Stein, Stein v. Reynolds Ventures, Inc., Wrightway Emergency Water Removal
Opinion
DISTRICT COURT OF APPEAL OF FLORIDA SECOND DISTRICT
KENNETH R. STEIN and JILL PATRICIA STEIN,
Petitioners,
v.
REYNOLDS VENTURES, INC., d/b/a WRIGHTWAY EMERGENCY WATER REMOVAL,
Respondent.
No. 2D2025-2795
August 7, 2026
Petition for Writ of Certiorari to the Circuit Court for Sarasota County; Danielle L. Brewer, Judge.
Kenneth R. Stein and Jill Patricia Stein, pro se.
Lori L. Moore and Peter Antonelli of Roetzel and Andress, LPA, Fort Myers, for Respondent.
SMITH, Judge.
Petitioners Kenneth R. Stein and Jill Patricia Stein seek review of the trial court's order denying their motion for judgment on the pleadings where Respondent Reynolds Ventures, Inc., d/b/a Wrightway Emergency Water Removal failed to satisfy the requirements of the Discharge of lien statute, section 713.21, Florida Statutes (2025), by not showing cause as
to why its mechanic's lien should not be enforced or vacated, and they seek discharge of the lien. We treat the Steins' petition for writ of certiorari as a petition for writ of mandamus. See Unnerstall v. Designerick, Inc., 17 So. 3d 900, 901 (Fla. 2d DCA 2009) ("Although the Unnerstalls filed a petition for a writ of certiorari in this court seeking to have the lien discharged, we treat the petition as one for mandamus and grant the petition."). Because Reynolds failed to sufficiently show cause under section 713.21(4), the trial court was required by statute to discharge the lien. Accordingly, we grant the petition and direct the trial court to discharge the mechanic's lien on the Steins' property.
I
The Steins own a condo in the Privateer North community in Longboat Key. Reynolds recorded a mechanic's lien based on work it performed on all units in the community pursuant to a contract with Privateer North (Association) listing all unit owners; the lien did not state whether the subject work was performed on common elements of the community, but Reynolds later argued that the work was performed on "common elements and multiple units."
The Steins commenced this action against Reynolds seeking to discharge the lien and requesting a declaratory judgment that the lien was invalid. Reynolds responded denying the allegations and raising six conclusory affirmative defenses.
Pursuant to section 713.21(4), the clerk of the circuit court on June 2, 2025, issued a Summons and Notice to Show Cause to Reynolds TO SHOW CAUSE WITHIN 20 DAYS WHY ITS LIEN SUBJECT OF THE PLAINTIFF'S COMPLAINT SHOULD NOT BE ENFORCED BY ACTION OR VACATED AND CANCELED OF RECORD. UPON FAILURE OF THE DEFENDANT TO SHOW CAUSE WHY ITS LIEN SHOULD NOT BE ENFORCED OR THE DEFENDANT'S FAILURE TO COMMENCE SUCH
ACTION BEFORE THE RETURN DATE OF THE SUMMONS THE COURT SHALL FORTHWITH ORDER CANCELLATION OF THE LIEN. Reynolds filed its Response to Plaintiffs' Order to Show Cause stating, in pertinent part:
7. [Reynolds] has not initiated foreclosure proceedings and has attempted to resolve the dispute with the Association. 8. [The Steins] are not the contracting party and were not billed directly for any portion of the work performed. Defendant's lien exists solely to preserve its right to payment from the property as permitted under Florida law. 9. Defendant respectfully submits that requiring it to commence litigation at this stage would undermine [Reynolds'] efforts to resolve the matter with the Association without further burdening the court or the affected parties. 10. In the alternative, if the Court concludes foreclosure must proceed, Defendant respectfully requests fourteen (14) days to initiate suit in order to comply with all applicable statutory prerequisites including service of a Final Contractor's Affidavit. The Steins later filed the third motion for judgment on the pleadings, arguing that the grounds in the "Response to Plaintiff's Order to Show Cause" did not show the appropriate "cause" under section 713.21(4). The trial court denied the motion, stating Reynolds established cause "based on the existence of a contract, services performed thereto and the lack of payment therefor."
II
In their petition, the Steins assert that because Reynolds failed to enforce its lien or show cause why the lien should not be enforced, the trial court erred in declining to discharge the lien. We agree.
Proceedings brought under section 713.21 to discharge a mechanic's lien constitute "special statutory proceedings." Matrix Constr. Corp. v. Mecca Constr., Inc., 578 So. 2d 388, 389 (Fla. 3d DCA 1991).
"When a property owner invokes [section 713.21], a lienor must strictly comply with the statute in order to preserve its lien." Unnerstall, 17 So. 3d at 902 (citing Ruffolo v. Parish & Bowman, Inc., 966 So. 2d 434 (Fla. 1st DCA 2007)). Strict compliance with the statute includes strict observance to time limits "and a trial court is without discretion to deviate from the statutorily specified time limits." Ruffolo, 966 So. 2d at 436 (citing Sturge v. LCS Dev. Corp., 643 So. 2d 53, 55 (Fla. 3d DCA 1994)); see also Dracon Constr., Inc. v. Facility Constr. Mgmt., Inc., 828 So. 2d 1069, 1071 (Fla. 4th DCA 2002) ("In a special statutory proceeding . . . the trial court does not have the same discretion to bend time requirements that might be allowed under the rules of civil procedure."); cf. Federated Stores Realty, Inc. v. Burnstein, 392 So. 2d 573, 575 (Fla. 4th DCA 1980) (holding that the time period of section 713.21 "may be extended by stipulation of the parties").
III
We first dispense with Reynolds' contention that the Steins lack standing to challenge the mechanic's lien on their individual unit because it was recorded based on work done pursuant to a contract with the Association. While its contract was with the Association, the lien was recorded against all the individual unit owners, as required by section 718.121(2), Florida Statutes (2025).
Liens on condominiums are controlled by section 718.121, Florida Statutes. Paraphrasing, subsection (1) provides that, after the declaration of condominium is recorded, no liens are valid against condominium property as a whole unless the unit owners unanimously consented thereto. Subsection (2) prohibits liens for work on individual units unless the unit owner expressly consented to or requested the work. However, it further provides that work performed on the common elements cannot give rise to a lien, but if authorized by the condominium association a lien may
be claimed against all of the condominium parcels in the proportion for which each unit is liable for common expenses. The condominium association authorization is deemed to furnish the express consent of each unit owner.
Royal Ambassador Condo. Ass'n v. E. Coast Supply Corp., 495 So. 2d 932, 934 (Fla. 4th DCA 1986). And so, by operation of section 718.121(2), Reynolds' contract with the Association served as the authorization to "furnish[] the express consent of each unit owner" to the lien in each unit owner's proportionate share of the common expenses for the work performed by Reynolds.1 Once recorded, "section 718.121(3) confirms that if a valid lien encumbers multiple condominium parcels, each owner of an encumbered parcel may exercise the rights of a property owner under Chapter 713 . . . ." Trintec Constr., Inc. v. Countryside Vill. Condo. Ass'n, 992 So. 2d 277, 279 (Fla. 3d DCA 2008); see also Royal Ambassador, 495 So. 2d at 934 ("Finally, subsection (3) enables the individual unit owners to remove or discharge a lien covering more than one unit by exercising any of the rights provided an owner by Chapter 713, Florida Statutes, or by paying his proportionate share of the claim."). Therefore, Reynolds' recording of the lien under 718.121(3) triggered the Steins' right to discharge that lien under chapter 713. It follows that because the Steins were interested parties named in the lien they had standing to seek discharge of the lien on their own unit under section 713.21.2
1 The Steins do not challenge the Association's authority to enter
into the contract with Reynolds.
Free access — add to your briefcase to read the full text and ask questions with AI
Stein, Stein v. Reynolds Ventures, Inc., Wrightway Emergency Water Removal (Stein, Stein v. Reynolds Ventures, Inc., Wrightway Emergency Water Removal) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.