Stewart v. Westwood Brick Co.
This text of 17 Ohio C.C. Dec. 272 (Stewart v. Westwood Brick Co.) is published on Counsel Stack Legal Research, covering Ohio Circuit Courts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
While it is true that the mechanic’s lien law has been amended since -the decision of Palmer v. Tingle, 55 Ohio St. 423 [45 N. E. Rep. 313], yet Lan. R. L. 5100 and 5117 (R. S. 3184 and 3195), as now amended, are open to the same objection in so far as they give a lien on the property of the owner to subcontractors, laborers and those who furnish material to subcontractors.
No contractual relation existed between the principal and contractor, William H. Stewart, and the plaintiff, the Westwood Brick Company, or the Moores Lime Company, each of whom furnished material to a subcontractor.
Judgment will be reversed and cause remanded with instructions to distribute $885.06 of the fund to the plaintiff and the Moores Lime Company, in proportion to their respective claims, and the residue of the fund to the principal contractor, William H. Stewart.
Free access — add to your briefcase to read the full text and ask questions with AI
Cite This Page — Counsel Stack
17 Ohio C.C. Dec. 272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stewart-v-westwood-brick-co-ohiocirct-1905.