Sternberg Dredging Co. v. Dawson

261 S.W. 286, 164 Ark. 24, 1924 Ark. LEXIS 360
CourtSupreme Court of Arkansas
DecidedApril 21, 1924
StatusPublished
Cited by3 cases

This text of 261 S.W. 286 (Sternberg Dredging Co. v. Dawson) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sternberg Dredging Co. v. Dawson, 261 S.W. 286, 164 Ark. 24, 1924 Ark. LEXIS 360 (Ark. 1924).

Opinion

Wood, J.

Drainage District No. 7 of Poinsett County, Arkansas, was created by act 193 of the Acts of the G-eneral Assembly of 1917. The directors of the district entered into a contract with the appellants for the construction of the improvement. The appellants, in turn, on September 14, 1920, entered into a contract with the appellee and one Stevenson, to clear the right-of-way for what is designated as Improvement No. 59 of District No. 7 of Poinsett County. Stevenson later transferred his interest to the appellee. The consideration to be paid the appellee was $75 per acre, payment to be made on monthly estimates of work done, which were to be furnished by the engineers of the district. Appellee was to do the work according to the specifications contained in the contract. The contract (inter alia) contained the following provision: “It is understood and agreed that the plans and specifications of Drainage District No. 7 pertaining to the right-of-way clearing for said levee work shall be made a part of this agreement as if hereto attached and herein recited.”

The original Improvement No. 59, as shown by the plat thereof prepared by the engineer of the district, contemplated the construction of a ditch from the east line of section 30, township 12 north, range 7 east, thence in a southwesterly direction through section 30, township 12 N., E. 7 E., and section 25 to near the center on the south line of section 26, T. 12 N., E. 6 E.; thence in a northwesterly direction through sections 26, 27, 22, 15,16, 9 and 4, in T. 12 N., E. 6 E., to the north boundary of Poinsett County. On the 23rd of November, 1920, appellee agreed to release to the appellants the contract for clearing beginning on the south line of - section 15, T. 12 N., E. 6 E., running north to the county line. The appellee proceeded with the work under his contract until about the 18th of Februarv, 1921, when he received notice from the auriellants to discontinue the work, as the district had ordered it shut down, or changed its location. Thereafter, some time between this date and. the first of the year 1922, the plans of the district were changed so as to provide for the construction of a ditch from the east line of section 30, T. 12 N., R. 7 E., thence in a southwesterly direction to a point near the southwest corner of section 25, T. 12 N., R. 6 E.; thence north on the west section line of section 25 to the northwest corner, and thence northeasterly across section 24 to a point about a quarter of a mile *west of the east line of section-13, T. 12 N., R. 6 E.; thence north on a straight line through sections 13, 12 and 1 to the county line.

Before the last change of plans was adopted, appellee had cleared about 114 acres of the right-of-way, for which he had been paid. After the plans were changed as indicated, appellee, on January 13,1922, received from the appellants a letter in which they inquired of the appellee if he was interested in clearing the right-of-way of Improvement No. 59, and offering to pay him $50 an acre for clearing the right-of-way according to the plans and specifications of District No. 7, and stating that this offer was subject to prior acceptance by other right-of-way contractors who were bidding’ on the work, and also stated that, inasmuch as the appellee was in close proximity to the work and had plenty of teams and force of men, appellants believed that the price would be very attractive to the appellee and enable him to make a reasonable profit on the work. Appellee, in reply to this letter, told the appellants that he was ready to comply with his contract; that he already had a contract with the appellants, and was ready to proceed with it. The appellants, in answer to appellee’s letter, stated that they considered the old contract covering the right-of-way clearing on Improvement 59 null and void; that they had settled with appellee in full for the work which he had done, and were then working on a change of plans, and could not consider the old contract as having any connection with the clearing to be done on the new location of Improvement No. 59, and advising appellee that they had let the work to another party.

Appellee instituted this action against the appellants, and alleged that appellants had abandoned their contract with him and had relet the work of clearing the right-of-way of Improvement No. 59 to other parties; that, at the time appellants abandoned their contract, there were 125 acres of right-of-way still to be cleared, which appellants had relet at the sum of $50 per acre. Appellee set up that he was damaged by reason of such breach of contract on the part of the appellants in the sum of $5,000, for which he prayed judgment.

The appellants answered, denying breach of the contract on their part, and admitted that they had let a new contract for the clearing of approximately 125 acres to other parties at $50 per acre. They admitted that they had entered into the original contract with the appellee as claimed by him, but alleged that the appellants had been notified that there had been a change in the plans of the District No. 7 whereby Improvement No. 59 of such district as originally planned was to be changed to a new location as shown on the new plans and specifications and plat prepared by the engineers of the district ; that the new plans provided for an entirely different amount and character of right-of-way work from that done under the first plan and original contract; that, immediately upon the change of plans by the district, the appellee was notified by the appellants, and they requested him to bid on the work as relocated, and enter into a new contract, all of which appellee did not do, and therefore appellants let the contract for the new work to other parties. The appellants further set up that, iby reason of the change of the plans on the part of the district, appellants’ original contracts with the district and with the appellee for the clearing of the right-of-way were abrogated. Appellants further set up that they had made final settlement with the appellee for all work and labor done by him under their contract, and had paid in full for such work, and that such settlement was in the nature of an accord and satisfaction of all claims of the appellee against the appellants.

The appellants filed a cross-action against the appellee for damages growing out of an alleged wrongful attachment. The appellee denied the allegations of the cross-action. In the attachment proceedings the appellants executed a bond and had the attached property released.

The above are the issues, so far as it is necessary to set them forth. In addition to the facts already stated, which are undisputed, the appellee testified, in regard to the alleged settlement with the appellants, that they paid appellee what they claimed was a legitimate estimate on what he had done. They paid a percentage on what they said was done. There were about ten acres on which nothing had been done. There were approximately four miles difference between the termination of the old right-of-way and the new right-of-way of Improvement No. 59. It would probably be around two miles apart at the point where the right-of-way turns in a northeasterly direction. Appellee was trying for about two months to get appellants to settle for his work done ón Improvement No. 59. They would not settle until they got a settlement with the district. That was in April of 1921. The work done in February was not settled for then. Appellee did not say anything to the appellants in effect that the settlement then had was a completion of the contract, or that he had abandoned his contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blair v. United States Ex Rel. Gregory-Hogan
147 F.2d 840 (Eighth Circuit, 1945)
Ozan Graysonia Lumber Co. v. Ward
66 S.W.2d 1074 (Supreme Court of Arkansas, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
261 S.W. 286, 164 Ark. 24, 1924 Ark. LEXIS 360, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sternberg-dredging-co-v-dawson-ark-1924.