Steel Service Corp. v. Board of County Commissioners

258 F. App'x 825
CourtCourt of Appeals for the Sixth Circuit
DecidedDecember 27, 2007
Docket07-3251
StatusUnpublished

This text of 258 F. App'x 825 (Steel Service Corp. v. Board of County Commissioners) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steel Service Corp. v. Board of County Commissioners, 258 F. App'x 825 (6th Cir. 2007).

Opinion

OPINION

RONALD LEE GILMAN, Circuit Judge.

In December of 2000, the Board of County Commissioners of Hamilton County, Ohio (the County) awarded Steel Service Corp., a Mississippi corporation, the general contract (the Contract) for the erection of the steel superstructure for the Cincinnati Reds Great American Ball Park (the Ball Park). By October of 2001, the County had directed Steel Service to accelerate its work to make up for delays that had occurred on the project. Steel Service did so, and in December of 2001 submitted a claim to the County for its additional costs, including extra costs incurred by its subcontractors. A month later, the County and Steel Service executed Change Order # 1, with neither party accepting responsibility for the delays, but agreeing that the County would make a provisional payment to Steel Service that would apply toward the latter’s additional costs for the accelerated work. In 2004, Steel Service filed suit against the County for breach of contract, alleging that the County had not paid Steel Service’s additional costs, which then totaled approximately $5 million.

The County moved for summary judgment, arguing that Steel Service’s claim was settled by Change Order # 9, executed in August of 2003, and that a portion of Steel Service’s claim was a “pass-through” claim on behalf of its subcontractors that is *827 not cognizable under Ohio law. The district court granted summary judgment for the County on these grounds. For the reasons set forth below, we REVERSE the judgment of the district court and REMAND the case for further proceedings consistent with this opinion.

I. BACKGROUND

On December 20, 2000, the County and Steel Service entered into the Contract, whereby Steel Service agreed to act as the general contractor in the fabrication and erection of the steel superstructure for the Ball Park. The initial contract sum was approximately $33 million. Several documents comprise the Contract, including a Standard Form of Agreement and the General and Supplementary Conditions, both of which were executed on American Institute of Architects (ALA) forms that were modified for the Ball Park project. Evidence in the record indicates that the County drafted the Contract, which was awarded through a public bidding process.

Work on the project commenced on or about December 21, 2000. Based on the initial construction schedule, Steel Service claims that it was to begin erection of the steel superstructure in April of 2001 and complete the project by December of that same year. Delays ensued, however, and actual construction did not begin until July of 2001. Neither party has accepted responsibility for the delays.

In October of 2001, Hunt Construction Group, Inc., the Construction Manager for the County, directed Steel Service in writing to undertake “Extraordinary Measures, including the provision of additional manpower, shifts, overtime and equipment” in order to complete its work in accordance with the Contract and the project construction schedule. The record indicates that Hunt had issued the same directive in both May and September of 2001. Whether the May directive was made orally or in writing is unclear; the September directive was indisputably oral.

Paragraph 8.2.7 of the Contract defines Extraordinary Measures as “work[ing] additional shifts or overtime, supply[ing] additional manpower, equipment and facilities, and ... other similar measures.” The same paragraph requires Steel Service to take such measures, at the County’s expense, if the County deems them necessary. But paragraph 8.2.8 obligates Steel Service to take Extraordinary Measures at its own expense if the delays result from any fault, neglect, omission, or act of Steel Service. Steel Service alleges that the Extraordinary Measures it was directed to take were necessary to make up for time lost as a result of the County’s inattention to the project, incomplete and inadequate structural-steel designs provided by the County, and the County’s constant revisions to the designs—all of which, it claims, disrupted and hindered its performance. Neither the County’s brief, nor the record generally, contains an explanation from the County as to why the Extraordinary Measures were necessary.

Steel Service confirmed the Extraordinary Measures directive in a letter to Hunt dated October 8, 2001, and alerted Hunt that Steel Service would “be submitting a claim to you for any and all costs” related to the directive. In December of 2001, Steel Service sent a second letter to Hunt, this time containing Steel Service’s “claim for equitable contract adjustment resulting from your direction to accelerate [Steel Service’s] work” on the project. The letter contained a “Claim for Additional Costs.” Steel Service asserted in the letter that, “[p]er the terms of our Contract, particularly 4.7.7, 8.2 and 8.3, Steel Service is entitled to the compensation requested for the extraordinary measures required to implement the directed Recovery Schedule as discussed below and as referenced in *828 Steel Service’s Initial Notice of Intent to File Claim dated October 8, 2001, and Recovery Schedule letter dated October 12, 2001.”

“Claims” are governed by paragraphs 4.7 and 4.8 of the Contract. Paragraph 4.7.1 defines a “Claim” as

a demand or assertion by one of the parties seeking, [as] a matter of right, adjustment or interpretation of Contract terms, payment of money, extension of time or other relief with respect to the terms of the Contract. The term “Claim” also includes other disputes and matters in question between the [County] and [Steel Service] arising out of or relating to the Contract. Claims must be made by written notice. The responsibility to substantiate Claims shall rest with the party making the Claim. [Steel Service] shall be entitled to make a Claim for an increase in the Contract Time and the Contract Sum for actual costs incurred by [Steel Service] for reasons other than the failure of [Steel Service] to perform its obligations under the Contract Documents.

Paragraph 4.7.7 of the Contract permits Steel Service to file written notice of a claim for an increase in the contract sum, and paragraph 4.8.5 requires the parties to submit claims to mediation before initiating litigation. Terms relating to time— including time limits, job progress, and Extraordinary Measures—are addressed in paragraph 8.2. Delays, acceleration, disruption, and extensions of time are governed by paragraph 8.3.

Just over a month after Steel Service alerted Hunt of its Claim, Steel Service, the County, and Hunt, along with the project manager, architect, and the Cincinnati Reds, executed the first of nine change orders. Change Order Number 1 (CO # 1) sets forth the parties’ agreement relating to Steel Service’s initial claim for additional compensation in the amount of $3,292,000 for the Extraordinary Measures it had been directed to take by Hunt. CO # 1 states that “[o]n December 18, 2001, pursuant to Articles 4.7.7, 8.2 & 8.3 of the Contract, [Steel Service] submitted a Recovery Claim Cost Document seeking the sum of approximately ... $3,292,000.00 from the [County] ... (the ‘Claim’).”

The parties acknowledge in CO # 1 that Steel Service had already begun to implement the Extraordinary Measures and that Steel Service had incurred, and would continue to incur, costs associated with such measures.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
International Union v. Cummins, Inc.
434 F.3d 478 (Sixth Circuit, 2006)
Abrams v. Siegel
850 N.E.2d 99 (Ohio Court of Appeals, 2006)
Latina v. Woodpath Development Co.
567 N.E.2d 262 (Ohio Supreme Court, 1991)
Hamilton Insurance Services, Inc. v. Nationwide Insurance
714 N.E.2d 898 (Ohio Supreme Court, 1999)
Saunders v. Mortensen
801 N.E.2d 452 (Ohio Supreme Court, 2004)
Schachner v. Blue Cross & Blue Shield
77 F.3d 889 (Sixth Circuit, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
258 F. App'x 825, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steel-service-corp-v-board-of-county-commissioners-ca6-2007.