Stickney v. General Electric Co.

44 F.2d 362, 1930 U.S. App. LEXIS 3371
CourtCourt of Appeals for the Fourth Circuit
DecidedOctober 21, 1930
Docket3018
StatusPublished
Cited by10 cases

This text of 44 F.2d 362 (Stickney v. General Electric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stickney v. General Electric Co., 44 F.2d 362, 1930 U.S. App. LEXIS 3371 (4th Cir. 1930).

Opinion

SOPER, District Judge.

General Electric Company was successful in the District Court upon its petition to recover from II. 0. Stickney, trustee in bankruptcy of the estate of the Spear Engineers, Incorporated, a fund of $12,944.06. The fund had its origin in a transaction growing out of two contracts. On August 14, 1928, the Spear Engineers, Incorporated, as builder, made an agreement with the city of Portsmouth, Va., and the county of Norfolk, Va., owners and operators of Norfolk County Perries, for the construction of a ferryboat within 300 calendar days. The contract provided amongst other things that payments should be made during the progress of the work as each 20 per cent, thereof should be completed according to certification of percentage of completion by the owner’s naval architect; that the builder should keep the ferryboat clear from all claims, liens, or incumbrances of every kind and description whatsoever; and that the ferryboat, together with all fixtures, material, appliances, etc., placed thereon or delivered on the premises of the builder, should become the property of the owner, subject, however, to the builder’s liens and rights under common or statute law or under the agreement.

The Spear Engineers, Incorporated, also made a contract with the General Electric Company for the purchase of'certain electric propulsion motors and equipment for installation in the ferryboat. The total contract price was $28,880; and material of the value of $19,361.18 had been delivered, upon which $6,600 had been paid, leaving a balance of $12,761.18 due at the time that the fund was established. This ‘contract contained a provision that the title to the apparatus and material should remain in General Electric Company until fully paid for in cash, and gave the company the right to retake the property in case of default in any payment by the purchaser. But the contract was not recorded in conformity with the Virginia statute regulating conditional sales, codified in section 5189 of the Code of Virginia 1924, and hence the reservation of title, while valid in other respects, was void under the terms of the statute as to creditors of the vendee who should acquire a lien upon the goods, and as to purchasers from the vendee for value without notice.

The building of the vessel was carried on during the latter part of 1928 and the early part of 1929, and two progress payments during the course of the work had been made by the owner to the builder. A third payment of $42,120, due at 60 per cent, of completion, was about to be made early in the month of May, 1929; but this stage in the progress of the work could not be said to have been reached unless there should be included in the computation of materials furnished the General Electric equipment then delivered at the yard of the builder but not yet installed upon the vessel. At this juncture, the General Electric Company, being concerned as to the debt due it by the Spear Engineers, wrote a letter under date of May 7, 1929, to the city of Portsmouth, wherein it claimed title to the electrical equipment under the reservation in its contract with the builder, and stated that there was then due it the sum of $12,761.18, with interest. It requested that the city set aside a sufficient sum to pay this debt out of the next money which should become due to the builder under the terms of the construction contract.

This letter was considered at a joint meeting of the council of the city of Portsmouth and the commissioners of the county of Norfolk, and was by them referred to the superintendent of the Perries, and the respective law officers of the municipal corporations. The superintendent consulted the naval architect who was required, as we have seen, to certify the percentage of completion before progress payments could be made. After consideration of the matter, the city attorney of Portsmouth, by letter of May 30, 1929, advised the superintendent that the architect should either deduct the amount of the lien of General Electric Company from the progress of the work, or should use the money so that Spear Engineers could acquire title to the equipment and thereby make it pos *364 rible to count the same in estimating the progress of the worirj. He said that the amount due the General Electrie Company would have to be either paid or placed in escrow. Accordingly, the architect authorized the third progress payment to be made, provided the amount of $12,761.18 due the General Electric Company was settled therefrom. Being thus advised, the superintendent made the distribution in accordance with the following memorandum made by his bookkeeper:

Third Payment on June 1, 1929.
Total amount including amount due General Electric ............................... $42,120 00
By check to- Spear Engrs........ $29,175 94
Deposited in escrow in A. N. B. to protect General Electric Company ............$12,761 18
And interest 3 — 7 to 6-1 — 29 .............. . 182 88 12,944 06 $42,120 00

The deposit slip for the sum of $12,944.06 in the American National Bank reads as follows :

Deposited in the American National Bank of Portsmouth, Portsmouth, Va. by Norfolk County Portsmouth Ferries,
Charles XT. Freund, Supt.
Special Account
General Electric Lien
6 — 1 — 29
checks as follows: $12,75118
182 88
$12,944 06

There was also an entry made in the ledger of the Norfolk County Ferries as follows:

“Funds out of third payment to Spear Eng. Inc. deposited in Amer. Natl. Bank, Norfolk County Ferries, Charles U. Freund, Supt., General Electric Co., June 1, 1929, $12,944.06.”

The superintendent testified at the hearing that the situation at the time that the notice from General Electric Company was received was that the material did not belong to the vessel because there was a lien on it, but that he thought that the owner of the vessel had the right to install the material until it received notice of the lien. After notice was received, he made the arrangements above outlined in order that the material furnished by General Electric Company might be included in the progress of the boat and permit the third payment to he made. The sum of $12,944 was deducted because a lien was claimed against the material, and the money was placed in the hands of the owner to protect it against the claim of the lien and also incidentally for the protection of General Electric Company.

The money remained on deposit in the bank until after the bankruptcy of the Spear Engineers, when it was paid over to the trustee in bankruptcy subject to the final adjudication of the controversy. The petition in bankruptcy was filed on September 21, 1929, the adjudication took place on October 7, 1929, and the petition of General Electric Company to recover the deposit was filed on November 6, 1929. In the meantime, no other transactions took place affecting the situation; hut some light is thrown by subsequent events upon the understanding between the parties at the time the fund was created.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dorula v. Holmes (In re Starlight Group, LLC)
531 B.R. 611 (E.D. Virginia, 2015)
Polo Club Office v. Vickers
Fifth Circuit, 1996
Guinee v. Prager (In Re James R. Corbitt Co.)
20 B.R. 460 (E.D. Virginia, 1982)
Felmey v. Household Finance Corp. (In Re Felmey)
9 B.R. 331 (E.D. Virginia, 1981)
Creel v. Birmingham Trust National Bank
383 F. Supp. 871 (N.D. Alabama, 1974)
Hoffman v. First National Bank
135 S.E.2d 818 (Supreme Court of Virginia, 1964)
United States Fidelity & Guaranty Co. v. Sweeney
80 F.2d 235 (Eighth Circuit, 1935)
Santee Timber Corporation v. Elliott
70 F.2d 179 (Fourth Circuit, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
44 F.2d 362, 1930 U.S. App. LEXIS 3371, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stickney-v-general-electric-co-ca4-1930.