Stone & Webster, Inc. v. Georgia Power Company

779 F.3d 614, 414 U.S. App. D.C. 281, 2015 U.S. App. LEXIS 3683, 2015 WL 1020208
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 10, 2015
Docket13-7151
StatusPublished
Cited by6 cases

This text of 779 F.3d 614 (Stone & Webster, Inc. v. Georgia Power Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stone & Webster, Inc. v. Georgia Power Company, 779 F.3d 614, 414 U.S. App. D.C. 281, 2015 U.S. App. LEXIS 3683, 2015 WL 1020208 (D.C. Cir. 2015).

Opinion

Opinion for the Court filed by Senior Circuit Judge RANDOLPH.

RANDOLPH, Senior Circuit Judge:

This is an appeal from the judgment of the district court, Judge Kollar-Kotelly, dismissing a complaint filed in the United States District Court for the District of Columbia in favor of a complaint filed in the federal district court for the Southern District of Georgia. The plaintiff in the D.C. action is the defendant in the Georgia action, and vice versa. Each suit is, to a large extent, the mirror image of the other. Jurisdiction rests on diversity of citizenship; 28 U.S.C. § 1332. There is no contention that both suits should proceed. The question is which complaint—the one filed in D.C. or the one filed in Georgia—should go forward. The district judge, in a thorough and closely reasoned opinion, determined that the D.C. action should be dismissed and that the Georgia action should proceed.

The dispute arises under a contract, signed in 2008, for the design and construction of two nuclear electrical generating units at a power plant in Georgia. Stone & Webster, Inc., and another company agreed to build the units for Georgia Power Company and others. The contract, which specifies that it is to be governed by Georgia law, sets a fixed price for the work but includes reimbursement for some additional costs.

Regulatory requirements of the United States Nuclear Regulatory Commission delayed the project and imposed additional costs. Stone & Webstér sought payment for the added expenses. Georgia Power denied that the contract made it responsible for the extra charges.

The contract includes dispute resolution procedures. The parties must first meet to seek a resolution. If this does not end the dispute within thirty days, the parties are to engage in mediation. For claims of more than $25 million (the claims here are considerably larger), if the mediation does hot conclude within sixty days, “either Party shall have the right to proceed to litigation ... in a court of competent jurisdiction.”

Under the heading “Venue,”' the contract states that the parties “agree to the non-exclusive jurisdiction of the United States District Court for the District of Columbia for any legal proceedings” aris *616 ing out of the contract and “aceept[ ], generally and unconditionally, the jurisdiction” of that court. Each party “waives” the right to challenge cases brought in the D.C. District Court “on the basis of forum non-conveniens or improper venue.” The contract adds, in the same “Venue” provision, that the parties do not “waive any fírst-to-fíle challenges to venue.”

Stone & Webster and Georgia Power attempted to negotiate a resolution of their dispute and, when that failed, entered into mediation. They agreed that mediation, if unsuccessful, would conclude on November 1, 2012, at 8:00 p.m., and that no lawsuit could be filed before then.

When the designated hour arrived on November 1, Stone & Webster filed its District of Columbia complaint against the Georgia Power group. The complaint sought more than $900 million resulting 'from regulatory changes that had occurred and would occur in the future. The law firm representing Stone & Webster used the district court’s electronic filing system. Affidavits from the firm stated'that one of its computers was connected to the United States Naval Observatory Master Clock. 1 When the Navy’s clock registered 8:00:00 p.m., a paralegal pressed the “submit” button on an adjacent computer, thereby “filing” the complaint according to local rules. See Rule 5.4(c)(3), Rules of the U.S. District Court for the District of Columbia; U.S. DistriCT Court for the District of Columbia, Eleotronio Case Filing System User’s Manual 20 (Jan.2010). The district court’s electronic filing log reported “11/01/2012 20:00:01” as the filing date and time of Stone & Webster’s complaint.

In the meantime, or at the same time, Georgia Power brought an action in the United States District Court for the Southern District of Georgia. Georgia Power’s complaint sought to recover more than $100 million paid under protest to Stone & Webster pursuant to a contract provision requiring the payment of 50 percent of disputed invoices until the dispute is resolved. The complaint also sought a declaratory judgment that the Georgia Power group was not contractually obligated to pay for costs caused by regulatory changes. According to the affidavit of a Georgia Power attorney, he handed the complaint to the court’s deputy clerk exactly when the clock on the attorney’s cell phone registered 8:00:00 p.m. The deputy clerk noted, on the hard copy of the complaint, “November 1, 2012” and “8:00 p.m.” as the date and time of the filing.

A few days later, Stone & Webster filed a motion in the District of Columbia action to enjoin Georgia Power from prosecuting the Georgia suit. Georgia Power responded with a motion to dismiss or stay the District of Columbia action. Each party claimed that it had filed first and that its complaint should therefore be given priority over the other. The district court did not decide who filed first. After reviewing the law and the equities, the court determined that the controversy should be adjudicated in the Southern District of Georgia, regardless of which party filed first. The court therefore dismissed Stone & Webster’s complaint, but without prejudice. Stone & Webster, Inc. v. Georgia Power Co., 965 F.Supp.2d 56, 61-64, 66-67 (D.D.C.2013).

Stone & Webster claims the district court erred for two reasons: the court “applied an improper legal standard in a first to file analysis and incorrectly interpreted” the contract. Appellants’ Brief at 15. Stone & Webster does not take issue with the district court’s findings regarding *617 the comparative advantage of trying the case in Georgia rather than D.C.

As to the legal standard, the general rule was set in Kerotest Manufacturing Co. v. C-O-Two Fire Equipment Co., 342 U.S. 180, 183, 72 S.Ct. 219, 96 L.Ed. 200 (1952), a decision the parties here neglected to mention. The Kerotest Court noticed that the Federal Declaratory Judgments Act, 28 U.S.C. §§ 2201-2202, had given rise to “the initiation of litigation by different parties to many-sided transactions-” Kerotest, 342 U.S. at 183, 72 S.Ct. 219. To determine which of two pending suits should proceed, the Supreme Court decided that the lower courts must be given “an ample degree of discretion,” id. at 183-84, 72 S.Ct. 219; see UtahAmerican Energy, Inc. v. Dep’t of Labor, 685 F.3d 1118, 1123 (D.C.Cir.2012).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Faizi v. Garland
District of Columbia, 2024
Lockey v. Carson
District of Columbia, 2021
United States v. Al-Nashiri
374 F. Supp. 3d 1190 (Special Court under the Regional Rail Reorganization Act, 2018)
D & S Consulting, Inc. v. Kingdom of Saudi Arabia
322 F. Supp. 3d 45 (D.C. Circuit, 2018)
Wise v. United States
128 F. Supp. 3d 311 (District of Columbia, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
779 F.3d 614, 414 U.S. App. D.C. 281, 2015 U.S. App. LEXIS 3683, 2015 WL 1020208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stone-webster-inc-v-georgia-power-company-cadc-2015.