Stewart v. District of Columbia

19 Ct. Cl. 98, 1884 U.S. Ct. Cl. LEXIS 115
CourtUnited States Court of Claims
DecidedJanuary 21, 1884
DocketNo. 98; No. 262
StatusPublished

This text of 19 Ct. Cl. 98 (Stewart v. District of Columbia) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stewart v. District of Columbia, 19 Ct. Cl. 98, 1884 U.S. Ct. Cl. LEXIS 115 (cc 1884).

Opinion

Richardson, J.,

delivered the opinion of the court: '

These two cases, depending substantially upon the same state of facts, were consolidated and tried together by order of court, under the provisions of section 2 of the District Claims Act June 16,1880, chapter 243 (Supplement to Rev. Stat., 562).

The findings show that the claimant Stewart did work and furnished materials for the defendant to the value of $16,550.99, and that he has been paid in certificates and property to the extent of $15,266.08, leaving a balance still due of $1,284.91, unless it is to be reduced or swept away by the allowance of one or both of two items of charge, or claims, set up against it by the defendant. The validity of these claims depends upon a determination of principles of law arising upon the following state of facts, as presented by the findings.

1. When the chief engineer measured the work done by Stewart on Dunbarton street, he charged to the contractor and deducted from the amount of his certificate for that work $580.44, therein stated to be “retained for repairs.”

On the part of the defendant it is claimed that the contractor is concluded by the certificate of the chief engineer, under the terms of the eighth and twelfth articles of the contract (set out at the end of finding I), or at least that the burden is upon him to show that the facts do not warrant the longer retention of the money due him.

We cannot concur in that view of the rights and obligations of the parties.

The twelfth article of the contract requires that the measurements be made by the engineer of the board of public works. The eighth article provides that payments shall be made only upon the estimates and certificates of the chief engineer of the board. Measurements, estimates, and certificates were so made [104]*104in this case. The insertion in one of the certificates of an item for the retention of a sum for repairs, under the circumstances, was not an estimate or certificate of required work left undone. It had no relation to the measurements nor to the quantity of work actually and properly completed. It is evident from the words of the item,'taken in connection with the terms of the contract, that the chief engineer put down the sum “ retained for repairs” not for existing defects in the work, but as security for the performance of the terms of the ninth article of the contract, which is as follows:

“Ninth. It is further agreed that if at any time during the period of one year from the completion of the work to be done under this contract any part ’or parts thereof shall become defective from imperfect or improper material or construction and in the opinion of the said party of the first part require repair, the said party of the second' part will, on being notified thereof, immediately commence and complete the same to the satisfaction of the party of the first part, and in case of a failure or neglect of the said party of the second part so to do, the same shall be done under the directions and orders of the party of the first part at the cost and expense of the party of the second part. (Finding I.)”

The defendant was not expressly authorized by the contract to retain any money specifically to secure the performance of the contractor’s obligations under that article, arid if it did so with his consent or because it claimed not to be forced to make final payment until all the obligations of the contractor were fulfilled, or because such was the usual practice, the District could not hold the money after the claimants’ obligations had been complied with or had ceased to exist. If, during one year next after the completion of the work, the defendant’s officers were of opinion that the work had become defective or imperfect and required repairs, it was their duty to notify the contractor of the fact that he might complete the same to their satisfaction; and if he failed to do so, then, and not till then, they could go on and do the repairs themselves at the cost and expense of the contractor. So far as the money retained was required to meet such costs and expense they might continue to hold it, but no further. That is the plain interpretation of the contract in its relations to this money retained for repairs.

It will be seen from the findings that it is. not shown that the defendant’s officers ever notified the contractor that his work was defective and needed repairs, or that the District had ex[105]*105pended any sum on account of defects, or that the work was in fact in a defective condition during the year after its completion or since that time. If the defendant had been put to cost, and expense for any breach of the ninth article of the contract on the part of the contractor, the burden was upon the District to show the fact expressly.

By the terms of the article the District officers were bound to notify the contractor if they were of opinion that his work required repairs, and it is hot for him to prove the negative... It is sufficient for his case that they do not prove that he has. broken any of the obligations assumed by him in the ninth article.

It follows that the defendants had no further lien or claim to-the $580.44 that was retained for repairs, and it cannot be-charged against.

2. The second item now under consideration in the defendant’s account of charges against the contractor is. for the sum of $2,610.72 paid through the accounting and disbursing officers, of the Treasury Department, under the provisions contained in the Appropriation Act June 20, 1878, chapter 359 (20 Stat. L., 209), to persons who claimed to be unpaid workmen employed by Stewart, in doing the work under his contracts with the board of public works. It is there enacted—

“ That a sum not exceeding seventy-five thousand dollars be appropriated to pay the workingmen employed in the public-, improvements under the late board of public works of the District of Columbia, or the contractors of the same, whose claims for work and labor are due and unpaid from contractors whose accounts against the government of the District of Columbia had been paid prior to the passage of the act of June twenty-third, eighteen hundred and seventy-four, entitled ‘An act making appropriations for sundry civil expenses of the government for the fiscal year ending June thirtieth, eighteen hundred and seventy-five, and for other purposes.’
Provided, That such claims shall be severally audited and paid by the proper accounting and disbursing officers of the Treasury, and that the amount found to be due to each workman shall only be paid to him in person if living, or in case of' non-residents of the District of Columbia, by draft on the Treasury of the United States to his or their order, or to his. legal representatives, if dead.
And provided further, That if said sum of seventy-five thousand dollars shall not be sufficient to pay all such claims filed prior to first day of December next in full, then there shall be-[106]*106made the required pro rata deduction on each claim, and the amount to be paid on each claim shall be paid and received in full discharge of the claim of such workman.
“ Provided further,

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
19 Ct. Cl. 98, 1884 U.S. Ct. Cl. LEXIS 115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stewart-v-district-of-columbia-cc-1884.