Stevens Concrete Pipe & Products, Inc. v. Burgess

209 So. 2d 733, 252 La. 136, 1968 La. LEXIS 3044
CourtSupreme Court of Louisiana
DecidedApril 29, 1968
Docket48946
StatusPublished
Cited by9 cases

This text of 209 So. 2d 733 (Stevens Concrete Pipe & Products, Inc. v. Burgess) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stevens Concrete Pipe & Products, Inc. v. Burgess, 209 So. 2d 733, 252 La. 136, 1968 La. LEXIS 3044 (La. 1968).

Opinion

McCALEB, Justice.

Plaintiff, a resident taxpayer of East Baton Rouge, individually and as President of Stevens Concrete Pipe & Products, Inc., seeks a declaratory judgment pronouncing the invalidity, and preliminary and permanent injunctions barring enforcement, of certain pipe criteria adopted by the City- *139 -Parish Council of East Baton Rouge at its meeting of February 16, 1966 on the ground that the requirement of 12-foot lengths was an arbitrary, unreasonable and capricious exercise of power designed to thwart the purpose of the competitive bidding laws, and that the proposed specifications are violative of R.S. 38:2211 et seq. (the “low bidder” or “public advertisement statute”), and R.S. 38:2290-38:2296 (the “closed specification law”).

Named as defendants are The City of Baton Rouge, The Parish of East Baton Rouge, and Ray W. Burgess, Director, Department of Public Works, for the City-Parish.

In plaintiff’s petition charges concerning favoritism for the only pipe manufacturer in the area presently capable of producing pipe in 12-foot lengths were leveled at the Director of Public Works, Mr. Ray W. Burgess.

Defendants filed certain exceptions, which were overruled. However, by pretrial order, the judge ruled out any questions inquiring into the motives or reasons of the Councilmen who voted either in favor of or against the action taken by the City-Parish Council at its meeting on February 16, 1966, 1 when the specification was approved.

After a trial on the merits, the district judge concluded from the evidence presented that the action of the Council in requiring pipe to be in minimum lengths of twelve feet was “clearly arbitrary and capricious”, there being no basis in fact on the difference in “n” factor as between eight and twelve foot pipe, nor is there valid reason for the opinion of defendants’ engineers that use of twelve foot pipe would reduce joint failure because all experts agree the use of the confined “O” ring joint provided for in the specifications reduces failures to a minimum. The judge further found that, since the evidence showed that pipe in 8-foot lengths is substantially equal in utility to pipe in 12-foot lengths, the restriction in the specifications requiring the use of pipe in 12-foot lengths violates the public policy of this state and the low bidder statutes. Accordingly, judgment was rendered against defendants, permanently enjoining them from requiring that concrete pipe used in public works projects be in minimum lengths of twelve feet, and invalidating the specification for reinforced concrete culvert, storm drain and sewer pipe insofar as it requires all such pipe to be in such minimum lengths.

A decree was also rendered declaring that, “ * * * no distinction be made by the defendants as between the use of twelve *141 foot lengths of pipe, on the one hand, and the use of eight foot lengths of pipe, on the other hand, based on the difference in the 'n’ factor.”

An appeal was taken by defendants and the Court of Appeal, First Circuit, affirmed the judgment. See 202 So.2d 498. That court did not rest its opinion on the action being arbitrary. 2 Rather, it chose to ground its affirmance on defendants’ violation of the closed specification law, R.S. 38:2290-38:2296, finding the evidence showed that the requirements regarding minimum 12-foot lengths of pipe eliminates the use of products equal to or as good as those specified.

Upon application of defendants, this Court granted certiorari and the matter has been argued and submitted for our determination.

Defendants (relators) contend the Court of Appeal erred in substituting its judgment for that of an elected legislative body on a matter of legislative discretion, there being a substantial difference of opinion concerning the engineering criteria in question; in holding that the provisions of R. S. 38:2290-38:2296 and R.S. 38:2211 et seq., were applicable, or if applicable, that the criteria of February 16, 1966 contravened the cited statutory provisions; and, finally, in holding that the defendants had the burden of proving by a preponderance of the evidence, the validity of the pipe criteria adopted by the City-Parish Council.

The record reveals the following facts: The City-Parish Council for the Parish of East Baton Rouge, in connection with a program of parish-wide improvement and extension of drainage facilities, adopted the following recommendation of the Capital Improvements Expediting Committee-at its meeting on February 16, 1966 -authorizing the use of 12-foot minimum lengths effective September 1, 1966:

“After discussion, a motion was made by Mr. Harris and seconded by Mr. Clegg that the Council adopt the new pipe criteria as proposed by the Director of Pub-lie Works effective September I, 1966; and that all projects to be let prior to September 1 be designed under present criteria, and all projects to be let after September 1 he designed under the proposed criteria with an ‘n’ factor of 0.010 and requiring a minimum of 12' pipe lengths.”

The criteria proposed by the Director of Public Works, Burgess, requires that:

“(d) All pipe between 12" and 72" to be in 12 foot lengths, except at junctions or where conditions would prohibit or make more costly the use of 12 ft. lengths then shorter lengths may be permitted
*143 with (the) Director of Dept, of Public Works permission.”

Plaintiff, or rather the corporation he heads, Stevens Concrete Pipe & Products, Inc., is a pipe manufacturer equipped to make pipe in 8-foot lengths only. While it has the machinery which can be converted to the manufacture of twelve foot pipe, this would be costly and is estimated to be $150,000. On this phase of the case, the trial judge observes:

“The evidence further reflects that the only plant in the Baton Rouge area that can competitively make twelve foot pipe in the sizes established by the criteria is the Anderson-Dunham plant in Baton Rouge. In order to make pipe in this size, the Dunham plant ordered a PH-72 McCracken pipe machine and in January of this year produced the first twelve foot Packerhead pipe.
“Neither the Holloway plant in Alexandria nor the T. L. James plant in Mandeville are capable at the present time of producing pipe to meet these criteria.
“The plaintiff has also purchased the same machine, but in order to make pipe in the sizes established by the criteria, the plaintiff would have to redesign his present plant at a considerable expense.”

Primarily, plaintiff alleges that the action of the City-Parish Council is capricious and arbitrary in requiring the use of twelve foot pipe in pipe between 12" and 72" in diameter. In an amended petition it is asserted:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Louisiana Associated Gen. Contr. v. Calcasieu
586 So. 2d 1354 (Supreme Court of Louisiana, 1991)
Associated Gen. Contractors v. Calcasieu Parish School Board
572 So. 2d 623 (Louisiana Court of Appeal, 1991)
City of Thibodaux v. Hillman
464 So. 2d 370 (Louisiana Court of Appeal, 1985)
Henning v. Carrier
430 So. 2d 1310 (Louisiana Court of Appeal, 1983)
Delta Bank & Trust Co. v. Lassiter
383 So. 2d 330 (Supreme Court of Louisiana, 1980)
State ex rel. Guste v. City of Baton Rouge
327 So. 2d 661 (Louisiana Court of Appeal, 1976)
Davis v. Humble Oil & Refining Company
283 So. 2d 783 (Louisiana Court of Appeal, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
209 So. 2d 733, 252 La. 136, 1968 La. LEXIS 3044, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stevens-concrete-pipe-products-inc-v-burgess-la-1968.