Stephens v. Morrison (In Re Morrison)

450 B.R. 734, 2011 WL 2144577
CourtUnited States Bankruptcy Court, W.D. Tennessee
DecidedMay 27, 2011
Docket19-21386
StatusPublished
Cited by12 cases

This text of 450 B.R. 734 (Stephens v. Morrison (In Re Morrison)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, W.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stephens v. Morrison (In Re Morrison), 450 B.R. 734, 2011 WL 2144577 (Tenn. 2011).

Opinion

MEMORANDUM OPINION RE: COMPLAINT OBJECTING TO DISCHARGEABILITY

G. HARVEY BOSWELL, Bankruptcy Judge.

The Court conducted a trial on the plaintiffs complaint objecting to dischargeability on April 4, 2011. Fed. R. Bankr.P. 7001. This matter is a core proceeding. 28 U.S.C. § 157(b)(2)(I) and J. The Court has reviewed the testimony from the hearing and the record as a whole. This memorandum opinion shall serve as the Court’s findings of fact and conclusions of law. Fed. R. Bankr.P. 7052.

Findings of Fact

The debtors in this case, Alabama Cheyenne Morrison and Crystal Dannette Morrison, (collectively “Debtors”), filed their chapter 7 petition for bankruptcy relief on December 4, 2009. On their Statement of Financial Affairs, under Item 4, “Suits and administrative proceedings, executions, garnishments, and attachments,” the Debtors listed a pending civil lawsuit in Benton County Chancery Court styled “Joseph Samuel Stephens vs. Alabama Morrison.”

The Debtors’ disclosure of the Chancery Court lawsuit was incorrect in two ways. First, the lawsuit was pending in Carroll County Chancery Court, not Benton County. Secondly, although the Debtors listed the status as “pending” at the time of filing, the Chancery Court had actually entered a default judgment against Alabama Morrison, (“Morrison”), on November 19, 2009, in the amount of $64,300 plus pre-judgment interest of 10% per annum since December 3, 2007. The judgment was for breach of an August 2, 2006, construction contract.

The state court breach of contract action arose out of a construction contract Joseph Stephens, (“Stephens”), entered into with ABC Remodeling in Bruceton, Tennessee, in the summer of 2006. As owner and operator of ABC, Alabama Morrison, (“Morrison”), submitted a bid to Stephens on July 1, 2006, which Stephens accepted on August 2, 2006. Pursuant to the terms of the signed contract, (“Contract”), Morrison agreed to renovate Stephens’ existing house at 27154 Highway 70 in Huntingdon, Tennessee, and to build an addition on to that house. As it was, Stephens’s house was approximately 1600 square feet and the addition would add approximately 1600 more square feet. The renovations to the existing house included removing and replacing all flooring, drywall, and light fixtures, building a trayed ceiling in the living *739 room, removing the fireplace, scraping and refinishing the ceilings, removing the back porch and carport, moving the primary entrance for electrical service to the house, painting and trimming the house and remodeling all transitions for the addition. The agreed upon price for the remodel and addition was originally set at $88,500. The price included all labor, services, and materials with the exception of the cabinets, windows, trim, hardwood, tile, light fixtures, doors and bathroom fixtures. Pursuant to the parties’ agreement, Stephens was to provide those supplies for the project.

The parties attached an “Estimated Schedule” to the contract which provided that the remodel and addition would begin on October 28, 2006, and be essentially completed by December 28, 2006. 1 At the time of entering into the Contract, Stephens’s wife, Dana Daniels, (“Daniels”), was three months pregnant. In light of this, Stephens specifically asked Morrison if he would be able to complete the project prior to the baby’s birth. Morrison assured him that the work would be finished and, as a result, Morrison prepared the expedited construction schedule.

Pursuant to the terms of the contract, the parties agreed that “[a]n Additional Charges sheet will be provided in the event any unforeseen changes need to be made. Both homeowner and contractor will need to sign off on these charges when they are made.” (Trial Exhibit 1). At some point during the project, 2 the parties executed an “Additional Charges Sheet” which provided that Morrison would remove and replace 9 windows in the existing house, add insulation in the existing structure attic, extend the addition by 153 square feet, remove and replace the existing air conditioner, add a trayed ceiling to the master bedroom, change ceiling height in the existing kitchen and den to 9 feet, add 2 headers for oversized doors, change the roof shingles and add 2 porches and 2 dormers. Stephens agreed to pay Morrison an additional $40,010 for these changes, bringing the total cost to be paid under the Contract to $128,510.00.

Although the Contract called for essential completion by December 2006, the project took longer than anticipated. Because of this, Stephens made payments under the contract over a period of approximately 18 months. Stephens disbursed a total of $128,871 to Morrison during this time period:

Date of Check Amount_

_6/27/06_$5000_

_7/19/06 $10,000_

_8/2/06 $10,000_

_9/8/06 $25,000_

_10/27/06 $25,000_

_12/19/06 $10,000_

_1/8/07 $15,000_

_7/9/07_$2,200_

_8/25/07 $12,800_

_11/20/07 $10,000_

_12/3/07 $3,871_

Stephens submitted copies of the cancelled checks for these payments as Trial Exhibit 3.

Despite the fact that Stephens had timely delivered all of the supplies he agreed to provide to the job site, Stephens testified that four months into the project Morrison had not started work on the Stephens’ home. When Stephens confronted Morrison about this, Morrison stated that he had other jobs going on at that time, but *740 he assured Stephens that he would get to their job and finish it timely.

Albeit grossly behind schedule, Morrison eventually did begin work on Stephens’ house. He did not, however, finish the project. The parties disagree as to the causes of the delay and the problems with completion of the project. According to the evidence presented at trial, including photos of the project submitted as collective exhibits 25 and 26, the testimony of Stephens and Morrison and the testimony from Carl Moore, a licensed contractor Stephens hired to complete the project, (“Moore”), the work Morrison completed included removing the roof and concrete pad on the existing carport, removing and replacing some of the brick on the exteri- or, removing all the windows in the existing house and replacing them with new ones, removing and replacing the existing air conditioner units, replacing most of the roof shingles, changing the ceiling height in the foyer, building the trayed ceilings in the living room and master bedroom, building the shell for the addition, installing windows in the addition, and beginning work on the 2 porches. Morrison did not, however, move the electrical service to a new location on the property nor did he complete the plumbing work inside the house. Although Morrison removed the old flooring, he did not install any new flooring in the house or addition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mey v. Phillips
M.D. Tennessee, 2025
Mey v. Thompson
M.D. Tennessee, 2025
Gregory Couch v. Panther Petroleum
704 F. App'x 569 (Sixth Circuit, 2017)
In re: Gregory Couch
Sixth Circuit, 2017
Driftwood Manor Owners Ass'n v. Borgus (In re Borgus)
544 B.R. 315 (E.D. North Carolina, 2016)
Anderson v. Fisher (In re Anderson)
520 B.R. 89 (Sixth Circuit, 2014)
In re: Kenneth Anderson v.
Sixth Circuit, 2014

Cite This Page — Counsel Stack

Bluebook (online)
450 B.R. 734, 2011 WL 2144577, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stephens-v-morrison-in-re-morrison-tnwb-2011.