Steiner v. Wenning

53 A.D.2d 437, 386 N.Y.S.2d 429, 1976 N.Y. App. Div. LEXIS 13074
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 12, 1976
StatusPublished
Cited by4 cases

This text of 53 A.D.2d 437 (Steiner v. Wenning) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steiner v. Wenning, 53 A.D.2d 437, 386 N.Y.S.2d 429, 1976 N.Y. App. Div. LEXIS 13074 (N.Y. Ct. App. 1976).

Opinions

Hawkins, J.

This appeal is from a judgment in favor of the defendant upon the trial court’s denial of plaintiffs motion, upon oral argument, after a jury had been selected, to amend the complaint so as to plead a cause of action for breach of contract and to strike the defendant’s affirmative defense that the action is time-barred by the three-year Statute of Limitations (CPLR 214) and upon granting the defendant’s cross motion to dismiss the action as time-barred.

On December 9, 1963 the parties entered into a written agreement whereby the plaintiff engaged the defendant, an architect,vto prepare plans for the design and construction of a one-family house. The defendant rendered such professional [439]*439services during the following two years. The house was completed in 1965. The certificate of occupancy was issued on May 27, 1965. Plaintiff began occupancy on May 3, 1965. The last items of work, the black-topping of the driveway and the installation of a floor slab in the garage, were completed in December of that year. This action was commenced in December, 1969.

Inter alia, the contract, the standard American Institute of Architects (A.I.A.) form, provided that: (1) the defendant would (a) prepare studies, drawings and specifications; (b) confer with persons desiring to enter into contracts for work on the project; (c) issue certificates for payments, (d) "supervise the work being done * * * or [the] furnishing [of] materials”; and (e) guard against noncompliance by any contractor, "but the architect does not thereby guarantee the performance by any contractor or other person of his, its or their contracts”; and (2) the defendant’s "supervision is to be distinguished from the continuous personal superintendence which can be obtained by the employment of a clerk-of-the-works. However, the architect specifically agrees and covenants that he will be at the premises at least three times a week to carry out his duties of supervision.” The stated fee was 10% of the cost of the project. It was to be paid at listed amounts and percentages at various stages of construction, with the last part to be paid at the time of the issuance of the certificate of occupancy.

The plaintiff, a lay person, prepared her own complaint and did not engage counsel until some four months before the trial. She is acting on her own behalf on the instant appeal. In the colloquy upon the motion at Trial Term, the Justice presiding commended the plaintiff’s efforts in drawing the pleadings, but added that if he were requested to reform the complaint, it would, nevertheless, emerge "substantively” in "malpractice”. The plaintiff’s then attorney, in support of the motion, urged that "the complaint has verbiage sounding in tort and in contract.” He further argued that the plaintiff "copied the verbiage from form books, which she did not know the value of, and what to do” and that, the architect had not guaranteed a result as in the instances of a doctor effecting "a cure” or a lawyer guaranteeing that he "will win a case for the party.” The specific guarantee alleged is that the house would be completed no later than August 1,1964.

This court has also considered whether the three- or six-[440]*440year Statute of Limitations is applicable where an owner, aggrieved by the architect’s services, seeks redress (see Sears, Roebuck & Co. v Enco Assoc., 54 AD2d 13). Until the advent of Matter of Paver & Wildfoerster (Catholic High School Assn.) (38 NY2d 669) in February, 1976, the cases held, with some measure of uniformity, that absent a "special agreement” as sometimes is found in a physician-patient relationship involving a guaranteed cure, or in an owner-architect contract containing a guarantee of continuous and more-than-routine supervisory services, the three-year period applied. No matter the precise terminology of the plaint, or the endeavors to anchor the action to contract rather than tort, the "reality” and the "essence” are in tort and not in contract (see Carr v Lipshie, 8 AD2d 330, affd 9 NY2d 983; Brick v Cohn-HallMarx Co., 276 NY 259, 264; Glens Falls Ins. Co. v Reynolds, 3 AD2d 686).

Paver, decided during the pendency of this appeal, is of little solace to the plaintiff. The crux of that holding is that when the contract provides for arbitration, and that remedy has been invoked, arbitration lies despite the action being time-barred at law by the three-year Statute of Limitations or by CPLR 7502 (subd [b]), which bars arbitration if the claim is time-barred.

We have considered the impact of Paver in deciding Sears, Roebuck & Co. v Eneo Assoc. Here, as in Sears, neither party has invoked arbitration; thus there is no departure from or variant of the rule set forth in Sosnow v Paul (36 NY2d 780). Sosnow held that the date of accrual of an action in malpractice runs from the date the architect last rendered services. The "reality” and the "essence” approach in determining whether the three-year tort or six-year contract Statute of Limitations applies remains unimpaired by Paver. The existence of a contract calling for professional services does not, ipso facto, make applicable the contract Statute of Limitations. As long ago as 1888, in Webber v Herkimer & Mohawk St. R.R. Co. (109 NY 311), the Court of Appeals held that although a passenger who had sustained injuries had entered into a contract at the time of purchase of the ticket of passage and that there necessarily had been a breach in failing safely to transport, the essence of the action was the failure to use due care. Thus, there was negligence or malpractice, and not breach of contract.

In Alyssa Originals v Finkelstein (22 AD2d 701, affd 24 [441]*441NY2d 976), we held that a tenant seeking redress from his landlord for damages caused by a leaking roof was proceeding in tort and not for breach of the lease. Accountants who had failed to detect a bookkeeper’s false entries were held liable for malpractice and not for breach of contract (see Carr v Lipshie, supra). That negligence is the critical factor rather than breach of contract in an actual or implied contractual situation is evident from Blessington v McCrory Stores Corp. (305 NY 140), where a products liability situation permitted the six-year statute since there was no need to prove negligence.

A "bifurcated” approach, as suggested by the dissent, whereby functions of supervision are separated from those of drawing plans, etc., is similarly unavailing. It may well be that, under the Education Law, one who supervises construction work need not be a licensed architect or engineer. For responsibility to attach to an architect performing such supervisory services, there would be required specific contractual provisions encompassing such services. Here the contract expressly excepts such continuing services.

The Trial Term correctly denied the belated application to amend the complaint. No attorney, no matter the semantic gymnastics, could under the facts transform the pleading to contract, for: "[t]he nature of the charge of malpractice is not changed by failing to sufficiently state it in necessary detail, or by putting it in language suitable to the statement of a cause of action on contract, omitting the usual allegations as to the absence of skill and negligence” (Horowitz v Bogart, 218 App Div 158, 160).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Catapano v. Winthrop University Hospital
19 A.D.3d 355 (Appellate Division of the Supreme Court of New York, 2005)
Piracci Construction Co. v. Skidmore, Owings & Merrill
490 F. Supp. 314 (S.D. New York, 1980)
Queensbury Union Free School District v. Jim Walter Corp.
91 Misc. 2d 804 (New York Supreme Court, 1977)
Graboi v. Kibel
432 F. Supp. 572 (S.D. New York, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
53 A.D.2d 437, 386 N.Y.S.2d 429, 1976 N.Y. App. Div. LEXIS 13074, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steiner-v-wenning-nyappdiv-1976.