Steven A. Hamner and Christine Arnold Hamner v. Robert Brent Hull, Brenda Hull, and Blue Ridge Construction Group, Inc.

CourtIntermediate Court of Appeals of West Virginia
DecidedDecember 23, 2024
Docket23-ica-565
StatusPublished

This text of Steven A. Hamner and Christine Arnold Hamner v. Robert Brent Hull, Brenda Hull, and Blue Ridge Construction Group, Inc. (Steven A. Hamner and Christine Arnold Hamner v. Robert Brent Hull, Brenda Hull, and Blue Ridge Construction Group, Inc.) is published on Counsel Stack Legal Research, covering Intermediate Court of Appeals of West Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steven A. Hamner and Christine Arnold Hamner v. Robert Brent Hull, Brenda Hull, and Blue Ridge Construction Group, Inc., (W. Va. Ct. App. 2024).

Opinion

IN THE INTERMEDIATE COURT OF APPEALS OF WEST VIRGINIA FILED STEVEN A. HAMNER and December 23, 2024 ASHLEY N. DEEM, CHIEF DEPUTY CLERK CHRISTINE ARNOLD HAMNER, INTERMEDIATE COURT OF APPEALS Plaintiffs Below, Petitioners OF WEST VIRGINIA

v.) No. 23-ICA-565 (Cir. Ct. Upshur Cnty. Case No. CC-49-2018-P-49)

ROBERT BRENT HULL, BRENDA HULL, and BLUE RIDGE CONSTRUCTION GROUP, INC., Defendants Below, Respondents

MEMORANDUM DECISION

Petitioners Steven A. Hamner and Christine Arnold Hamner (the “Hamners”) appeal the October 30, 2023, and November 17, 2023, orders from the Circuit Court of Upshur County. Respondents Robert Brent Hull, Brenda Hull (the “Hulls”), and Blue Ridge Construction Group filed a response with cross assignments of error challenging the November 17, 2023, order.1

This Court has jurisdiction over this appeal pursuant to West Virginia Code § 51- 11-4 (2024). After considering the parties’ arguments, the record on appeal, and the applicable law, this Court finds no substantial question of law and no prejudicial error. For these reasons, a memorandum decision affirming the circuit court’s order is appropriate under Rule 21 of the Rules of Appellate Procedure.

The underlying case arose from a dispute between adjoining landowners. On August 14, 2018 (“Original Litigation”), the Hamners filed a petition in circuit court to quiet title and for declaratory judgment regarding a road on their property. The road serves as the designated right of way the Hulls use to access their 105-acre and 15-acre tracts of land adjoining the Hamners’ property. However, of the two tracts, the issues on appeal only concern the 15-acre tract that was purchased by the Hulls in 2017.

The Original Litigation was decided by an amended order dated September 27, 2019 (“September 2019 Order”). In that order, the circuit court found that the record established:

1 The Hamners are represented by Anthony M. Salvatore, Esq. The Hulls and Blue Ridge Construction Group, Inc. are represented by Bridgette R. Wilson, Esq., and Robert C. Chenoweth, Esq. 1 a. The parcels all have access by the way of “Grub Hollow” road which is partially maintained by the WV Department of Highways and designated as County Route 43/20. b. From the end of the WVDOH maintenance, the “private” road is for access by the individual landowners in the deeds referenced in [the Landman’s] report. c. The “use” of this lane is described throughout the various chains of title and eventually included in the sale of the Snyder Property as part of the residue. d. The right to use the road was granted in the chains of title in the chains of title and the actual ownership was not granted until the “residue property” was sold and it was part of the residue tract.

Thereafter, the circuit court concluded:

1. The Court FINDS that the [Hulls] have a right to access and use the road between the end of “Grub Hollow” Road and their properties free of interference by the [Hamners] or any other persons. 2. The Court FINDS that any altering, placing of impediments, or interference with the [Hulls’] use of this road is contrary to the provisions set forth in the deeds of the various parcels relevant to this action.

This order also directed that the Hamners “shall not interfere, with the [Hulls’] use of the road,” and ordered the Hamners “to not block, alter, or perform construction on the road, except for routine maintenance and restoration of the road[.]” The Hamners were also directed to return the road to its pre-suit condition within thirty days. The September 2019 Order was not appealed.

Significant here, is that at some time prior to the Original Litigation, the Hulls installed a culvert pipe across the road to prevent water from impeding their ingress and egress across the right of way to their 15-acre tract. However, in July 2023, the Hamners removed the culvert pipe, took it to another location, and blocked the right of way, which prevented the Hulls’ access to the 15-acre tract. Thereafter, the Hulls removed the blockade and installed a temporary culvert at their own expense of $2,600.00. However, this did not return the property to its original condition prior to the Hamners removing the culvert pipe and blocking the road. The cost to return the road its original condition was estimated to cost $6,150.89, which included $2,958.00 to purchase replacement culvert pipe.

On August 24, 2023, the Hulls filed a “Motion to Reopen Matter and Hold Petitioners in Contempt of this Court’s Order.” The Motion gave a brief recitation of the Original Litigation, quoted language from the governing September 2019 Order, and alleged that the Hamners’ removal of the culvert in July 2023 violated the same. The Motion requested the Hamners be held in contempt and sanctioned. The Hulls also made

2 separate requests for an award of attorney’s fees and court costs; damages for emotional distress, inconvenience, and anguish; costs and fees associated with the remediation of the damages caused by the Hamners; as well as any other damages the circuit court deemed appropriate.

The circuit court heard the motion on October 19, 2023, and issued an order on October 30, 2023, memorializing its findings of fact and conclusions of law. The order referenced its findings in the September 2019 Order, as well as made additional findings with respect to subsequent actions taken by the parties regarding the 15-acre tract since July 2023. Based upon those findings, the circuit court made the following conclusions of law:

17. This Court took testimony and litigated the issues regarding Grub Hollow Road and the right of way over it before it entered its Orders in September 2019. This Court will not relitigate that action.

18. The Court finds and so ORDERS that Grub Hollow Road as it exists from Route 20 in Upshur County, WV to the 105-acre parcel currently owned by the Hulls is the right-of-way granted through the chain of title to the 105-acre parcel. The 105-acre parcel was granted a right of way through its chain of title over the property currently owned by the Hamners.

19. The Court finds and so ORDERS that Grub Hollow Road as it exists from Route 20 in Upshur County, WV to the 15-acre parcel owned by the Hulls is the right-of-way granted through the chain of title to the 15-acre parcel of property. This includes a small section that cuts off of the right of way to the 105-acre parcel as it now exists, and where the culvert was removed by the Petitioners. The 15-acre parcel was granted a right of way through its chain of title over the property currently owned by the Hamners.

20. Stephen [sic] Hamner is ORDERED to return the culvert which he took from the Hulls to the place where it was located originally within 72 hours of this hearing.

21. Brent Hamner [sic] is ORDERED to look at the culvert to confirm that it is usable and that it has not been damaged in any way. He is further directed to obtain photos of the culvert to submit to the Court should the culvert be unusable. In such a case, the Court will review how to proceed.

22. Brent Hull is ORDERED to use the old culvert if possible when reinstalling it and returning the property to its original condition.

3 23. The Respondents are ORDERED to present to the Court an invoice for the work to return the property to its original condition.

24. It is ORDERED that the Petitioners are to pay the Hulls for the reinstallation of the culvert and returning the property to its original condition. Those amounts will be presented by separate order.

25. The Court directs the attorney for the Respondents to submit an invoice to the Court for time spent and costs incurred in bringing this action to reopen the matter and hold the Petitioners in contempt of Court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Checker Leasing, Inc. v. Sorbello
382 S.E.2d 36 (West Virginia Supreme Court, 1989)
Carter v. Carter
470 S.E.2d 193 (West Virginia Supreme Court, 1996)
Walker v. West Virginia Ethics Commission.
492 S.E.2d 167 (West Virginia Supreme Court, 1997)
State v. Thompson
647 S.E.2d 526 (West Virginia Supreme Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Steven A. Hamner and Christine Arnold Hamner v. Robert Brent Hull, Brenda Hull, and Blue Ridge Construction Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/steven-a-hamner-and-christine-arnold-hamner-v-robert-brent-hull-brenda-wvactapp-2024.