Stephenson v. Vastar Resources, Inc.

89 S.W.3d 790, 2002 Tex. App. LEXIS 7643, 2002 WL 31398689
CourtCourt of Appeals of Texas
DecidedOctober 24, 2002
Docket13-01-702-CV
StatusPublished
Cited by8 cases

This text of 89 S.W.3d 790 (Stephenson v. Vastar Resources, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stephenson v. Vastar Resources, Inc., 89 S.W.3d 790, 2002 Tex. App. LEXIS 7643, 2002 WL 31398689 (Tex. Ct. App. 2002).

Opinion

OPINION

Opinion by Justice AMIDEI (Assigned).

Surface owners sued a pipeline operator to enjoin it from using and operating a pipeline across their land in Orange County, Texas, and to terminate the easement granting the pipeline right-of-way. Lloyd Glenn Stephenson, Jr. and Beverly Stephenson, appellants, appeal from a summary judgment granted in favor of Vastar Resources, Inc., appellees, and the denial of their motion for partial summary judgment.

Appellants claim in one issue, as a matter of law: (1) the easement has terminated; (2) appellee did not comply with the easement; and (3) appellee cannot transmit through the pipelines oil and gas which comes from sources outside the land which is a part of the mineral estate over the land. Appellee claims the issue is whether the trial court erred in granting its motion for summary judgment and denying appellants’ motion for partial summary judgment, when as a matter of law, (a) the 1924 easement has not terminated or reverted, (b) appellee as the dominant estate owner properly exercised its rights under the easement, (c) appellee properly exercised its rights reserved or obtained by virtue of two deeds, and (d) the appellants were not entitled to a permanent injunction under the well-established rules of equity. While the parties did not agree on the answer to these issues, they seem to agree there are *792 no issues of fact and the determination of the case should be as a matter of law.

Standard of Review

A party moving for summary judgment must establish its right to summary judgment on the issues expressly presented to the trial court by conclusively proving all elements of its cause of action or defense as a matter of law. Elliott-Williams Co., Inc. v. Diaz, 9 S.W.3d 801, 803 (Tex.1999).

Contract construction is a matter of law for the trial court. Id.

It is well settled that the rules which control the courts in the construction of easements are, in general, the same as those applied to the construction of deeds and other written instruments. Knox v. Pioneer Natural Gas Co., 321 S.W.2d 596, 602 (Tex.Civ.App.-El Paso 1959, writ ref'd n.r.e.).

A defendant moving for a traditional summary judgment on the whole case has the burden of establishing that, as a matter of law, the plaintiff has no cause of action against the defendant. Am. Tobacco Co., Inc. v. Grinnell, 951 S.W.2d 420, 434 (Tex.1997); 3 Roy W. McDonald & Elaine A. Grafton Carlson, Texas Civil PRACTICE (2d ed. 2000) § 18:8, note 77.

The grant or refusal of a permanent or temporary injunction is ordinarily within the trial court’s sound discretion, and on appeal, review of the trial court’s action is limited to the question of whether the trial court’s action constituted a clear abuse of discretion. Morris v. Collins, 881 S.W.2d 138, 140 (Tex.App.-Houston [1st Dist.] 1994, writ denied).

Procedural and Factual Background

Appellants’ suit: (1) alleges that the easement which originally granted the right-of-way for appellee’s pipeline, which crosses appellants’ property, terminated by its terms because of its non-use for two years, and (2) seeks an order to prevent further use and the removal of the pipeline on a trespass theory. Appellee’s motion for summary judgment on all claims was granted. Appellants’ motion for partial summary judgment claiming trespass and requesting a permanent injunction was denied. Appellants’ damage and separator tank claims were severed into a separate cause.

Appellee is the owner of the fee mineral estate under approximately 775,030 acres of land located within Jasper, Newton, Hardin, Tyler and Orange Counties, Texas. Appellants own the surface estate to 90 acres in Orange County located within said 775,030 acres. Also, appellee owns two pipelines, one 18" in diameter and the other 10" in diameter, which cross appellants’ land, although portions of the 18" line remaining on appellants’ land only serve as a conduit for the newer 10" pipeline. The 18" pipeline was originally installed, used and maintained by appellee’s predecessors-in-interest pursuant to an easement granted in 1924, which provides in pertinent part as follows:

WITNESSETH:
That the Party of the First Part, ... does hereby grant unto the Party of the Second Part a right-of-way to lay, construct, maintain, operate, repair and remove an oil and gas pipeline ... over, through, and upon ... the following lands....
... and shall have at all reasonable times the right of ingress to and egress from said lands for the purpose of laying, constructing, maintaining, operating, repairing, and removing, in whole or in part, ... said pipeline....
... grants ... the right to lay, construct, maintain, operate, repair and remove a second oil and gas pipeline over *793 the same lands and right-of-way granted above, parallel, and adjacent to the first pipeline and as near to same as practicable and in no event more than ten (10) feet therefrom, upon the payment ... of Twenty-five Cents ... per lineal rod. ... so long as the same shall be used for the purposes for which granted ... (Emphasis supplied)

The easement does not specify any required width or route of the right-of-way. The 10" pipeline was laid pursuant to rights and mineral estate ownership reserved under 1916 deeds, which provide in pertinent part as follows:

... save and except all oil and gas, on, in and under the same, all of which are expressly reserved from this conveyance, with perpetual rights of ingress and egress to prospect for, take, use, enjoy and remove same as fully as if this conveyance had not been made. Also, reserving in said Houston Oil Company of Texas, its successors and assigns, the further right to build, or otherwise acquire, and to use and maintain upon said premises, all such buildings, derricks, tanks, reservoirs, pipe lines, tram roads, railroads, telegraph lines, or other improvements or equipment of any character whatsoever, which the said Houston Oil Company of Texas, its successors or assigns, may find necessary, proper or convenient in taking, using, enjoying or removing said oil and gas from said lands, with perpetual right of ingress and egress to utilize said right. (Emphasis supplied).

Arguments, Discussion and Decision

Appellants claim that under paragraph VII of the 1924 easement, the easement terminated as of January 1997, prior to appellee’s acquisition of the pipeline because Midcon, appellee’s predecessor-in-interest, failed to use the 18" pipeline for a period of two years. Paragraph VII provides as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
89 S.W.3d 790, 2002 Tex. App. LEXIS 7643, 2002 WL 31398689, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stephenson-v-vastar-resources-inc-texapp-2002.