Steamship Rutherglen Co. v. Howard Houlder & Partners, Inc.

196 F. 916, 1910 U.S. Dist. LEXIS 9
CourtDistrict Court, S.D. New York
DecidedOctober 18, 1910
StatusPublished

This text of 196 F. 916 (Steamship Rutherglen Co. v. Howard Houlder & Partners, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steamship Rutherglen Co. v. Howard Houlder & Partners, Inc., 196 F. 916, 1910 U.S. Dist. LEXIS 9 (S.D.N.Y. 1910).

Opinion

UOUT, District Judge.

These are a libel and cross-libel filed to recover claims arising out of a shipment of a cargo of railroad iron on the steamship Rutherglen on a voyage from New York to Dalny, Manchuria, and thence to Takow, Formosa. The original libel was filed by the owner of the Rutherglen against Howard Houlder & Partners, Inc., the charterers of the steamer, to recover upon three claims: (1) A claim for an unpaid balance of the lump sum chartered freight of £277.7.7, amounting in United States currency to $1,349.86. (2) A claim for 15J/> days’ demurrage while awaiting discharge at Dalny, at the rate of £45.14 per day, making a total of £708.7, or, in United States currency, $3,447.17. (3) A claim for an excess agency fee charged to the steamship by the agents designated by the charterers at Takow in the sum of £14.10, or $70.56. The cross-libel is to recover damages because the steamer was not loaded to her full capacity. It alleges that the steamer when she sailed had 13,112 empty cubic feet of space, which would have stowed 325 tons of cargo, and that the charterers were damaged by the steamer’s refusal to take said additional cargo in the sum of £466.17.6, making £169.9.11 due, in addition to the sum of £277.7.7, withheld by the charterers from the lump sum freight.

[1] 1. '1'lie charter party was made in New York. It guaranteed the steamer's dead weight capacity at “6,100 tons of 20 cwt.” A ton of 20 cwt. in this country usually means a short toil of 2,000 pounds. Tut this was a charter party of an English vessel, and there is evi[918]*918dence in the case that the generally understood meaning of the term “ton” as used in charter parties is a long ton; that is to say, that the term “cwt.” means a weight of 112 pounds, the usual meaning of the term in England, instead of 100 pounds. It does not appear to be contradicted by the counsel for the Rutherglen that that is the correct meaning of the phrase, and I shall assume that the charter party guaranteed that the steamer had a dead weight capacity of 6,100 tons of 2,240 pounds each. The evidence in my opinion shows that the actual weight of the cargo carried was 13,1/3,389 pounds, amounting to 5,880.97 long tons. With this amount of cargo the ship was overloaded, and in ,my opinion, upon the evidence, the ship could not carry 6,100 long tons, and the owner-is liable under the guaranty that she could carry that amount. The price to be paid for the steamer as fixed in the charter was the lump sum of ¿9,400. The evidence in the case is not sufficiently clear and specific to enable me to pass satisfactorily on the question what- amount of deduction should be made from the lump sum freight in view of the claim made in the cross-libel of the respondents. A reference will be directed upon that point.

[2] 2. The second claim in the libel is to recover $3,447.17 for 15% days’ demurrage at Dalny. The steamer, when she arrived at Dalny, could not get a berth where she could lie without discharging a part of her cargo, and was obliged to wait 15% days before she could get such a berth at which to discharge. The charter party provided that the charterers were to provide lighters, if necessary, to enable the steamer to go alongside of any safe dock, wharf, or anchorage. There were vacant berths at Dalny where the steamer could have gone alongside and discharged, if about 500 tons of cargo had been removed upon lighters. It is claimed that -no lighters could be obtained at Dalny. The evidence is that there were junks which could have been obtained. The respondent claims that they were fishing junks, unfit to be used for the discharge of heavy railroad iron, but the evidence is that there were large junks there which could have been obtained. It is also claimed that, if the iron had been discharged into; any of these junks, it could not have been unloaded from the junks onto the wharf. The evidence does not satisfy me that such was the case, but', if 500 tons had been put upon junks, that would have enabled the steamer to go to her wharf and begin unloading, and then, if necessary, the iron on the junks could have been taken back after an equivalent amount had been taken out from the steamer. There is a provision in the charter party that any time lost in loading or discharging through various causes, and, among others, through any causes beyond the personal control of the charterers, is not to be computed as part of the lay dhys; and it is claimed that the charterers could not obtain lighters, and that, therefore, they were absolved from the obligation to obtain lighters. But I think that that provision does not nullify the other positive provision of the charter party that the charterers should provide lighters, if necessary, to enable the steamer to go alongside a safe dock. This was a voyage charter. The owner [919]*919was entitled to have the ship make the voyage and return promptly, and I think that the charterers by the charter in substance agreed to provide lighters, if necessary, to discharge the cargo at Dalny promptly, and agreed that, if that was not done, they would be liable for de-murrage.

The charterers rely on a clause in the charter party that the vessel is to be discharged according to the custom of the port, and have called a witness who testified that it was the custom of the port at Dalny for steamers to discharge in turn. This witness had been at Dalny but once, and was hardly qualified to prove custom. But probably the alleged custom was nothing but the usual practice of harbor masters in all ports. A common sense of justice would lead any harbor master to send steamers to vacant berths in their turn. But I do not understand that the libelant complains that the Rutherglen was not admitted to a dock deep enough for her draft as soon as one was vacant. The complaint is that no lighters were provided! so that, by taking off a part of her cargo, she could have gone at once to a shallower berth which was vacant.

[3] The charterers further rely upon the cesser clause in the charter, which provides: “Charterers’ liability to cease on cargo- being shipped, and freight paid.” The Rutherglen Company claims that that clause does not apply because the lump sum freight was not paid in full, but, as in my opinion the charterers were justified in the deduction which they made, the just amount due for the lump sum freight was paid in full. The question recurs then whether the cesser clause applies, so as to free the charterers from their specific agreement to provide lighters, if necessary, at the port of discharge. The question is a nice one. Some authorities have undoubtedly gone very far in holding charterers exonerated by the cesser clause from all claims arising at the port of discharge. But I concur with Judge Hough in the case of Union Steamshipping Co. v. Gans Steamship Line,1 that:

“If the charter party contains an agreement between the owner and the charterer which cannot he performed and cannot even be entered upon when the cargo is shipped or wiien bills of lading are signed at the loading ports, the charter must continue in existence until that portion of the contract relating to some other placo and to a future time is completed.”

If the provision in the charter party that the charterers are to provide lighters, if necessary, at the port of discharge is nullified by the cesser clause, there was no reason for inserting it in the charter party. It never had any validity. It died at birth.

In this case the Manchurian Railway was being constructed.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
196 F. 916, 1910 U.S. Dist. LEXIS 9, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steamship-rutherglen-co-v-howard-houlder-partners-inc-nysd-1910.