Steak & Ale Restaurants of America v. Commonwealth

70 Pa. D. & C.2d 582
CourtPennsylvania Environmental Hearing Board
DecidedSeptember 17, 1974
DocketDocket no. 74-039-W
StatusPublished

This text of 70 Pa. D. & C.2d 582 (Steak & Ale Restaurants of America v. Commonwealth) is published on Counsel Stack Legal Research, covering Pennsylvania Environmental Hearing Board primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steak & Ale Restaurants of America v. Commonwealth, 70 Pa. D. & C.2d 582 (Pa. Super. Ct. 1974).

Opinions

WATERS, Member,

This matter comes before the board as an appeal from the denial of a permit to appellant for connection of a commercial establishment, a Steak and Ale Restaurant, to the south plant of the East Pennsboro Township Authority. The sewage treatment plant in question was the subject of a [584]*584previous order of the board which found an hydraulic overload at the plant and limited future connections to three new residential dwellings per month, unless the parties agreed to some other equivalent distribution of the three permits on a case by case basis, until the plant capacity problem, which was being addressed, was completely solved.

Appellant presented testimony at the hearing to support an appeal based on a belief that, if the sewage was released from its business establishment at night, then the plant design limit of 1.12 million gallons per day would not be adversely affected.

A motion to dismiss the appeal was made, but was denied when appellant raised another issue concerning the lack of due process by permitting some connections and prohibiting others. It is argued that there must be an “all or none” rule applied, and any other solution is constitutionally inappropriate.

FINDINGS OF FACT

1. Appellant, Steak and Ale Restaurants of America, Inc., applied for a sewage permit for connection to the south plant of the East Pennsboro Township Authority, which is presently under a partial sewer ban.

2. The partial sewer ban presently in effect at the plant was imposed by order of this board as a modification of a complete ban which had previously been imposed by the Department of Environmental Resources in response to an overload of the plant capacity.

3. The south treatment plant of East Pennsboro Township has a capacity of 1.12 million gallons per day, but has been and is receiving flows in excess of that amount.

[585]*5854. The board, in modifying the complete sewer ban to alimited ban, found no organic overload, and found that the authority was making substantial efforts to solve the hydraulic overload.

5. Considering all of the circumstances of that case, a complete sewer ban was not deemed to be reasonable by the board.

6. Appellant had informal meetings with the department to obtain the permit it seeks, but these meetings were not fruitful, and appellant now feels that due consideration was never really given to its application.

7. Appellant has devised a system whereby all of the discharge from its establishment into the sewage system would be made by a time release at night when the south plant receives a low flow.

CONCLUSIONS OF LAW

1. The board has jurisdiction over the parties and the subject matter.

2. The introduction of sewage into a public system going to a treatment plant which is already hydraulically overloaded cannot be allowed on the basis that it will be released at a time of lowest flow to the plant during the 24-hour period.

3. The board may properly modify a sewer ban by allowing a limited number of new connections where there is no substantial organic overload, and where limited connections present no public health hazard.

4. The board must permit the department to carry out its discretionary administrative function in determining which connections pose the least threat to an hydraulically overloaded treatment plant so long as the decisions are not arbitrary or unreasonable.

[586]*5865. The Clean Streams Act authorizes the department to prohibit any additional sewer connections to a municipal system, and this authority includes the power to limit the number of such connections under proper circumstances.

6. The order of the board issued in the matter of East Pennsboro Township Docket no. 73-287-W permitting three residential dwellings per month and only such other connections as were agreed upon between the department, township, and township sewer authority, is not so vague as to violate the due process clause of the State or Federal Constitution.

7. Equal protection of the law guarantees only that all persons, within a particular classification, shall be treated equally before the law, provided that the classes themselves have some reasonable and proper basis for distinction.

DISCUSSION

Appellant desires to establish a restaurant in East Pennsboro Township and to discharge sewage to a hydraulically overloaded treatment plant.

It is clear to us that, if this is to be permitted, it will not be on the basis of any theory that turns on the time of day (or night) that is selected for the discharge of sewage into the public system. It would seem to be beyond question that, if a treatment plant has a capacity of 1.12 million gallons per day, that same system does not gain additional capacity at night. The hearing in this proceeding was largely given over to the above proposition, and we would have granted the motion to dismiss the case if this were the sole issue raised by this ap[587]*587peal.1 It is the department’s position that appellant may not now attack the order issued by the board in March 1974, and appealed only by the township. We disagree. Appellant had neither reason nor standing to appeal the order until the application for a permit was denied.2

Appellant raises three issues — two constitutional and one statutory — which now deserve our attention. First, it is argued that under the Clean Streams Act the board is without authority to limit the total number of connections to a public sewage system. It is argued that the law allows all applications to hook up or, where there is danger to public health, no applicant may hook up.3 What the department or this board may not do, appellant urges, [588]*588is impose a monthly quota on connections. At first blush this appears to be a weighty and cogent argument. If this argument were applied to a case where an organic overload were the sole issue, we would agree emphatically. This, however, is not the case. Here we are dealing with a limited ban imposed because of a much more speculative, and difficult to prove, danger to public health, which comes from exceeding the plant capacity due to infiltration of water, usually from a source having nothing to do with sewage, i.e., rainwater and surface water. It is for this reason that we believe a limited sewer connection order was proper in the first instance. The Clean Streams Act states that the department orders:

“. . . may prohibit sewer systems extensions, additional connections, or any other action that would result in an increase in the sewage that would be discharged into an existing sewer system or treatment facility.”: 35 PS §691.203.

We believe this language was intended by the legislature to have a liberal construction.4 It is axiomatic that the greater includes the lesser. Where the department is authorized to prohibit all connecr tions beyond a given number, this is deemed to be the maximum that will permit the plant to operate without posing a threat to public health. It is admittedly difficult if not impossible to determine the exact number, any excess of which would create a danger to health. There is no “magic” number.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hannah v. Larche
363 U.S. 420 (Supreme Court, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
70 Pa. D. & C.2d 582, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steak-ale-restaurants-of-america-v-commonwealth-paenvhrbd-1974.