Sterling-Kates Properties Joint Venture v. United States

5 Cl. Ct. 398, 1983 U.S. Claims LEXIS 1819
United States Court of Claims·Decided March 21, 1983·No. No. 602-81C·Published·Cited by 3 cases

Opinion

ORDER RE: DEFENDANT’S MOTION FOR LEAVE TO FILE PRETRIAL STATEMENT OUT-OF-TIME

YANNELLO, Judge.

Background

At all times relevant to this order defendant’s counsel has continued to be its present attorney of record.

On September 8, 1982, the trial judge issued a Standard Pretrial Order requiring submissions from the parties as follows: plaintiff’s submission was due on November 15; defendant’s submission and response was due within 60 days of receipt of plaintiff’s submission; and plaintiff’s response was due within 30 days of receipt of defendant’s submission.

Presumably, immediately upon receipt of this pretrial order, counsel would note the schedule of proceedings required by such order.

Plaintiff’s submission was timely received on November 15, and defendant’s submission was then due on January 15, 1983.

Presumably, immediately upon receipt of plaintiff’s pretrial submission, counsel would note that a responsive submission was due and, by referring to the pretrial order, could again note the due-dates for such proceedings.

Defendant, on December 23, 1982, filed a motion for leave to file an amended answer (asserting a counterclaim) which motion was granted.

At the time of filing its amended answer, and again on February 4, 1983, when plaintiff responded to the amended answer, counsel could be expected to check the status of this case to determine what further proceedings were appropriate.*

[399] Notwithstanding all of the foregoing, defendant neither furnished its pretrial submission nor requested any enlargement of time as of March 1, 1983.

At that time, the judge advised the parties that, since defendant’s time had expired and no pretrial submission had been received, the case was ready to go to trial based on the plaintiff’s pretrial submission and the parties were requested to furnish a schedule of convenient dates for trial.

On March 9, 1983, defendant filed a motion for leave to file its pretrial submission out-of-time and alleged, in support thereof, that:

counsel assigned to this matter neglected to record the date this submission was due on his calendar and, as a result, defendant’s counsel was unaware that the time for filing this submission had passed.

Plaintiff responded in opposition on March 17, and noted that the defendant had failed to meet the criteria and the standards announced in Whorton v. United States, 1 Cl.Ct. 41 (1982) (Kozinski, C.J.).

DISCUSSION

The Whorton decision, supra, while not binding on the court in all cases, nonetheless is well-reasoned and persuasive.

In the instant case particularly, the arguments offered in support of defendant’s motion are meager to say the least. While these arguments point to obvious neglect on the part of counsel, they offer no explanation for such neglect — either excusable or inexcusable.

Moreover, as the background of this case clearly indicates, counsel has had a number of opportunities for noting the schedules of pretrial proceedings and can reasonably have been expected to take note of its due-dates on more than one occasion.

Accordingly, based on the motions now before it, the court issues the following order.

DECISION

IT IS HEREBY ORDERED THAT defendant’s motion for leave filed March 9, 1983, is DENIED.

The matter will proceed to trial, on the question of whether the default termination of plaintiff’s contract was valid. Plaintiff will, of course, be required to sustain its burdens of proof, with the defendant entitled to full rights of cross-examination of the witnesses listed by plaintiff and scheduled to testify. However, defendant, having failed to submit a pretrial statement, will not be permitted to call additional witnesses or to introduce additional exhibits.

The plaintiff’s pretrial statement was filed before the assertion of defendant’s counterclaim, and might, in any case, not have initially addressed the subject of defendant’s claims. Thus, the present trial will not address the questions raised by that counterclaim, but if it is determined that the default termination of plaintiff’s contract was valid, further pretrial will be scheduled on the issues of whether the defendant is entitled to an assessment of excess reprocurement cost and, if so, the appropriate amount thereof.

ON MOTION FOR RECONSIDERATION

On March 21, 1983, the judge issued an Order denying defendant’s motion for leave to proceed with submission of its Pretrial Statement on Liability out of time.

By motion of March 29, the defendant seeks reconsideration of that Order. Plain[400] tiff responded in opposition on April 12, and defendant replied on April 14 and 19, 1983.

Defendant does not dispute the court’s conclusion that the reasons set forth in defendant’s motion for leave for its delay in complying with the original due dates for submission of its pretrial submission were insufficient to warrant a finding of excusable neglect, or other finding of justification.

Rather, defendant now seeks to be permitted to proceed with a pretrial statement and with the introduction of evidence at trial for the reason, essentially, that the court’s order of March 21

[has] worked an extremely severe prejudice against defendant, wholly disproportionate to the inconvenience defendant’s counsel’s inadvertence has caused the court and plaintiff.

At the outset it must be noted that this is not a situation where a party, in good faith, submits a pretrial statement which is then exceeded during trial in order to meet the unforeseeable exigencies of such a proceeding. Nor is this a situation where the scope of pretrial, or the initial pleadings, is exceeded by the evidence by agreement of (or without objection by) the parties (see, e.g., plaintiff’s opposition to defendant’s motion.)

More importantly, this is not a situation where a party is seeking an extension of time in which to file a pretrial submission and states, as one (but by no means controlling) element in support thereof, that the requested extension will not prejudice either the opposing party or the court.

Rather, this is a situation in which the party has wholly failed — without offering any justifiable excuse whatever for its neglect — to adhere to the court’s order requiring the timely submission of a pretrial statement.

The defendant attempts to vitiate its earlier omission by proffering, out of time, the required pretrial statement, and by urging that it is merely proceeding in a somewhat extended period of time.

However, such a proffer would be cognizable only if the party were granted leave to proceed out of time, recognizing the excusable or justifiable nature of its initial neglect. Here, such leave has not been granted because defendant has not offered such justification.

The ultimate furnishing of a pretrial submission does not serve to eliminate the need for the delinquent party to establish that its failure to proceed in a timely manner, in accord with the court’s orders, is justified and/or due to excusable neglect.

Free access — add to your briefcase to read the full text and ask questions with AI

Sterling-Kates Properties Joint Venture v. United States, 5 Cl. Ct. 398, 1983 U.S. Claims LEXIS 1819 (cc 1983).

5 Cl. Ct. 398 (Sterling-Kates Properties Joint Venture v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hey v. United States
5 Cl. Ct. 482 (Court of Claims, 1984)