Stoetzer v. Ohio Dept. of Transp.

2010 Ohio 6650
CourtOhio Court of Claims
DecidedOctober 15, 2010
Docket2010-07156-AD
StatusPublished
Cited by3 cases

This text of 2010 Ohio 6650 (Stoetzer v. Ohio Dept. of Transp.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stoetzer v. Ohio Dept. of Transp., 2010 Ohio 6650 (Ohio Super. Ct. 2010).

Opinion

[Cite as Stoetzer v. Ohio Dept. of Transp., 2010-Ohio-6650.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

GARY STOETZER

Plaintiff

v.

OHIO DEPARTMENT OF TRANSPORTATION

Defendant

Case No. 2010-07156-AD

Deputy Clerk Daniel R. Borchert

MEMORANDUM DECISION

{¶ 1} Plaintiff, Gary Stoetzer, filed this action against defendant, Department of Transportation (ODOT), contending his 2009 Chevrolet Malibu was damaged as a proximate cause of negligence on the part of ODOT in maintaining a hazardous condition in a roadway construction area on Interstate 75 North in Warren County. In his complaint, plaintiff noted he was traveling “[b]etween milemarker 30 & 31" on Interstate 75 when his car struck a pothole in the center lane damaging the right front wheel on the vehicle. Plaintiff recalled the stated property damage event occurred on April 26, 2010 at approximately 5:45 p.m. Plaintiff submitted a photograph depicting the pothole his vehicle struck pointing out that the roadway surface shown “has been repaired numerous times.” Plaintiff expressed the opinion that the repairs initiated were done “very poorly.” The trier of fact finds the roadway area depicted in the submitted photograph shows a surface where vast multiple patching attempts had been previously conducted. Plaintiff requested damages in the amount of $296.39, the total stated cost of a replacement wheel. The $25.00 filing fee was paid and plaintiff requested reimbursement of that cost along with his damage claim. {¶ 2} Defendant acknowledged the roadway area where plaintiff’s incident occurred was within the limits of a working construction project under the control of ODOT contractor, John R. Jurgensen Company (Jurgensen). Defendant explained the particular construction project “dealt with widening of I-75 between Cincinnati-Dayton Road and SR 122 in Butler and Warren Counties.” According to defendant, the construction project limits “corresponds to state mileposts 21.0 to 32.0” on Interstate 75 and plaintiff’s damage incident occurred between state mileposts 31.0 and 32.0, a location within the construction area limits. Defendant asserted that this particular construction project was under the control of Jurgensen and consequently ODOT had no responsibility for any damage or mishap on the roadway within the construction project limits. Defendant argued that Jurgensen, by contractual agreement, was responsible for maintaining the roadway within the construction zone. Therefore, ODOT contended that Jurgensen is the proper party defendant in this action. Defendant implied that all duties such as the duty to inspect, the duty to warn, the duty to maintain, and the duty to repair defects were delegated when an independent contractor takes control over a particular section of roadway. Furthermore, defendant contended that plaintiff failed to introduce sufficient evidence to prove his damage was proximately caused by roadway conditions created by ODOT or its contractors. All construction work was to be performed in accordance with ODOT requirements and specifications and subject to ODOT approval. Also evidence has been submitted to establish that ODOT personnel were present on site conducting inspection activities. {¶ 3} For plaintiff to prevail on a claim of negligence, he must prove, by a preponderance of the evidence, that defendant owed him a duty, that it breached that duty, and that the breach proximately caused his injuries. Armstrong v. Best Buy Company, Inc., 99 Ohio St. 3d 79, 2003-Ohio-2573,¶8 citing Menifee v. Ohio Welding Products, Inc. (1984), 15 Ohio St. 3d 75, 77, 15 OBR 179, 472 N.E. 2d 707. Plaintiff has the burden of proving, by a preponderance of the evidence, that he suffered a loss and that this loss was proximately caused by defendant’s negligence. Barnum v. Ohio State University (1977), 76-0368-AD. However, “[i]t is the duty of a party on whom the burden of proof rests to produce evidence which furnishes a reasonable basis for sustaining his claim. If the evidence so produced furnishes only a basis for a choice among different possibilities as to any issue in the case, he fails to sustain such burden.” Paragraph three of the syllabus in Steven v. Indus. Comm. (1945), 145 Ohio St. 198, 30 O.O. 415, 61 N.E. 2d 198, approved and followed. This court, as trier of fact, determines questions of proximate causation. Shinaver v. Szymanski (1984), 14 Ohio St. 3d 51, 14 OBR 446, 471 N.E. 2d 477. {¶ 4} Defendant had the duty to maintain its highways in a reasonably safe condition for the motoring public. Knickel v. Ohio Department of Transportation (1976), 49 Ohio App. 2d 335, 3 O.O. 3d 413, 361 N.E. 2d 486. However, defendant is not an insurer of the safety of its highways. See Kniskern v. Township of Somerford (1996), 112 Ohio App. 3d 189, 678 N.E. 2d 273; Rhodus v. Ohio Dept. of Transp. (1990), 67 Ohio App. 3d 723, 588 N.E. 2d 864. The duty of ODOT to maintain the roadway in a safe drivable condition is not delegable to an independent contractor involved in roadway construction. ODOT may bear liability for the negligent acts of an independent contractor charged with roadway construction. Cowell v. Ohio Department of Transportation, Ct. of Cl. No. 2003-09343-AD, jud, 2004-Ohio-151. Despite defendant’s contentions that ODOT did not owe any duty in regard to the construction project, defendant was charged with duties to inspect the construction site and correct any known deficiencies in connection with the particular construction work. See Roadway Express, Inc. v. Ohio Dept. of Transp. (June 28, 2001), Franklin App. 00AP-1119. {¶ 5} Alternatively, defendant denied that neither ODOT nor Jurgensen “had notice of a pothole on I-75 prior to plaintiff’s incident.” Defendant pointed out that ODOT records “indicate that no calls or complaints were received regarding a pothole prior to Plaintiff Stoetzer’s incident.” Defendant advised, “[i]t should be noted that this portion of I-75 has an average daily traffic volume between 73,320 and 93,130, however, no other complaints were received (regarding a roadway defect) prior to plaintiff’s alleged incident.” Defendant contended plaintiff failed to offer any evidence of negligent roadway maintenance on the part of ODOT and failed to produce evidence to establish his property damage was attributable to conduct on either the part of ODOT or Jurgensen. Defendant denied receiving any complaints before April 26, 2010 regarding a pothole on Interstate 75 between milepost 30.0 and 31.0. {¶ 6} Defendant submitted a letter from Jurgensen Project Manager, Kate Holden, who recorded Jurgensen was notified of the pothole plaintiff’s vehicle struck by the Ohio State Highway Patrol (OSP) at approximately 8:05 p.m. on April 26, 2010. According to Holden, the Jurgensen Work Traffic Supervisor, upon receiving notice of the pothole from OSP, “made the repair immediately.” Holden specifically denied any Jurgensen personnel received any notice of the particular pothole prior to 8:00 p.m. on April 26, 2010. With her letter, Holden attached copies of her daily journal notes for late April 2010 referencing Jurgensen work activity on the project. The first notation regarding a pothole appears on the April 26, 2010 journal notes. Holden wrote the following: “Jason Mudd called 805 p OSP called him we have a pothole NB center.” {¶ 7} In order to find liability for a damage claim occurring in a construction area, the court must look at the totality of the circumstances to determine whether ODOT acted in a manner to render the highway free from an unreasonable risk of harm for the traveling public. Feichtner v. Ohio Dept. of Transp. (1995), 114 Ohio App. 3d 346, 683 N.E. 2d 112.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barnes v. Dept. of Transp.
2011 Ohio 6989 (Ohio Court of Claims, 2011)
Sheppard v. Ohio Dept. of Transp.
2011 Ohio 6911 (Ohio Court of Claims, 2011)
Batten v. Ohio Dept. of Transp.
2011 Ohio 5533 (Ohio Court of Claims, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
2010 Ohio 6650, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stoetzer-v-ohio-dept-of-transp-ohioctcl-2010.