Stevens & Thompson Paper Co. v. Niagara Mohawk Power Corp.

802 N.E.2d 1084, 1 N.Y.3d 158, 770 N.Y.S.2d 686, 2003 N.Y. LEXIS 3979
CourtNew York Court of Appeals
DecidedNovember 25, 2003
StatusPublished

This text of 802 N.E.2d 1084 (Stevens & Thompson Paper Co. v. Niagara Mohawk Power Corp.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stevens & Thompson Paper Co. v. Niagara Mohawk Power Corp., 802 N.E.2d 1084, 1 N.Y.3d 158, 770 N.Y.S.2d 686, 2003 N.Y. LEXIS 3979 (N.Y. 2003).

Opinion

OPINION OF THE COURT

Ciparick, J.

This appeal requires us to determine whether a power purchase agreement (PPA) between a utility, Niagara Mohawk (NIMO), and a generator of electricity, Stevens and Thompson (S&T), is subject to the grandfathering provisions of Public Service Law § 66-c (2) (a) (ii), and thus subject to the six cent per kilowatt hour minimum rate for the 7.5 megawatts of “new” capacity generated by S&T for the remainder of the agreement. We conclude that the grandfathering provision is not applicable to this PPA and that the appropriate payment rate for the “new” capacity is NIMO’s actual avoided cost.1

Congress enacted the Public Utility Regulatory Policies Act of 1978 (PURPA) (Pub L 95-617) in order to help foster the development of alternative sources of energy (see Matter of Consolidated Edison Co. v Public Serv. Commn., 63 NY2d 424, 431 [1984]). New York Public Service Law § 66-c was enacted soon thereafter to fulfill the same purposes at the state level (Public Service Law § 66-c [1]). It provided for a minimum sales price of six cents per kilowatt hour for electricity purchased from qualifying facilities by utilities. The provision requiring the six cent minimum was removed from section 66-c (1) in 1992 and section 66-c (2) was added (L 1992, ch 519, §§ 3, 4).

Section 66-c (2) is a grandfathering provision allowing certain agreements to continue to function under the six cent minimum rate if the agreement was executed by the parties and filed with the Public Service Commission by June 26, 1992, and the agreement “provides] for the purchase of electricity at a utility tariff rate referencing a statutory minimum sales price . . . provided, however, that such minimum sales price shall be implemented [161]*161in accordance with the policies and conditions established by the commission” (Public Service Law § 66-c [2] [a]). The six cent minimum rate was apparently repealed because the rate turned out to be an overestimate of the cost of production of electricity by the qualifying facilities, resulting in the imposition of overpayments on the utilities and their customers. The Governor’s Approval Memorandum in support of the repeal and the grandfathering provision stated “[c]onsumers are thereby relieved of the outdated minimum sales price while reasonable protection is provided to producers who relied on this minimum price provision” (Governor’s Mem approving L 1992, ch 519, 1992 McKinney’s Session Laws of NY, at 2898).

S&T owns and operates a small hydroelectric generating facility that had an original capacity of three megawatts (MW)— referred to as “old” capacity. The facility was replaced in 1986, increasing its capacity by an additional 7.5 MW of “new” capacity, for a total existing output of 10.5 MW. S&T and NIMO entered into a PPA pursuant to Public Service Law § 66-c (1) (a) in January 1987 whereby NIMO was required to purchase the entire 10.5 MW capacity of electricity generated by S&T.

The PPA was divided into three time periods—the first period ending December 31, 2000, the second December 31, 2008, and the third December 31, 2016. For purposes of this appeal, the only contract provisions at issue are those that relate to the rate that must be paid for the “new” capacity during the second and third periods.2 The PPA states that for the second period, in consideration for a longer contract term, NIMO will pay S&T 90% of its avoided cost and recognizes that the discount may result in payments that are below any applicable minimum rate.3 The PPA goes on to define avoided cost as

“such actual cost of electric production . . . avoided by reason of this agreement, as defined in Service Classification No. 6 of PSC No. 207 Electricity as the same may be from time to time changed, amended and/or supplemented, the tariff duly approved by the commission applicable for payments to qualifying on-site generation suppliers whose [162]*162sales of capacity and energy to Niagara are made under the terms of such tariff.”

For the third period, NIMO would pay S&T 80% of its avoided cost at “the rate contained in Service Classification No. 6.”4

NIMO’s tariff, Service Classification No. 6 (SC No. 6), sets forth a formula to be applied for determining the rate to be paid by NIMO to qualifying facilities. The tariff provides “[t]o the extent that a minimum unit rate applied under Section 66-c of the Public Service Law . . . the rate to be paid under this service classification shall be no less than 6.0 cents per kWh.”

Before the parties executed the PPA, the Commission issued an order directing certain terms (see Pub Serv Commn Case No. 29448, issued Dec. 3, 1986). The Commission determined that mere agreement between the parties to extend the PPA for longer than 15 years was insufficient consideration to allow NIMO to purchase the electricity at a discounted rate (see Pub Serv Commn Case No. 29448, issued Dec. 3, 1986).5 The Commission also

“direct[ed] Niagara Mohawk to enter into a [301-year contract that provides for payment at the settlement rates for the increase in capacity resulting from the proposed facility through the year 2000 and thereafter through the end of the [30]-year term at full avoided costs. With respect to the 3 MW representing existing capacity, the payment rate will be tariff-based avoided costs, subject to the statutory minimum, throughout the [30]-year term of the contract” (Pub Serv Commn Case No. 29448, issued Dec. 3, 1986).6

S&T commenced this action in May 2001 after the expiration of the first payment period because, as of February 2001, NIMO stopped paying S&T at the six cent minimum rate for the entire [163]*163capacity—instead paying only NIMO’s avoided costs. S&T sought declarations that the PPA was within the grandfathering provisions of section 66-c, and thus subject to the six cent minimum, and that NIMO could not legally pay S&T at a rate below the six cent minimum. S&T also sought damages for the difference between the rate it was actually paid—NIMO’s avoided costs—and the six cent rate, with interest, and further, to enjoin NIMO from paying it at a rate less than six cents per kilowatt hour. The parties cross-moved for summary judgment pursuant to CPLR 3212.

Supreme Court granted each party’s motion in part, finding the PPA was grandfathered because it was in effect prior to June 26, 1992, the effective date of the amendment, and incorporated the six cent minimum through the SC No. 6 tariff. The court then determined that, for the second and third periods, NIMO must pay its actual avoided costs for the “new” capacity and the tariff-based avoided costs subject to the six cent minimum for the “old” capacity. The court based its decision, in part, on the language in the Commission’s December 1986 order differentiating between “full avoided costs” for the “new” capacity—without mentioning the six cent minimum— and “tariff-based avoided costs, subject to the statutory minimum” for the “old” capacity.

The Appellate Division affirmed for different reasons.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Consolidated Edison Co. v. Public Service Commission
472 N.E.2d 981 (New York Court of Appeals, 1984)
Niagara Mohawk Power Corp. v. Public Service Commission
507 N.E.2d 287 (New York Court of Appeals, 1987)
New York Telephone Co. v. Public Service Commission
731 N.E.2d 1113 (New York Court of Appeals, 2000)
Stevens & Thompson Paper Co. v. Niagara Mohawk Power Corp.
299 A.D.2d 628 (Appellate Division of the Supreme Court of New York, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
802 N.E.2d 1084, 1 N.Y.3d 158, 770 N.Y.S.2d 686, 2003 N.Y. LEXIS 3979, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stevens-thompson-paper-co-v-niagara-mohawk-power-corp-ny-2003.