Stein v. Steamboat Prairie Rose

17 Ohio St. (N.S.) 472
CourtOhio Supreme Court
DecidedDecember 15, 1867
StatusPublished

This text of 17 Ohio St. (N.S.) 472 (Stein v. Steamboat Prairie Rose) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stein v. Steamboat Prairie Rose, 17 Ohio St. (N.S.) 472 (Ohio 1867).

Opinion

Dav, C. J.

The original suit in this case was brought February 15, 1864, in the Superior Court of Cincinnati, under the provisions of the water-craft law of this state, against the steamboat Prairie Bose, to recover for the hire of the barge Mary Jane, from January 2 to July 22, 1863, at ten dollars a day, amounting to $2,020.

The defendant answered, denying the allegations in the petition; and, among other defenses, set up that the barge was hired by the-owners of the steamboat in August, 1862, to accompany the boat from Cincinnati to Evansville, Indiana; that the barge was left there in September of the same year; that the boat was subsequently sold to the present owners, who had no notice of any claim against the boat for the hire of the barge; and that on the first day of January, 1863, the plaintiff brought a suit in said Superior Court against the defendant, for the hire of the barge from the time *it was originally received by the defendant to the commencement of the suit, embracing all the time the barge was used by the defendant, and recovered a jhdgment therefor, which has been paid.

The plaintiff replied, denying that the barge was hired to accompany the boat from Cincinnati to Evansville, and alleges that the barge was hired August 13,1862, at ten dollars a day, until it was delivered back in Cincinnati in like good order as received.

The plaintiff, in his reply, further says “ that he admits that he has received all but a small balance for the hire of said barge, from the 13th day of August; 1862, until the first day of January, 1863, but claims by and under said agreement there is still due to him the sum stated in his said petition, and for the amount at the rate of’ ten dollars per day, as therein specified.”

[437]*437It appears from the bill of exceptions that the plaintiff sought to recover in this case on the following contract:

“ Cincinnati, August 13, 1862.
I have this day hired barge Mary Jane, of Albert Stein, for the sum of ten dollars per day, until delivered back in Cincinnati, in like good order as received.
“ Geo. W. Cox, Gapt.,
“ For steamer Prairie Bose and owners

It also appears that the action brought January 1, 1863, upon which there was a recovery as stated in the answer, was founded solely upon the same contract; and the present case was brought for the barge hire that accrued under the contract from the date of the former suit to the time when the plaintiff repossessed himself of the barge.

The plaintiff recovered a judgment for $2,412.45. The case was taken by proceedings in error, on the part of the defendant,' to the Superior Court at general term, where the judgment was reversed, and a final judgment was rendered in favor of the defendant.

The case is brought into this court by petition in error, to reverse the judgment of the Superior Court at general term, *for the reasons, that the court erred in reversing the judgment rendered at special term, and in rendering final judgment in favor of the defendant, instead of remanding the case to the special term for further proceedings.

The first question presented for consideration is, whether there was error in the judgment rendered at special term. The view we entertain of the case renders it unnecessary for us to consider but one of the grounds urged in the argument for the. reversal of that judgment.

It is shown by the record that the original action in this case, and the action between the same parties previously brought, were both founded on the same contract. It is well settled that if this is an entire and not a divisable contract, the plaintiff exhausted his remedies by the first suit, and can not sustain another action thereon. Hites v. Enos, 13 Ohio St. 283; Bendernagle v. Cocks, 19 Wend. 207; Fish v. Folley, 6 Hill, 54; Secor v. Sturgis, 16 N. Y. 554; Logan v. Coffrey, 30 Penn. St. 196.

Here the principal question in the case arises — whether the contract was entire or divisible. The consideration furnished by the [438]*438plaintiff to the defendant was entire; it consisted of the delivery of the barge to be used until returned. There being no suggestion of divisibility in the consideration for the contract, is there any in the promise made thereupon by the defendant? The undertaking of the defendant is not fully expressed in the instrument executed on its behalf. It is, therefore, to be construed so as to effect the true meaning of the parties; and this is to be gathered from the writing, in the light of the circumstances under which it was made. We think that the parties understood the writing as obligating the defendant to return the barge to Cincinnati; and to return it in as good order as it was in when received; and, when so returned to pay for the use thereof at the rate of ten dollars per day. It surely could not have been contemplated by them, that there should be-remitted to the plaintiff, at Cincinnati, ten dollars daily from the boat wherever it might be, nor that the plaintiff should follow the boat and make such daily collections. Such a literal construction of the contract would lead, not only to the necessity of such daily ^payment to the more absurd perpetual per diem liability in case it became impossible to return the boat. The parties must have contemplated the redelivery of the boat, and that the sum due for the hire should then be paid. But no time is mentioned in the contract when the barge should be returned. Doubtless this was omitted for the reastfn that it could not be told how long it would take to make the contemplated trip, or complete the service for which the barge was hired. The law, however, will imply — -just what the parties clearly intended — that the barge was to be returned at such time as would be reasonable under the circumstances attending the transaction. We think that this is the true construction to be given to the contract, and is one that would harmonize with the meaning of the parties, and secure justice to each of them. It gives to the plaintiff a full remedy under it, whether it be for the hire of the barge, or for injuries it might receive, or for the value of the barge on failure of its return.

Upon the construction we have given to this contract, we do not see how anything more can be claimed for it, than that it should stand upon the same principles that it would if a definite time had been expressed in it for the return of the barge. The authorities in like cases most clearly rebut the claim that the insertion of the [439]*439per diem rate was intended to divide the contract and warrant a suit at the end of each day.

In Larkin v. Buck, 11 Ohio St. 561, it was held that a promise to work six months, certain, at eleven dollars per month, is an entire contract, and the sum is payable only at the end of the time, and upon performance of the full amount of labor.

The sole object of the reference in such cases to separate days or months, is to provide a convenient mode of ascertaining the amount of the compensation to be paid under the contract, and is not for the purpose of dividing it. To this effect is the case of Hutchinson v. Wetmore, 2 Cal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hutchinson v. Wetmore
2 Cal. 310 (California Supreme Court, 1852)
Shaffer v. Lee
8 Barb. 412 (New York Supreme Court, 1850)
Bendernagle v. Cocks
19 Wend. 207 (New York Supreme Court, 1838)
Hites v. Irvine's Administrator
13 Ohio St. 283 (Ohio Supreme Court, 1862)

Cite This Page — Counsel Stack

Bluebook (online)
17 Ohio St. (N.S.) 472, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stein-v-steamboat-prairie-rose-ohio-1867.