Steuben Lakes Regional Waste District v. Tucker

904 N.E.2d 718, 2009 Ind. App. LEXIS 840, 2009 WL 1124456
CourtIndiana Court of Appeals
DecidedApril 24, 2009
Docket76A03-0812-CV-621
StatusPublished
Cited by4 cases

This text of 904 N.E.2d 718 (Steuben Lakes Regional Waste District v. Tucker) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steuben Lakes Regional Waste District v. Tucker, 904 N.E.2d 718, 2009 Ind. App. LEXIS 840, 2009 WL 1124456 (Ind. Ct. App. 2009).

Opinion

OPINION

BARNES, Judge.

Case Summary

The Steuben Lakes Regional Waste District ("the Waste District") appeals the trial court's grant of summary judgment in favor of Lyndon and Kathleen Tucker. We affirm.

Issue

The Waste District raises three issues, which we consolidate and restate as whether the trial court properly entered summary judgment in favor of the Tuckers.

Facts

The Tuckers own property in Steuben County. In 2002, the Waste District designed a new waste treatment plant and sewage collection system. The system required the installation of grinder pumps on some residents' property that would be maintained by the Waste District. To complete the system, the Waste District needed to obtain temporary construction and permanent easements from the affect *720 ed property owners, including the Tuckers. The Waste District calculated that the cost for the connection was $8,191.60, but because it "negotiated various funding," it was able to offer a reduced connection charge of $2,775.00 for property owners "who timely and voluntarily registered for connection to the new system{[.]" App. pp. 37-38.

Initially, the Tuckers agreed to the connection and also agreed to issue the necessary easements. However, a dispute arose regarding the specific location of the easement that the Tuckers were willing to give the Waste District. 1 On October 14, 2004, the Waste District informed the Tuckers that if they did not grant "an acceptable" easement, the cost of the connection would increase to "around $8,000.00." Id. at 51.

On July 14, 2005, the Tuckers filed a complaint for declaratory judgment against the Waste District. The Tuckers alleged that the Waste District's demand for an easement was unconstitutional. On August 2, 2005, the Waste District answered the Tuckers' complaint and counter-claimed, alleging that the Tuckers' refusal to consent to the connection of the sewer system resulted in the lost opportunity to exercise the discount negotiated by the Waste District. The Waste District requested that the trial court order the Tuckers to connect to the sewer system at the full connection charge of $8,191.60 and to pay the Waste District's costs and attorney fees.

On February 9, 2007, the Waste District moved for summary judgment. On March 283, 2007, the Tuckers filed a memorandum in opposition to summary judgment. On April 5, 2007, the Waste District replied. On June 28, 2007, the Waste District notified the trial court that the parties had reached an agreement regarding the location of the easement and that an easement had been recorded. The Waste District requested the trial court to "schedule a hearing on the remaining issues in this case, including but not limited to costs and fees." Id. at 61.

On March 26, 2008, a summary judgment hearing was held. On October 9, 2008, the trial court granted summary judgment in favor of the Tuckers. The trial court reasoned that the Water District created a "Constitutional dilemma" for the Tuckers by forcing them to either surrender their right to a condemnation proceeding or pay a higher connection charge and attorney fees. Id. at 8. The trial court ordered the Tuckers to pay the $2,775.00 connection charge plus pre-judgment interest and ordered the parties to pay their own attorney fees. The Waste District filed a motion to correct error, which the trial court denied. The Waste District now appeals.

Analysis

The Waste District argues that the trial court improperly granted summary judgment in favor of the Tuckers. When reviewing the grant or denial of summary judgment, we use the same standard of review as the trial court. Naugle v. Beech Grove City Schs., 864 N.E.2d 1058, 1062 (Ind.2007). "Summary judgment is appropriate only where the evidence shows that there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law." Id. (citing Ind. Trial Rule 56(C)). "All facts and reasonable inferences drawn from those facts are construed in favor of the non-moving party." Id. Our review is limited to those materials designated in the trial court un *721 der Indiana Trial Rule 56(C). Id. "When any party has moved for summary judgment, the court may grant summary judgment for any other party upon the issues raised by the motion although no motion for summary judgment is filed by such party." TR. 56(B). Finally, we will af firm summary judgment if it may be sustained on any theory or basis found in the record. Yates v. Johnson County Bd. of Comm'rs, 888 N.E.2d 842, 847 (Ind.Ct.App.2008).

The Waste District first argues that because the Tuckers granted it an easement, "the issues relating to the easement were moot and it was error for the Court to address those issues in its Summary Judgment Order." Appellant's Br. p. 7. Indeed, the actual execution of an easement by the Tuckers is a moot issue. See Lake County Bd. of Elections and Registration v. Copeland, 880 N.E.2d 1288, 1291 (Ind.Ct.App.2008) ("Generally, an issue is deemed to be moot when the case is no longer live and the parties lack a legally cognizable interest in the outcome of its resolution or where no effective relief can be rendered to the parties."). Nevertheless, by the Waste District's own assertion in its notice concerning the execution of the easement, the issues of the connection charge, litigation costs, and attorney fees arising out of the easement issue remained unresolved even after the Tuckers executed the easement. In that regard, it was proper for the trial court to consider the facts of the case to resolve these issues.

The Waste District argues that it was permitted to offer the Tuckers a reduced connection charge of $2,775.00 if they voluntarily provided it with the requested easement and connected to the sewer. Because the Tuckers did not provide the requested easement, the Waste District claims it is entitled to recover the $8,190.60 connection charge.

As the Waste District points out, it may "collect reasonable rates and other charges" for the purpose of "construction, acquisition, improvement, extension, repair, maintenance, and operation of the district's facilities and properties." Ind. Code § 13-26-5-2(7)(B). It may also require connection to the sewer system. 2 1.C. § 18-26-5-2-(8). The Waste District, however, points to no statutory authority allowing it assess higher connection charges for residents who do not voluntarily provide easements.

Relying on Goodpasture v. Tennessee Valley Authority, 484 F.2d 760

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
904 N.E.2d 718, 2009 Ind. App. LEXIS 840, 2009 WL 1124456, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steuben-lakes-regional-waste-district-v-tucker-indctapp-2009.