Stellar J Corp. v. Smith & Loveless, Inc.

749 F. Supp. 2d 1137, 2010 WL 3118360
CourtDistrict Court, D. Oregon
DecidedAugust 5, 2010
Docket3:09-cr-00353
StatusPublished

This text of 749 F. Supp. 2d 1137 (Stellar J Corp. v. Smith & Loveless, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stellar J Corp. v. Smith & Loveless, Inc., 749 F. Supp. 2d 1137, 2010 WL 3118360 (D. Or. 2010).

Opinion

ORDER

BROWN, District Judge.

Magistrate Judge John Jelderks issued Findings and Recommendation (#48) on May 11, 2010, in which he recommends the Court grant the Motion (# 21) for Partial Summary Judgment of Stellar J Corporation and Travelers Casualty and Surety Company of America. Smith & Loveless, Inc., filed timely Objections to the Findings and Recommendation. The matter is now before this Court pursuant to 28 U.S.C. § 636(b)(1) and Federal Rule of Civil Procedure 72(b).

When any party objects to any portion of the Magistrate Judge’s Findings and Recommendation, the district court must make a de novo determination of that portion of the Magistrate Judge’s report. 28 U.S.C. § 636(b)(1). See also United States v. Reynar-Tapia, 328 F.3d 1114, 1121 (9th Cir.2003) (en banc); United States v. Bernhardt, 840 F.2d 1441, 1444 (9th Cir.1988).

*1139 In its Objections, Smith & Loveless reiterates the arguments contained in its Response to the Motion for Partial Summary-Judgment of Stellar J Corporation. The Magistrate Judge thoroughly addressed Smith and Loveless’s arguments in his Findings and Recommendation. This Court also has carefully considered Smith and Loveless’s Objections and concludes they do not provide a basis to modify the Findings and Recommendation. The Court also has reviewed the pertinent portions of the record de novo and does not find any error in the Magistrate Judge’s Findings and Recommendation.

CONCLUSION

The Court ADOPTS Magistrate Judge Jelderks’s Findings and Recommendation (# 48) and, accordingly, GRANTS the Motion (# 21) for Partial Summary Judgment of Stellar J Corporation and Travelers Casualty and Surety Company of America.

IT IS SO ORDERED.

FINDINGS AND RECOMMENDATION

JOHN JELDERKS, United States Magistrate Judge:

Plaintiff Stellar J Corporation (Stellar) brings this construction related action against Smith & Loveless, Inc. (Smith). Smith asserts counterclaims, and asserts third-party claims against Travelers Casualty and Surety Company of America (Travelers).

Plaintiff Stellar and third-party defendant Travelers move for a partial summary judgment establishing that they are entitled to prevail on defendant Smith’s counterclaim against Stellar and third-party claim against Travelers on the grounds that Smith was not licensed by the Oregon Construction Contractors Board when it performed the work that is subject to this dispute.

For the reasons set out below, the motion should be granted.

Background

This action arises from a contract between plaintiff Stellar and defendant Smith for the purchase and installation of equipment for use in a wastewater treatment improvement project (the Project) in the City of Rainier, Oregon (Rainier).

Stellar is a Texas corporation whose principal place of business is located in Woodland, Washington. Smith is a Kansas corporation whose principal place of business is located in Lenexa, Kansas.

Plaintiff Stellar subcontracted with Rainier for the construction of certain improvements in Rainier’s waste treatment plant. On March 28, 2008, Stellar and Smith entered into a contract under which Smith agreed to fabricate and install certain equipment on the Project. Defendant Smith agreed to build and supply a Biological Wastewater Treatment Unit and Aeration Diffuser System (New Wastewater Unit) for the sum of $506,250, and to provide additional wastewater treatment equipment (Retrofit Equipment) for the sum of $256,400. Smith agreed to install the Wastewater Treatment Unit for the sum of $168,750. Smith, in turn, subcontracted with DC Design and Construction, Inc., a licensed Oregon contractor, for installation of the New Wastewater Unit.

When Stellar and Smith entered into their subcontract, and while it worked pursuant to that agreement, Smith did not have an Oregon Contractor’s license. On March 28, 2008, Smith faxed Stellar a copy of the subcontract agreement that included a copy of page 7 which had not been filled out. On April 2, 2008, Stellar faxed Smith a copy of page 7, and asked Smith to complete and return the form. On April 24, 2008, Smith faxed a copy of page 7 back to Stellar. On a line on that page which asked for Smith’s Oregon Contractor’s license number, Smith placed the notation “N/A.”

*1140 At some point during the Project, Stellar terminated the parties’ subcontract agreement. As noted above, the subcontract between Stellar and Smith provided that Smith would be paid $506,250 for the New Wastewater Unit, $168,750 for the erection and installation of the New Wastewater Unit, and $256,400 for the Retrofit Equipment. Smith asserts Stellar still owes it $73,406.25 for the New Waste-water Unit, $148,118.75 for installation of that unit, and the entire $256,400 contract price of the Retrofit Equipment.

Pursuant to the terms of a Payment Bond, third-party defendant Travelers agreed to pay on behalf of Stellar, as principal, and Rainier, as obligee, any supplier of labor, material, or equipment for the Project whom Stellar failed to pay.

In the present action, plaintiff Stellar alleges that defendant Smith breached the terms of the parties’ subcontract agreement by failing to timely and diligently perform the services it was required to provide, failing to ever provide the Retrofit Unit, and failing to “cure its defaults.” Stellar seeks recovery of damages “in an amount not less than $300,000.” In its counterclaims against Stellar, Smith alleges that Stellar breached the subcontract by failing to give it the required “notice of correction” and providing it a reasonable opportunity to cure before terminating the subcontract agreement. Smith brings claims for breach of contract and “Quantum Meruit/Unjust Enrichment” against Stellar, and seeks recovery of $477,924.62 in damages. In a third counterclaim captioned “Action on Payment Bond,” brought against both Stellar and third-party defendant Travelers, Smith seeks recovery of that amount from Stellar and Travelers pursuant to a Payment Bond guaranteeing payment to “all persons supplying labor and material” in the event that Stellar or a subcontractor failed to make required payments.

In their answer to defendant Smith’s counterclaims, filed on April 30, 2009, plaintiff Stellar and third-party defendant Travelers asserted an affirmative defense based upon plaintiffs failure to obtain an Oregon Contractor’s license. These parties asserted that Smith’s “counterclaims are barred pursuant to ORS 701.131

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Parthenon Construction & Design, Inc. v. Neuman
999 P.2d 1169 (Court of Appeals of Oregon, 2000)
Bennett v. CITY OF SALEM
235 P.2d 772 (Oregon Supreme Court, 1951)
L. H. Morris Electric, Inc. v. Hyundai Semiconductor America
66 P.3d 509 (Court of Appeals of Oregon, 2003)
Clausen v. M/V New Carissa
339 F.3d 1049 (Ninth Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
749 F. Supp. 2d 1137, 2010 WL 3118360, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stellar-j-corp-v-smith-loveless-inc-ord-2010.