Stewart-Decatur Security Systems, Inc. v. Von Weise Gear Company

517 F.2d 1136, 17 U.C.C. Rep. Serv. (West) 24, 1975 U.S. App. LEXIS 14375
CourtCourt of Appeals for the Eighth Circuit
DecidedJune 5, 1975
Docket74-1419
StatusPublished
Cited by10 cases

This text of 517 F.2d 1136 (Stewart-Decatur Security Systems, Inc. v. Von Weise Gear Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stewart-Decatur Security Systems, Inc. v. Von Weise Gear Company, 517 F.2d 1136, 17 U.C.C. Rep. Serv. (West) 24, 1975 U.S. App. LEXIS 14375 (8th Cir. 1975).

Opinion

WEBSTER, Circuit Judge.

In this appeal we consider whether, in a contract for the sale of goods, an approved prototype may displace an inconsistent specification in a written purchase order.

Appellant Stewart-Decatur Security Systems, Inc., manufactures jail doors for use in penal institutions. A small electric gear motor is employed to open and close the doors automatically. Appellee von Weise Gear Co. builds gears and fractional horsepower gear motors.

In early 1970, Stewart-Decatur placed an order with von Weise for a prototype of a gear motor to replace a gear motor then being supplied by General Electric Company. Von Weise had earlier submitted a drawing of such a prototype through its agent S. William Pratt, Inc. The design and dimensions set forth in the drawing had been approved by Gerald L. Butt, assistant to the engineering manager at Stewart-Decatur. The prototype was constructed and shipped to Stewart-Decatur for testing. It was installed in an actual jail door and tested over a period of three days by using it to open and close the door approximately three thousand times. At various times during this testing, slats were placed in the door frame to see if the gear motor would back off of a jam. Stewart-Decatur was satisfied with the performance of the prototype; at that time it did not know that the input speed of the prototype was 3200 r. p. m. 1

Stewart-Decatur submitted a written purchase order to von Weise for 1560 gear motors on April 3, 1970. The purchase order referred to certain specifications of the General Electric motor, including an input speed of approximately 1590 r. p. m. It also included a previously agreed upon metallurgical change. The gear motors were to be manufactured “as per prototype drawing.” 2 The drawing made no reference to input speed and this specification was overlooked at von Weise’s place of manufacture.

Von Weise returned an order acknowledgment dated April 27, 1970, which referred to the accepted prototype by description and number, 3 and approved the sale of 1560 production line models of the prototype. Shortly thereafter, von Weise sent Stewart-Decatur a dimensional drawing of the prototype containing specifications identical to those in its order acknowledgment. Gerald L. Butt examined the drawing for Stewart-Decatur. He questioned two of the dimensions on the drawing not relevant to the problems which gave rise to this lawsuit, but nevertheless marked the drawing “approved for fabrication delivery urgent.”

The first shipment of the production model gear motors was received by Stewart-Decatur on October 9, 1970. It was noticed from the specifications *1138 stamped on the motors that their input speed was approximately 3200 r. p. m. rather than 1590 r. p. m. as had been specified in the purchase order. After further testing, Stewart-Decatur found that the higher input speed prevented the motors from backing off a jam, making them unfit for use in jail doors; 4 it so notified von Weise. Much later tests revealed that the gear motors also failed to meet Stewart-Decatur’s torque specifications.

*1137 Gear motor[s], G.E. series 49 permanent split capacitor * * * approximately 1590/64 r. p. m. — 115 V., 1 phase, 60 cycle, instantly reversible, shaft extension 215/i6” from center line of gear box as per prototype drawing and with flat on shaft. Torque approximately 17 in. lbs. at 64 r. p. m., motor to have thermal overload and steel cupped output gear.

*1138 Von Weise submitted a second prototype. When it, too, was found unsuitable, because it lacked self-locking capabilities, von Weise indicated that it would be unable to produce a unit acceptable to Stewart-Decatur.

At the time Stewart-Decatur placed its order with von Weise, it had a contract to install jail doors in a New York City prison and intended to use the von Weise gear motors in this project. When the motors were found unsuitable, and before the second prototype had been supplied, Stewart-Decatur purchased satisfactory motors from another manufacturer at an increased cost. Stewart-Decatur brought this action to recover the monies it had paid von Weise under the contract and the extra cost it had incurred when it purchased substitute motors. In a counterclaim, von Weise sought recovery of the production costs of the gear motors.

The District Court 5 applied the Uniform Commercial Code, as adopted in Missouri, and ruled that while technical specifications in a contract normally take precedence over an inconsistent model, Stewart-Decatur’s actions with respect to the first prototype were a substantial contributing factor in von Weise’s failure to meet the motor speed requirement set forth in Stewart-Decatur’s purchase order. It found that the variance in torque was not a basis for rejection of the production units because the variance was not discovered until after the rejection. It held that Stewart-Decatur had not given von Weise an adequate opportunity to correct the defect before “covering” 6 and that it was therefore not entitled to recover. Von Weise’s counterclaim was also denied.

Stewart-Decatur appeals from the decision of the District Court, contending that: (1) von Weise was obliged to follow the technical specifications contained in Stewart-Decatur’s purchase order, (2) Stewart-Decatur’s failure to state the improper torque as a ground for rejecting the gear motors does not preclude it from relying on this to establish a breach of contract, and (3) Stewart-Decatur was entitled to cover following von Weise’s alleged failure to tender gear motors which conformed to the parties’ contract. Upon a full review of the record, we affirm the District Court, but we base our decisions on somewhat different. grounds.

I.

The District Court was correct in applying the Missouri Uniform Commercial Code in this diversity action. 7 (V.A. M.S. §§ 400.1-101 to .10-102 (1965)) [hereinafter cited as §----]. See, e. g., Erie Railroad Co. v. Tompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188 (1938). This case involves a transaction in goods; 8 we therefore begin our analysis with Article 2 of the Code.

*1139 Stewart-Decatur’s purchase order was an offer. Smyth Worldwide-Movers v. Little Rock Packing Co., 235 Ark. 679, 361 S.W.2d 534 (1962); see V’Soske v. Barwick, 404 F.2d 495 (2d Cir. 1968), cert. denied, 394 U.S. 921, 89 S.Ct. 1197, 22 L.Ed.2d 454 (1969); § 2-206(l)(b).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lithuanian Commerce Corp. v. Sara Lee Hosiery
179 F.R.D. 450 (D. New Jersey, 1998)
St. Charles Cable TV, Inc. v. Eagle Comtronics, Inc.
687 F. Supp. 820 (S.D. New York, 1988)
Romicon, Inc. v. L & J of New England, Inc.
1981 Mass. App. Div. 164 (Mass. Dist. Ct., App. Div., 1981)
JB MOORE ELEC. CON. v. Westinghouse Elec.
273 S.E.2d 553 (Supreme Court of Virginia, 1981)
Amf, Incorporated v. McDonald Corporation
536 F.2d 1167 (Seventh Circuit, 1976)
Falcon Tankers, Inc. v. Litton Systems, Inc.
355 A.2d 898 (Superior Court of Delaware, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
517 F.2d 1136, 17 U.C.C. Rep. Serv. (West) 24, 1975 U.S. App. LEXIS 14375, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stewart-decatur-security-systems-inc-v-von-weise-gear-company-ca8-1975.