Sterling Packaging Corp. v. Systec Corp. (In Re Sterling Packaging Corp.)

265 B.R. 701, 46 Collier Bankr. Cas. 2d 1222, 2001 Bankr. LEXIS 1038, 38 Bankr. Ct. Dec. (CRR) 78, 2001 WL 957406
CourtUnited States Bankruptcy Court, W.D. Pennsylvania
DecidedAugust 22, 2001
Docket19-20172
StatusPublished
Cited by1 cases

This text of 265 B.R. 701 (Sterling Packaging Corp. v. Systec Corp. (In Re Sterling Packaging Corp.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sterling Packaging Corp. v. Systec Corp. (In Re Sterling Packaging Corp.), 265 B.R. 701, 46 Collier Bankr. Cas. 2d 1222, 2001 Bankr. LEXIS 1038, 38 Bankr. Ct. Dec. (CRR) 78, 2001 WL 957406 (Pa. 2001).

Opinion

MEMORANDUM OPINION

BERNARD MARKOVITZ, Bankruptcy Judge.

Debtor Sterling Packaging Corporation has objected to the secured claim of Systec Corporation (“Systec”) and contends that Systec’s claim should be disallowed in its entirety. Alternatively, to the extent the claim is allowed, debtor asserts that it is completely offset by a counterclaim debtor has asserted against Systec. Debtor also contends that any allowed claim Systec has is unsecured rather than secured because the mechanic’s lien securing the claim of Systec was divested or extinguished by debtor’s confirmed chapter 11 plan of reorganization.

For reasons set forth in this memorandum opinion, we conclude that debtor’s objection to the claim of Systec must be overruled and that the claim should be allowed in its entirety, debtor’s counterclaim notwithstanding. We further conclude that Systec’s lien was not divested or extinguished by debtor’s confirmed chapter 11 plan of reorganization and therefore passed through this bankruptcy case unaffected.

— FACTS —

Debtor is in the business of producing cardboard cartons.

Systec is in the business of designing and installing conveyor systems for industrial uses.

*703 Prior to 1998, debtor operated at two locations, one in Jeannette, Pennsylvania, and the other in Jonestown, Pennsylvania. After losing its biggest customer, debtor closed its Jonestown plant early in 1998 and consolidated its operations at the Jeannette location.

Due to the consolidation, debtor needed to expand and upgrade the conveyor system at its Jeannette plant to handle increased traffic. Debtor approached Systec in February or March of 1998 about expanding and upgrading the conveyor system at its Jeanette plant.

On April 30,1998, after extensive discussions with debtor, Systec issued an “Acknowledgment”, wherein it quoted a fixed price of $150,000.00 for upgrading and expanding the conveyor system then in place in Jeanette. Delivery of the required equipment within five to seven weeks after receipt of the order was listed as one of the terms of its proposal. The remainder of the proposed terms pertained to when debtor would pay for the equipment required to install the conveyor system and for its installation. The estimated shipment date of the equipment was during the week of June 27, 1998. The written proposal submitted by Systec contained no indication concerning when the upgraded conveyor system would be installed and fully operational.

On June 5, 1998, some five weeks later, debtor issued a purchase accepting Sys-tec’s proposal.

On June 26, 1998, just three weeks after debtor had issued its purchase order, Sys-tec delivered the new equipment for the upgraded conveyor system to the Jeannette location and began installing it that same day. Installation was hindered, however, by conditions at the plant that were not of Systec’s making. The roof and electrical system, for instance, were undergoing renovation at that time. Also, machinery and equipment belonging to debtor that was to be incorporated into the new conveyor system was buried beneath debris left by these renovations. Systec spent considerable time sifting through the debris and identifying items for utilization in the upgraded conveyor system.

Installation of the new conveyor system did not proceed as rapidly as debtor and Systec had hoped. On August 14, 1998, debtor’s vice-president for operations wrote to Systec identifying various unresolved problems with the newly-installed conveyor system and complaining that it was not yet operational. He complained, among other things, about the steepness of certain inclines and declines of the conveyors.

On September 18, 1998, after debtor and Systec agreed that certain modifications of the conveyor system were required to make it fully operational, debtor issued a change order for additional equipment to complete the modifications. It was agreed that debtor would pay for the cost of the additional equipment — $15,950.00—while Systec would install it at no additional cost to debtor.

On November 5, 1998, debtor’s vice-president for operations signed a field activity report prepared by Systec which asserted that the conveyor system was working as designed and that no further work by Systec was required to complete it. That same day, he also signed another field activity report Systec prepared which asserted that all necessary adjustments to the conveyor system had been made and that all three shifts at the plant had used the new conveyor system without interruption.

On November 6, 1998, debtor ordered additional unspecified equipment from Systec for use in operating the conveyor *704 system. The cost of the equipment totaled $337.70.

On January 6, 1999, after debtor had rejected Systec’s repeated requests for payment, Systec filed a notice of mechanic’s lien in the Court of Common of Common Pleas of Westmoreland County, Pennsylvania, the county in which debtor’s Jeannette plant was located. The total amount of the lien was $166,787.70, which included the initial quoted price of the system ($150,000.00), the cost of the equipment debtor ordered on September 18, 1998 ($15,950.00), and the cost of the equipment debtor ordered on November 6, 1998 ($337.70).

Systec brought suit against debtor in federal district court on February 1, 1999, seeking to recover the sum of $166,787.70, which Systec claimed debtor owed it for equipment and installation of the above conveyor system. Debtor responded that the work done by Systec was defective and incomplete and asserted a counterclaim in the amount of $447,728.00 for damages allegedly suffered.

Debtor filed a voluntary chapter 11 petition on April 1, 1999, thereby automatically staying Systec’s pending lawsuit against debtor in federal district court.

On June 16, 1999, Systec filed a secured claim in debtor’s bankruptcy case in the amount of $166,787.70 for goods and services rendered. Its claim arises out of debtor’s refusal to pay Systec for the above conveyor system Systec had installed in debtor’s Jeannette plant.

Debtor’s second amended plan of reorganization was confirmed on April 28, 2000. Neither the plan nor the order confirming it expressly dealt with Systec’s claim or with its statutory lien. The same is true of a consent order modifying the plan which issued on June 26, 2000.

Debtor eventually objected to Systec’s secured claim on August 4, 2000. According to debtor, it was a provision of its agreement with Systec that the conveyor system would be fully operational by the beginning of July of 1998. Debtor asserted that Systec’s claim should be denied because the conveyor system was neither installed nor fully operational by the beginning of July of 1998 or at any time thereafter. According to debtor, it had to hire someone else to make it fully operational. Any claim Systec may have, debtor further argues, is completely offset by its counterclaim for damages it suffered as the result of Systec’s failure to install a fully operational conveyor system by the beginning of July of 1998 or at any time thereafter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dollar Bank, FSB v. Tarbuck (In re Tarbuck)
304 B.R. 718 (W.D. Pennsylvania, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
265 B.R. 701, 46 Collier Bankr. Cas. 2d 1222, 2001 Bankr. LEXIS 1038, 38 Bankr. Ct. Dec. (CRR) 78, 2001 WL 957406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sterling-packaging-corp-v-systec-corp-in-re-sterling-packaging-corp-pawb-2001.