Stenger v. Ohio Dept. of Transp.

2011 Ohio 5310
CourtOhio Court of Claims
DecidedJuly 18, 2011
Docket2011-02727-AD
StatusPublished

This text of 2011 Ohio 5310 (Stenger v. Ohio Dept. of Transp.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stenger v. Ohio Dept. of Transp., 2011 Ohio 5310 (Ohio Super. Ct. 2011).

Opinion

[Cite as Stenger v. Ohio Dept. of Transp., 2011-Ohio-5310.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

THOMAS A. STENGER

Plaintiff

v.

OHIO DEPARTMENT OF TRANSPORTATION

Defendant

Case No. 2011-02727-AD

Acting Clerk Daniel R. Borchert

MEMORANDUM DECISION

{¶1} On February 9, 2011, at approximately 5:45 a.m., plaintiff, Thomas Stenger, was traveling east on State Route 18 “about 150 yards past the Interstate 77 overpass in Summit County” when his 2009 Nissan Maxima “struck a pothole with the driver’s side front wheel and tire.” Plaintiff related that upon impact, “the tire blew out and my front windshield cracked about 10 inches up from the dash.” Plaintiff submitted photographs depicting the damage-causing pothole. Based upon a review of the photographs, it appears that the pothole had been previously patched at some undetermined time and the patching material had completely deteriorated forming a very deep rectangular roadway defect. The roadway area around the pothole and extending down the lane of travel for several feet shows signs of pavement deterioration along with other repaired areas. {¶2} Plaintiff asserted that the damage to his car was proximately caused by negligence on the part of defendant, Department of Transportation (DOT), in failing to adequately maintain the roadway free of defects. Plaintiff filed this complaint seeking to recover $871.64, the stated cost of a tire and wheel, as well as other related automotive repairs. The filing fee was paid. {¶3} Defendant denied liability based on the contention that no DOT personnel had any knowledge of the particular damage-causing pothole prior to the February 9, 2011 incident. Defendant noted that DOT records show no prior calls or complaints were received about the pothole, which defendant located “near milepost 1.90 on SR 18 in Summit County.” Defendant asserted that plaintiff did not produce any evidence to establish the length of time the pothole near milepost 1.90 existed before February 9, 2011 and suggested that “it is more likely than not that the pothole existed in that location for only a relatively short amount of time before plaintiff’s incident.” Defendant explained that the DOT “Summit County Manager conducts roadway inspections on all state roadways within the county on a routine basis, at least one to two times a month.” Apparently, no potholes were discovered near milepost 1.90 on State Route 18 the last time that section of roadway was inspected prior to February 9, 2011. Defendant did not provide any inspection records. Defendant stated that, “[a] review of the six-month maintenance history [record submitted] for the area in question reveals that seven (7) pothole patching operations were conducted in the general vicinity of plaintiff’s incident” and there “were two more repairs on February 11, 2011, which shows that ODOT responded after plaintiff called in this location.” (Emphasis added.) {¶4} Defendant’s maintenance records for State Route 18 verify that six of the seven repairs in the vicinity of plaintiff’s incident took place in December 2010. ODOT crews patched potholes there on December 16, twice on December 21, and three more times on December 29, 2010. Patching operations were also performed near milepost 1.90 on February 4, 2011. {¶5} For plaintiff to prevail on a claim of negligence he must prove, by a preponderance of the evidence, that defendant owed him a duty, that it breached that duty, and that the breach proximately caused his injuries. Armstrong v. Best Buy Company, Inc., 99 Ohio St. 3d 79, 2003-Ohio-2573,¶8 citing Menifee v. Ohio Welding Products, Inc. (1984), 15 Ohio St. 3d 75, 77, 15 OBR 179, 472 N.E. 2d 707. Plaintiff has the burden of proving, by a preponderance of the evidence, that he suffered a loss and that this loss was proximately caused by defendant’s negligence. Barnum v. Ohio State University (1977), 76-0368-AD. However, “[i]t is the duty of a party on whom the burden of proof rests to produce evidence which furnishes a reasonable basis for sustaining his claim. If the evidence so produced furnishes only a basis for a choice among different possibilities as to any issue in the case, he fails to sustain such burden.” Paragraph three of the syllabus in Steven v. Indus. Comm. (1945), 145 Ohio St. 198, 30 O.O. 415, 61 N.E. 2d 198, approved and followed. {¶6} Defendant has the duty to maintain its highways in a reasonably safe condition for the motoring public. Knickel v. Ohio Department of Transportation (1976), 49 Ohio App. 2d 335, 3 O.O. 3d 413, 361 N.E. 2d 486. However, defendant is not an insurer of the safety of its highways. See Kniskern v. Township of Somerford (1996), 112 Ohio App. 3d 189, 678 N.E. 2d 273; Rhodus v. Ohio Dept. of Transp. (1990), 67 Ohio App. 3d 723, 588 N.E. 2d 864. {¶7} In order to prove a breach of the duty to maintain the highways, plaintiff must prove, by a preponderance of the evidence, that defendant had actual or constructive notice of the precise condition or defect alleged to have caused the accident. McClellan v. ODOT (1986), 34 Ohio App. 3d 247, 517 N.E. 2d 1388. Defendant is only liable for roadway conditions of which it has notice but fails to reasonably correct. Bussard v. Dept. of Transp. (1986), 31 Ohio Misc. 2d 1, 31 OBR 64, 507 N.E. 2d 1179. {¶8} Generally, in order to recover in a suit involving damage proximately caused by roadway conditions including potholes, plaintiff must prove that either: 1) defendant had actual or constructive notice of the pothole and failed to respond in a reasonable time or responded in a negligent manner, or 2) that defendant, in a general sense, maintains its highways negligently. Denis v. Department of Transportation (1976), 75-0287-AD. The fact defendant’s “Maintenance History” reflects pothole repairs were made in the vicinity of plaintiff’s incident several times in the weeks preceding February 9, 2011, supports a finding of negligent maintenance of the roadway on the part of ODOT. See Maynard v. Ohio Dept. of Transp., Ct. of Cl. No. 2004-03730-AD, 2004-Ohio-3284; Marcis v. Ohio Dept. of Transp., Ct. of Cl. No. 2004- 05830-AD, 2004-Ohio-4830. {¶9} Based upon the numerous roadway patching operations performed near milepost 1.90 during the fifty-day period preceding plaintiff’s incident, the trier of fact also finds defendant had constructive notice of the pothole at milepost 1.90 on State Route 18. “[C]onstructive notice is that which the law regards as sufficient to give notice and is regarded as a substitute for actual notice or knowledge.” In re Estate of Fahle (1950), 90 Ohio App. 195, 197-198, 47 O.O. 231, 105 N.E. 2d 429. “A finding of constructive notice is a determination the court must make on the facts of each case not simply by applying a pre-set time standard for the discovery of certain road hazards.” Bussard, at 4. “Obviously, the requisite length of time sufficient to constitute constructive notice varies with each specific situation.” Danko v. Ohio Dept. of Transp. (Feb. 4, 1993), Franklin App. 92AP-1183. In order for there to be a finding of constructive notice, plaintiff must prove, by a preponderance of the evidence, that sufficient time has elapsed after the dangerous condition appears, so that under the circumstances defendant should have acquired knowledge of its existence. Guiher v. Dept. of Transportation (1978), 78-0126-AD; Gerlarden v. Ohio Dept. of Transp., Dist. 4, Ct. of Cl. No. 2007-02521-AD, 2007-Ohio-3047. {¶10} Plaintiff has provided sufficient photographic evidence to establish that the damage-causing defect was massive in both size and depth, and constituted a recurring problem defendant failed to properly correct. Ordinarily size of a defect (pothole) is insufficient to show notice or duration of existence. O’Neil v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Knickel v. Department of Transportation
361 N.E.2d 486 (Ohio Court of Appeals, 1976)
McClellan v. Ohio Department of Transportation
517 N.E.2d 1388 (Ohio Court of Appeals, 1986)
Kniskern v. Township of Somerford
678 N.E.2d 273 (Ohio Court of Appeals, 1996)
Rhodus v. Ohio Department of Transportation
588 N.E.2d 864 (Ohio Court of Appeals, 1990)
In Re Estate of Fahle
105 N.E.2d 429 (Ohio Court of Appeals, 1950)
Stevens v. Industrial Commission
61 N.E.2d 198 (Ohio Supreme Court, 1945)
Bussard v. Ohio Department of Transportation
507 N.E.2d 1179 (Ohio Court of Claims, 1986)
State v. Dehass
227 N.E.2d 212 (Ohio Supreme Court, 1967)
Menifee v. Ohio Welding Products, Inc.
472 N.E.2d 707 (Ohio Supreme Court, 1984)
Armstrong v. Best Buy Co.
788 N.E.2d 1088 (Ohio Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
2011 Ohio 5310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stenger-v-ohio-dept-of-transp-ohioctcl-2011.