell Associates, Inc. ("SB"), for a total price of $203,878.08. The contract required Matthews Brothers to begin the work on June 11, 1994, and to complete the work by August 11, 1994. In addition, the contract contained the following material provisions:

"5. Retainage: 10% retainage shall be withheld from periodic payments [to Matthews Brothers] until final inspection [and] approval by Elmore County Commission.

*Page 963
"After final inspection and approval by the County Engineer, then the balance of contract payments plus all retainage withheld shall be due by the 10th of the following month.

. . . .

"8. Liquidated Damages: [Matthews Brothers] is aware of the critical time schedule for completion of the contract work and hereby agrees to reimburse [Stonebrook] for damages caused by not completing the Contract work specified within the time period shown hereon. The amount of damages shall be calculated at a rate equal to 1/2 of one percent of the total contract price, multiplied by the number of days [Matthews Brothers] has exceeded the completion time schedule shown in Paragraph 7. "9. Time Extensions: Contract time extensions shall be granted by [Stone-brook] for delays caused by `Act of God' including rain falls prohibiting 6 hrs. of work in one calendar day, or other delays caused by [Stonebrook] o[r] other parties not in the employ or contractual control of [Matthews Brothers]. [Matthews Brothers] must request time extensions within 2 weeks of occurrence of the loss of time. The [project] Engineer shall be the final authority on granting or denying requests for time extensions and such extensions shall be [granted or denied by] written notification within 2 weeks of receipt of request or said request shall be assumed to be accepted."

Sanford, who was a principal in both Stonebrook and SB, served as the project engineer.

Matthews Brothers did not complete the work required by the contract until sometime in December 1994. Thereafter, Stonebrook paid Matthews Brothers the 10% retainage Stonebrook had been withholding from its payments to Matthews Brothers. In 1995, Matthews Brothers returned to the job at Stonebrook's request and made repairs to the roads. In February 1997, Matthews Brothers sent Stonebrook a bill in the amount of $42,049.96 for the repair work it had performed in 1995. Stonebrook refused to pay this bill because, Stonebrook said, Matthews Brothers had warranted that its work under the contract was free from defects and the repair work was necessary because of defects in Matthews Brothers' work.

Procedural History
In 1997, Matthews Brothers sued Stone-brook, seeking to recover the $42,049.96 Matthews Brothers had billed Stonebrook for the 1995 repair work. Matthews Brothers claimed that it was entitled to the money under theories of open account, account stated, and work and labor done. Stonebrook denied liability and asserted counterclaims of breach of contract and breach of warranty. Under its breach-of-contract counterclaim, Stonebrook sought to recover liquidated damages for Matthews Brothers' failure to complete its work under the contract by August 11, 1994. In response to the counterclaims, Matthews Brothers denied liability and asserted a third-party claim against Sanford and SB. Matthews Brothers' third-party claim alleged that, because Sanford and SB had been negligent in preparing the plans and the specifications for the roads that Matthews Brothers had to build, Matthews Brothers was entitled to a judgment against Sanford and SB reimbursing Matthews Brothers for any judgment against it under Stonebrook's counterclaims.

The trial court entered a Rule 12(b)(6), Ala. R. Civ. P., dismissal of Matthews Brothers' third-party claim against Sanford and SB; entered a partial summary judgment in favor of Stonebrook on its breach-of-contract counterclaim and awarded it liquidated damages in the *Page 964 amount of $155,966.73 under that counter-claim; and, following a bench trial, entered a judgment finding in favor of Stonebrook with respect to Matthews Brothers' claims against Stonebrook, finding in favor of Stonebrook with respect to Stonebrook's breach-of-warranty counterclaim, and awarding Stonebrook compensatory damages in the amount of $27,604.50 under its breach-of-warranty counterclaim. Matthews Brothers then appealed.

In Matthews Brothers Construction Co. v. StonebrookDevelopment, L.L.C., supra, this court reversed the dismissal of Matthews Brothers' third-party claim, reversed the partial summary judgment in favor of Stonebrook on its breaeh-of-contract counterclaim, reversed the judgment finding in favor of Stonebrook with respect to its breach-of-warranty counterclaim and Matthews Brothers' claims against Stone-brook, and remanded the action with instructions to the trial court to conduct a new trial.

On remand, the trial judge who had presided in the first bench trial recused himself, and a new trial judge was assigned. Upon the motion of Stonebrook, the trial judge dismissed Stonebrook's breach-of-warranty counterclaim. The trial judge then held a bench trial at which he received evidence ore tenus. On June 29, 2005, the trial judge entered the following interlocutory judgment:

"Upon hearing the evidence on the original complaint by Matthews Brothers Construction as against Stonebrook Development and upon the Defendant Stonebrook Development as against Matthews Brothers Construction on the Counter-claim, Breach of Contract claim, this Court hereby finds judgment in favor of Stonebrook Development, LLC and against Matthews Brothers Construction, Inc. in the sum of $27,500.00 plus cost of Court."

Although the June 29, 2005, judgment was not a final judgment because it did not adjudicate Matthews Brothers' third-party claim against Sanford and SB, Matthews Brothers appealed the June 29, 2005, judgment to this court, and Stonebrook cross-appealed. This court dismissed that appeal and cross-appeal because they were based on a nonfinal judgment. On January 11, 2007, the trial court entered the following judgment:

"The judgment of June [29], 2005 is set aside and the following is substituted:

"1. Judgment is hereby entered in favor of Stonebrook Development, LLC and against Matthews Brothers Construction, Inc. in the sum of $27,500.00 plus cost of Court on the counter-claim for breach of contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Enriquez v. Kokomo Properties, LLC
39 So. 3d 198 (Court of Civil Appeals of Alabama, 2009)
Southern Electric Corp. v. Utilities Board of Foley
643 F. Supp. 2d 1302 (S.D. Alabama, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
985 So. 2d 960, 2007 WL 3037259, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stonebrook-dev-llc-v-matthews-bros-constr-co-alacivapp-2007.