Steamship Rutherglen Co. v. Howard Houlder & Partners, Inc.

203 F. 848, 122 C.C.A. 166, 1913 U.S. App. LEXIS 1209
CourtCourt of Appeals for the Second Circuit
DecidedFebruary 10, 1913
DocketNos. 130, 131
StatusPublished
Cited by10 cases

This text of 203 F. 848 (Steamship Rutherglen Co. v. Howard Houlder & Partners, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steamship Rutherglen Co. v. Howard Houlder & Partners, Inc., 203 F. 848, 122 C.C.A. 166, 1913 U.S. App. LEXIS 1209 (2d Cir. 1913).

Opinion

WARD, Circuit Judge.

The owners of the British steamer Rutherglen chartered her to Howard Houlder & Partners for a voyage from New York to Dalny and Takow, Formosa, with a cargo of railway material which has been duly delivered. Various disputes have arisen between the parties which are now to be disposed of.

[1] 1. The owners filed a libel to recover an unpaid balance of charter hire. The charter called for a lump sum hire of ¿9,400 to [850]*850be paid before sailing. The charterers paid only £9,122.12.6, claiming that the vessel fell short of the dead weight capacity guaranteed by the owners to the extent of 219.3 tons. The charterers filed a cross-libel to recover the freight engaged for the cargo shut out by this breach of guaranty.-

The District Judge found that the vessel did fall short of the guaranty as claimed by the charterers, and that the bill of lading freight coming to them for cargo shut out would be, if it had been carried, £397.11.6. He allowed to the charterers the difference between the charter hire and the bill of lading freight, to wit, £120.3.11. The owners claim that the charterers are only entitled to the difference between the unpaid charter hire, £277.7.7, and £120.3.11, the profit on the bill of lading freight. This would result in the charterers being liable to the owners on this account for the sum of £157.3.8.

We think the District Judge was right. If the vessel had conformed to the guaranty the charterers would owe £277.7.7. Because it did not, they have lost £397.11.6. Setting one claim off against the other, the difference is against the owners and in favor of the charterers, £120.3.11.

The court below entered a decree in each action, the effect of which is precisely the same as if the better practice of entering one decree as in case of bill and cross-bill in equity had been followed. The contention of the owners is manifestly wrong, because it makes the charterers pay £157.3.8 for cargo space they never received, and this for the singular reason that they had sustained an additional loss of £120.3.11. In other words, if they had not engaged at a profit the cargo shut out, they would have been better off, because they would have been allowed £277.7.7 for the cargo capacity short, instead of £157.3.8.

■ 2. The owners claim 15% days’ demurrage at Dalny, and the District Judge allowed it. The provisions as to demurrage are as follows:

“Fifteen (15) running days, Sundays and holidays excepted, to be allowed charterers for loading steamer and the cargo to be discharged with all possible speed, according to the custom of the port of discharge. Vessel to receive cargo on clearing day if required, free of demurrage. Demurrage over and above the said lay days to be paid at the rate of four pence per net register ton per day for each and every day the steamer is detained at port of loading by the default of the charterers.”

The steamer arrived December 17th, was free of pratique on the morning of December 18th, and on that day served notice of readiness to discharge upon the charterers’ agents. She did not get into her berth until January 2d, nor begin discharging until January 3d. The District Judge allowed demurrage at the rate of four pence per net registered ton for every day from December 19th to January 3d.

[2] The charterers contend that they were relieved of liability for anything occurring at Dalny by virtue of the cesser clause, which reads:

“Charterers’ liability to cease on cargo being shipped and freight paid.”

The freight was paid at New York on the shipment of the cargo," and the owners make no claim for demurrage or anything else occur[851]*851ring there. The clause would protect the charterers from liability for anything done at the discharging port by others, hut not for anything which they had themselves agreed to do. The charter contemplates that the charterers will receive the cargo at Dalny. It provides that in certain circumstances they will be obliged to provide lighters, and that for delay in discharging, due to certain excepted causes, they are not to be liable, and that the vessel is to be consigned to their agents. Accordingly the cesser clause does not protect them from liability for delay incurred in discharging at Dalny not within the exceptions.

[3] There is a wilderness of law upon the subject of demurrage. The decisions depend upon the language of the various charters and are difficult to reconcile. Mr. Carver has laid down six propositions in his work on Carriage by Sea (section 623), which have been approved in the case of Leonis S. S. Co. v. Rank, 1 K. B. (1908) 499. We need not consider them, because they are confined to charters which provide for a fixed number of lay days within which a charterer is bound to load or unload, and which generally, as in the case of the Reonis Company, define precisely when the lay days shall begin to run. Notwithstanding these propositions, it is the law in England that, where no lay days are provided for, the charterer is only required to load and receive cargo with reasonable diligence. Carver, Carriage by Sea, § 628; Hulthen v. C. A. Stewart & Co. [1903 ] A. C. 389; Id., 8 Com. Cas. 297. What constitutes reasonable diligence will depend upon all the circumstances of the case; among others, the character, condition, and customs of the port of loading and discharging. In such a case, where no place of loading is specified, nor any agreement that the vessel shall go to a berth as ordered, the charterer has the right to name the loading or discharging place; but, if he does not do so within a reasonable time, the master may choose one for himself.

[4] In the present case the charter did provide lay days for loading, the rate payable for demurrage, and that the vessel should load at a berth or berths as ordered by the charterers. In respect to discharging, however, it only provided that “the cargo be discharged witli all possible speed according to the custom of the port of discharge,” and that any time lost in discharging for certain excepted causes, should not lie chargeable to the charterers. The owners admit that, after the discharge began, the cargo was received without delay. When the steamer arrived at Dalny, all berths where she could lie afloat were occupied or congested with freight, and neither the charterers’ agents nor the master of the steamer were able to get a berth for her sooner. In such circumstances we do not think that the charterers can be said to be chargeable with any lack of reasonable diligence in discharging.

The District Judge, however, held that the charterers were bound to employ lighters to take off enough cargo to enable the vessel to lie afloat safely at one of the unoccupied berths, where there was not water enough for her when fully loaded. It was his opinion that they could have obtained such lighters, but, even if they could not, that [852]*852they were liable for not enabling the steamer to go to such a berth, and so saving time in discharging. He rested his conclusion upon the parenthetical clause, supra:

“(Charterers to provide lighters, if necessary, to enable steamer to go alongside any safe dock, wharf, or anchorage as ordered Where steamer shall discharge always afloat.)” (

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
203 F. 848, 122 C.C.A. 166, 1913 U.S. App. LEXIS 1209, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steamship-rutherglen-co-v-howard-houlder-partners-inc-ca2-1913.