OPINION
Before RABINOWITZ, C. J., and CON-NOR, BURKE, MATTHEWS and COMPTON, JJ.
RABINO WITZ, Chief Justice.
This dispute is between one defendant (the Municipality of Anchorage, hereafter the Municipality) and one former defendant (Stephan & Sons, Inc., hereafter S&S) in a separate damages action brought by the mother of Walter DeHusson. The issue is whether S&S, a construction contractor, had a duty to defend the Municipality in the DeHusson action. The original DeHus-son action was dismissed before the reply brief in the case at bar was filed, but the defense cost issue is still extant. The superior court granted summary judgment to the Municipality. For the reasons given below, we affirm.
A. Facts
The case stems from construction work done by S&S for the Municipality on the Westchester Lagoon spillway structure. The structure was originally built by the Kelly Construction Company, according to specifications set by the Municipality. In 1972, the Municipality contracted with S&S for street improvements to Arctic Boulevard. Subsequently, a 1973 change order to this contract was made, according to which S&S was to do some additional work on the Westchester Lagoon spillway structure, including repairing some ice damage to the south wing wall, repairing the fish ladder, grading the earthen dike, and other miscellaneous matters. S&S subcontracted the spillway repair work to Tunnel Bay Construction Company, retaining for itself the earth work in the lagoon bed and dike.
On July 27, 1973, Walter DeHusson and one Randall Redmond were playing on the spillway structure, apparently guiding boards down the spillway.
At first, Walter, hanging on to a vertical pipe, pushed the boards in the water with his feet to guide them into the spillway. This did not work with one board, and Walter, letting go of the pipe, walked to the other end of the board and started stomping on it. Walter fell into the water, was swept into a culvert, and drowned.
About two years after the accident, Walter’s mother filed suit against the Municipality, S&S, Tunnel Bay, and Kelly Construction. The complaint (as amended) included allegations that S&S and Tunnel Bay were negligent in not installing a fence, in not securely covering the hole made in the grating on top of the structure, in not installing grating over the flood gate mouths and other open areas of the structure, and in not installing warning signs around the area. In a ruling which was on appeal to this court,
DeHusson v. Stephan & Sons Construction Co.,
File No. 5231, S&S was awarded summary judgment on the ground that there was no evidence of any negligence on its part. Obviously, the parties disagree on the correctness of this ruling. Tunnel Bay remained a defendant in the DeHusson suit.
Subsequently, the Municipality instituted the present action for declaratory judgment against S&S, alleging that S&S was required to defend the Municipality in the DeHusson action, and to indemnify the Municipality for its defense costs and any damages, under the following contractual provision:
10.15
HOLD HARMLESS CLAUSE
The contractor shall indemnify, save and hold the City harmless, and defend the City at the contractor’s sole cost and expense against any claim or liability for any injury to any person or persons or a
damage to any property or any other liability arising or resulting from the construction of any improvement, or any part thereof, or from any other performance by the contractor or his subcontractors under this contract. The liability assumed by the contractor pursuant to this section shall include but not be limited to all claims brought by any person for work or materials furnished for construction of improvements under this contract.
S&S denied that the clause required it to defend the Municipality. It also attacked the clause on statutory and public policy grounds.
The Municipality entered a motion for complete summary judgment on June 26, which the superior court denied. One year later, the Municipality moved for reconsideration on the issue of S&S’s duty to defend, and the superior court set aside its previous ruling and ordered S&S to take up the Municipality’s defense in the underlying action. S&S moved for relief from and reconsideration of that order, both of which motions the superior court denied after oral argument. The Municipality then moved for partial summary judgment for the costs and attorney’s fees incurred thus far in the DeHusson suit, which was granted over S&S’s opposition. It is from this order (as amended) that this appeal is taken.
During the pendency of this appeal, the original DeHusson action in the superior court and, consequently, the appeal as to S&S in this court, have been dismissed.
B. The Contractual Duty to Defend
The initial issue we must resolve is whether the contractual duty of S&S to defend the Municipality is to be defined solely by the allegations in the DeHusson complaint, or whether we must look beyond the complaint to the “true facts” to determine whether these facts in actuality fit the situation contemplated by the clause. Only if we adopt the latter view must we turn to an assessment of the facts.
S&S’s position is that the duty to defend and the duty to indemnify come into play together or not at all, since they are both conditioned on the same language in the contract.
Its claim is that only if it is found that S&S had a duty to indemnify the Municipality for any liability in the DeHusson action can it also be found that S&S had a duty to defend the Municipality. Since the superior court granted summary judgment on the duty to defend issue but not on the duty to indemnify, S&S argues, its ruling is logically inconsistent. According to S&S, if material factual issues yet to be resolved will determine the extent of the duty to indemnify, these same factual issues must be resolved to determine the extent of the duty to defend.
The Municipality’s position is that the duty to defend is determined by looking to the allegations in the complaint, whereas the duty to indemnify is determined by the ultimate findings of fact. It argues that the court below only had to look at the DeHusson complaint; if it included allegations that S&S, or its subcontractor, Tunnel Bay, was negligent, then S&S had a duty to defend. Since the DeHusson complaint in-disputedly contained such allegations, the Municipality insists that no genuine issue of material fact was presented as to the duty to defend.
We have already held in two contexts that there may be a duty to defend even if there is no duty to indemnify: insurance cases
and implied indemnity eases.
We have not addressed this particular question in the construction contractor context.
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION
Before RABINOWITZ, C. J., and CON-NOR, BURKE, MATTHEWS and COMPTON, JJ.
RABINO WITZ, Chief Justice.
This dispute is between one defendant (the Municipality of Anchorage, hereafter the Municipality) and one former defendant (Stephan & Sons, Inc., hereafter S&S) in a separate damages action brought by the mother of Walter DeHusson. The issue is whether S&S, a construction contractor, had a duty to defend the Municipality in the DeHusson action. The original DeHus-son action was dismissed before the reply brief in the case at bar was filed, but the defense cost issue is still extant. The superior court granted summary judgment to the Municipality. For the reasons given below, we affirm.
A. Facts
The case stems from construction work done by S&S for the Municipality on the Westchester Lagoon spillway structure. The structure was originally built by the Kelly Construction Company, according to specifications set by the Municipality. In 1972, the Municipality contracted with S&S for street improvements to Arctic Boulevard. Subsequently, a 1973 change order to this contract was made, according to which S&S was to do some additional work on the Westchester Lagoon spillway structure, including repairing some ice damage to the south wing wall, repairing the fish ladder, grading the earthen dike, and other miscellaneous matters. S&S subcontracted the spillway repair work to Tunnel Bay Construction Company, retaining for itself the earth work in the lagoon bed and dike.
On July 27, 1973, Walter DeHusson and one Randall Redmond were playing on the spillway structure, apparently guiding boards down the spillway.
At first, Walter, hanging on to a vertical pipe, pushed the boards in the water with his feet to guide them into the spillway. This did not work with one board, and Walter, letting go of the pipe, walked to the other end of the board and started stomping on it. Walter fell into the water, was swept into a culvert, and drowned.
About two years after the accident, Walter’s mother filed suit against the Municipality, S&S, Tunnel Bay, and Kelly Construction. The complaint (as amended) included allegations that S&S and Tunnel Bay were negligent in not installing a fence, in not securely covering the hole made in the grating on top of the structure, in not installing grating over the flood gate mouths and other open areas of the structure, and in not installing warning signs around the area. In a ruling which was on appeal to this court,
DeHusson v. Stephan & Sons Construction Co.,
File No. 5231, S&S was awarded summary judgment on the ground that there was no evidence of any negligence on its part. Obviously, the parties disagree on the correctness of this ruling. Tunnel Bay remained a defendant in the DeHusson suit.
Subsequently, the Municipality instituted the present action for declaratory judgment against S&S, alleging that S&S was required to defend the Municipality in the DeHusson action, and to indemnify the Municipality for its defense costs and any damages, under the following contractual provision:
10.15
HOLD HARMLESS CLAUSE
The contractor shall indemnify, save and hold the City harmless, and defend the City at the contractor’s sole cost and expense against any claim or liability for any injury to any person or persons or a
damage to any property or any other liability arising or resulting from the construction of any improvement, or any part thereof, or from any other performance by the contractor or his subcontractors under this contract. The liability assumed by the contractor pursuant to this section shall include but not be limited to all claims brought by any person for work or materials furnished for construction of improvements under this contract.
S&S denied that the clause required it to defend the Municipality. It also attacked the clause on statutory and public policy grounds.
The Municipality entered a motion for complete summary judgment on June 26, which the superior court denied. One year later, the Municipality moved for reconsideration on the issue of S&S’s duty to defend, and the superior court set aside its previous ruling and ordered S&S to take up the Municipality’s defense in the underlying action. S&S moved for relief from and reconsideration of that order, both of which motions the superior court denied after oral argument. The Municipality then moved for partial summary judgment for the costs and attorney’s fees incurred thus far in the DeHusson suit, which was granted over S&S’s opposition. It is from this order (as amended) that this appeal is taken.
During the pendency of this appeal, the original DeHusson action in the superior court and, consequently, the appeal as to S&S in this court, have been dismissed.
B. The Contractual Duty to Defend
The initial issue we must resolve is whether the contractual duty of S&S to defend the Municipality is to be defined solely by the allegations in the DeHusson complaint, or whether we must look beyond the complaint to the “true facts” to determine whether these facts in actuality fit the situation contemplated by the clause. Only if we adopt the latter view must we turn to an assessment of the facts.
S&S’s position is that the duty to defend and the duty to indemnify come into play together or not at all, since they are both conditioned on the same language in the contract.
Its claim is that only if it is found that S&S had a duty to indemnify the Municipality for any liability in the DeHusson action can it also be found that S&S had a duty to defend the Municipality. Since the superior court granted summary judgment on the duty to defend issue but not on the duty to indemnify, S&S argues, its ruling is logically inconsistent. According to S&S, if material factual issues yet to be resolved will determine the extent of the duty to indemnify, these same factual issues must be resolved to determine the extent of the duty to defend.
The Municipality’s position is that the duty to defend is determined by looking to the allegations in the complaint, whereas the duty to indemnify is determined by the ultimate findings of fact. It argues that the court below only had to look at the DeHusson complaint; if it included allegations that S&S, or its subcontractor, Tunnel Bay, was negligent, then S&S had a duty to defend. Since the DeHusson complaint in-disputedly contained such allegations, the Municipality insists that no genuine issue of material fact was presented as to the duty to defend.
We have already held in two contexts that there may be a duty to defend even if there is no duty to indemnify: insurance cases
and implied indemnity eases.
We have not addressed this particular question in the construction contractor context. Other jurisdictions have considered this question with mixed results: some cases
favor the Municipality’s position
others the position urged by S&S.
To the extent that it makes sense to find majority and minority rules in this area, it appears that the Municipality has the weight of authority on its side.
Two general principles emerge from the case law from other jurisdictions we have examined. First, the question must be resolved by examination of the wording of the contract.
The second point is a less obvious one. Of the cases ruling in favor of S&S’s position, virtually all have been from jurisdictions which apply some variant of a “strict construction” rule to contracts in which an indemnitee is attempting to recover indemnity against losses caused by its own negligence; and indeed, in all three cases we have cited, a claim for actual indemnity was refused along with (or prior to) the refusal of the claim for defense costs.
Although this concern was not articulated, it appears that the courts in those cases were more concerned with the problem of recovery by a negligent party in light of the “strict construction” rule than they were concerned about whether the duty to defend might be broader than the duty to indemnify. To the extent that Alaska has rejected the “strict construction” rule, the persuasive value of these cases is diminished.
With these considerations in mind, we turn to an examination of the language here. S&S’s principal argument is that the language used to trigger the two duties is identical: “The contractor shall indemnify . . . and defend the City .. . against any claim or liability for any injury ... or any other liability arising or resulting from the construction ... by the contractor or his subcontractors under this contract.”
Only two of the cases cited to us by the parties have analyzed an identity of language argument, and those cases reached different results.
Smith v. Chevron Oil Co.,
517 F.2d 1154 (5th Cir. 1975), took the position urged by S&S here: that identical language means the duties are coterminous.
Bituminous Insurance Co. v. Pennsylvania Manufacturers’ Association Insurance Co.,
427 F.Supp. 539 (E.D.Pa.1976), took the position of the Municipality: that, although the language is identical, the duties can be different.
S&S argues that the identity of language for the two duties means that, if we find a duty to defend here, we must also logically find a duty to indemnify, since they come into play together or not at all; and that imposing a duty to indemnify before the true facts are found is illogical, as the court below recognized in refusing to grant summary judgment on the duty to indemnify issue.
We think the wording of the contract here clearly supports the Municipality’s position, and refutes S&S’s argument that the two duties come into play together or not at all. The key words are “indemnify .. . and defend” and “claim or liability.” We think that the most reasonable reading of the clause is that S&S agreed to defend against claims and to indemnify for liabilities.
“Claim” clearly connotes assertion of a legal right, rather than legal recognition or enforcement of that right.
One does not
indemnify until there is actually liability; the existence of a claim alone does not call for indemnification. Since the inclusion of the word “claim” makes it clear that S&S undertook some responsibility with regard to claims, and since it is illogical to link the term “indemnify” with “claims,” it follows that the obligation undertaken with respect to claims was an obligation to defend.
By the same token, one cannot “defend” against liabilities; if liability has been established, the time for defense is past. Therefore, the obligation S&S must have undertaken with respect to “liabilities” was one to indemnify.
The differing nature of these two duties means that if, as S&S asserts, the facts were to show that the actual injury did not arise or result from the construction work, the duty to defend would be different from the duty to indemnify. Under that factual situation, any liability imposed would not be for an injury arising or resulting from the construction work; and if there were no “liability ... for any injury arising or resulting from the construction,” then there would be no duty to indemnify. This does not mean, however, that there was no “claim ... for any injury arising or resulting from the construction.” The “true facts” affect only the existence of actual liability, not the claim.
Thus, despite the identity of language here, we see nothing inconsistent in ruling that there is a duty to defend at all points of the case during which there is a claim for injury arising or resulting from the construction work, whether or not this claim is eventually borne out, but that there is no duty to indemnify unless the liability in fact arose or resulted from the construction work.
We think that the duty to defend attaches as long as the principal case continues to include a cause of action “arising or resulting out of” the construction work.
In this case, Tunnel Bay, the subcontractor, was still a party to the principal DeHusson suit up until the point of settlement; thus, the case continued to include a cause of action alleging negligence on the part of Tunnel Bay, and this clearly encompasses a claim arising or resulting from the construction work.
Having reached this con-
elusion, we need not address the parties’ arguments as to what the “true facts” show.
C. Public Policy Arguments
1. The public service exception
S&S makes two public policy arguments which it asserts would void both the duty to indemnify and the duty to defend.
First, relying on
Manson-Osberg Co. v. State,
552 P.2d 654, 659-60 (Alaska 1976), and
Northwest Airlines, Inc. v. Alaska Airlines, Inc.
351 F.2d 253 (9th Cir.1965),
cert, denied,
383 U.S. 936, 86 S.Ct. 1068, 15 L.Ed.2d 853 (1966), S&S argues that enforcement of the contract would tend to promote breach of a duty owing to the public at large. These cases support the proposition that, where the indemnitee is charged with a duty of public service
(e.g.,
a common carrier) and the indemnification is for some neglect in the performance of that duty, the indemnity agreement should not be enforced, as the indemnitee’s “relaxed vigilance” in fulfilling such duties, because of the indemnification, might inure to the detriment of society at large.
The Municipality contends that this ease is controlled by
Burgess Construction Co. v. State,
614 P.2d 1380 (Alaska 1980). That case also involved an agreement by a construction company to indemnify a governmental body, and the court enforced the indemnity clause. We said:
Burgess first argues, relying on the language of
Manson-Osberg
emphasized above, that since in this case enforcement of the indemnity clause would tend to promote breach of a duty which the State owed to the public at large, the clause should not be enforced. The public duty exception to which we referred in
Manson-Osberg
is generally held applicable to public utilities and common carriers, and is based on two principles. The first is that those to whom the exception applies should guard against the consequences of their negligence at all times; indemnity agreements, or prospective releases, are thought to eliminate their incentive to do so. The second is that it is thought unfair to allow public service entities to impose liability-avoiding agreements on those they are supposed to serve, since the latter have no choice but to accept such agreements. Because we believe that neither principle applies here, we reject Burgess’ arguments that this case falls within the public duty exception.
Id.
at 1381-82 (footnotes omitted). The Municipality is correct in asserting that the reasoning in
Burgess
controls this aspect of the case and requires rejection of S&S’s first public policy argument.
2. The statutory public policy argument S&S also argues that the clause is void under former AS 45.47.010,
which reads:
Indemnification agreements contra to public policy.
A provision, clause, covenant, or agreement contained in, collateral to, or affecting any construction contract which purports to indemnify the promisee against liability for damages for (1) death or bodily injury to persons, (2) injury to property, (3) design defects or (4) any other loss, damage or expense arising under (1), (2), or (3) of this section from the sole negligence or wilful misconduct of the promisee or the promisee’s
agents, servants or independent contractors who are directly responsible to the promisee, is against public policy and is void and unenforceable; however, this provision does not affect the validity of any insurance contract, workmen’s compensation or agreement issued by an insurer subject to the provisions of AS 21.
This statute became effective September 23, 1975, ch. 155, § 1, SLA 1975, and governs contracts executed on or after that date.
Contracts executed before that date are governed by the rule we announced in
Burgess Construction Co. v. State,
614 P.2d 1380, 1382 (Alaska 1980) (citations omitted):
Most modern authorities hold that an indemnity clause such as the present one is effective to shift responsibility for an accident where the indemnitee is negligent and the indemnitor is not.... ‘[Tjhere is no essential public policy impediment to an indemnitor undertaking to indemnify the indemnitee in respect of the in-demnitee’s own negligence... . ’
Since this contract, like the one in
Burgess,
was entered into prior to the statute’s effective date, it is governed by the
Burgess
rule rather than by the statute.
Since the superior court judge correctly concluded that there were no issues of material fact here, and since there are no public policy considerations applicable to this case which dictate a contrary result, the judgment of the superior court is affirmed.