STEPHEN M. McPARLAND, Trustee, & Another v. CONSERVATION COMMISSION OF BARNSTABLE.

Massachusetts Appeals Court·Decided July 14, 2025·No. 24-P-0675·Unpublished

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

24-P-675

STEPHEN M. McPARLAND, trustee,1 & another2

vs.

CONSERVATION COMMISSION OF BARNSTABLE.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

The plaintiffs, Stephen M. McParland and Beth F. McParland,

as trustees for the McParland Family 2014 Revocable Trust

(McParlands), brought an action in the nature of certiorari

under G. L. c. 249, § 4, challenging the denial by the

conservation commission of Barnstable (commission) of their

application to construct a permanent pier on their waterfront

property in Osterville (property). On the parties' cross

motions for judgment on the pleadings, a Superior Court judge

entered judgment affirming the decision of the commission. The

McParlands appeal, claiming principally that the commission's decision was arbitrary and capricious and based on findings unsupported by substantial evidence. We vacate the Superior Court judgment and remand for entry of a new judgment that annuls the decision of the commission and remands the matter to the commission for further consideration.

Background. The McParlands own property at 150 Carriage Road in Osterville. On December 16, 2022, the McParlands applied for a permit to build a pier for nonmotorized watercraft in a high-value shellfish area (project). On January 3, 2023, and February 14, 2023, the commission held public hearings on the project. On February 28, 2023, the commission voted to approve the project under the Wetlands Protection Act, G. L. c. 131, § 40 (act), but to deny the project under the town's wetland protection regulations. On March 2, 2023, the commission issued an order of conditions and, in support of its decision, found that the McParland project would (1) reduce water access for shellfish harvesting; (2) have a significant impact on shellfish habitat due to space occupied by pilings; (3) scour shellfish habitat; and (4) contribute to the potential for exotic species proliferation.

Discussion. We review de novo a judge's order allowing a motion for judgment on the pleadings. See UBS Fin. Servs., Inc. v. Aliberti, 483 Mass. 396, 405 (2019). "[O]ur review is

limited at most to whether the commission's decision is supported by substantial evidence in the administrative record, whether the commission's action was arbitrary and capricious, and whether the commission committed an abuse of discretion or other error of law." Delapa v. Conservation Comm'n of Falmouth, 93 Mass. App. Ct. 729, 733-734 (2018). Under the act, municipalities are empowered to issue regulations and "may enact more stringent requirements than those provided in the act." See Hobbs Brook Farm Prop. Co. v. Conservation Comm'n of Lincoln, 65 Mass. App. Ct. 142, 149 (2005). "Unless an agency's interpretation of its own regulation is arbitrary, unreasonable, or inconsistent with the plain terms of the rule, such interpretation is entitled to deference" (quotation and citation omitted). Carey v. Commissioner of Correction, 479 Mass. 367, 369-370 (2018).

Section 703-3(A) of the local regulations requires an applicant, in relevant part, to file a notice of intent before constructing "any new pier or dock, whether fixed or floating, permanent or seasonal." Under local regulation § 237-6(B), the commission is authorized to deny a permit where the application (1) fails "to meet the design specifications, performance standards, policy guidelines or other requirements in [the regulations]"; (2) fails "to avoid or prevent unacceptable significant or cumulative effects upon the wetlands values

protected by [the regulations]"; or (3) where denial is "deemed . . . necessary to preserve the environmental quality of resource areas." According to local regulation § 703-1(K), piers conforming to local regulations "can be presumed to minimize . . . possible negative [wetland] impacts."

Here, the commission denied the McParlands a permit based on findings that the project "will cause negative impacts on [wetland] values" and "result in negative effects" on shellfish habitats and fishing access.3 Ultimately, the commission found that the McParlands failed to prove, by a preponderance of the evidence, that "a permanent pile pier would, in fact, lessen the environmental impact" compared to a seasonal pier.4 However, the proper question under the local regulations was whether the McParlands proved that the project would not have "unacceptable

significant or cumulative effects" on the wetland resource values.5 Because the commission did not apply the correct standard, the commission's "denial of [the McParlands'] application was improperly based on a policy existing outside of the regulatory framework." Fieldstone Meadows Dev. Corp. v. Conservation Comm'n of Andover, 62 Mass. App. Ct. 265, 267 (2004). Where the project complied but the commission failed to apply the standard of review articulated by the local regulations, we conclude that the commission's decision to deny the McParlands' application was arbitrary and capricious and based on an error of law.6 See

5 To the extent that the commission based the permit denial on "environmental quality" concerns due to potential for proliferation of invasive species on permanent piers, we note that the commission's May 9, 2023, permit application approval for the nearby site did not mention the potential for the proliferation of invasive species. The appeals in that unrelated case and this case were paired for oral argument; at oral argument, the commission offered no justification for why the potential for invasive species proliferation was central to the negative determination on the McParland pier application, but not relevant to the approval of the other permit application.

6 We decline to address the McParlands' general contention that the commission's decision was a product of its "ad hoc agenda against permanent docks and piers." The McParlands also argue that the commission's determinations that the project would reduce access for shellfish harvesting and that "ice eaters" used to prevent pilings on permanent piers from freezing would scour shellfish habitats were not supported by substantial evidence. Based on our conclusion that the commission's decision was arbitrary and capricious, we need not reach those issues either, except to note that shellfish could be raked

id. at 268. Thus, we vacate the Superior Court judgment and remand for entry of a new judgment that annuls the decision of the commission and remands the matter to the commission for further factual findings and application of the proper standard under the local regulations; that is, whether the project would have "unacceptable significant or cumulative effects" on the wetland resource values.7 The judgment is vacated, and the case is remanded to the Superior Court for further proceedings consistent with this memorandum and order. By the Court (Henry, Shin & Brennan, JJ.8),

Clerk

Entered: July 14, 2025.

Free access — add to your briefcase to read the full text and ask questions with AI

STEPHEN M. McPARLAND, Trustee, & Another v. CONSERVATION COMMISSION OF BARNSTABLE., (Mass. Ct. App. 2025).

STEPHEN M. McPARLAND, Trustee, & Another v. CONSERVATION COMMISSION OF BARNSTABLE. (STEPHEN M. McPARLAND, Trustee, & Another v. CONSERVATION COMMISSION OF BARNSTABLE.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Carey v. Commissioner of Correction
95 N.E.3d 220 (Massachusetts Supreme Judicial Court, 2018)
Box Pond Ass'n v. Energy Facilities Siting Board
435 Mass. 408 (Massachusetts Supreme Judicial Court, 2001)
Fieldstone Meadows Development Corp. v. Conservation Commission
816 N.E.2d 141 (Massachusetts Appeals Court, 2004)
Hobbs Brook Farm Property Co. v. Conservation Commission
838 N.E.2d 578 (Massachusetts Appeals Court, 2005)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)
Delapa v. Conservation Comm'n of Falmouth
108 N.E.3d 474 (Massachusetts Appeals Court, 2018)