Ste. Genevieve County Levee District 2 v. Luhr Bros., Inc.

288 S.W.3d 779, 2009 Mo. App. LEXIS 854, 2009 WL 1659968
CourtMissouri Court of Appeals
DecidedJune 16, 2009
DocketED 91297
StatusPublished
Cited by10 cases

This text of 288 S.W.3d 779 (Ste. Genevieve County Levee District 2 v. Luhr Bros., Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ste. Genevieve County Levee District 2 v. Luhr Bros., Inc., 288 S.W.3d 779, 2009 Mo. App. LEXIS 854, 2009 WL 1659968 (Mo. Ct. App. 2009).

Opinion

OPINION

GLENN A. NORTON, Judge.

Luhr Bros., Inc. (“Contractor”) appeals from the judgments of the trial court (1) denying its motion for summary judgment and (2) enforcing the settlement between Ste. Genevieve County Levee District # 2 (the “Levee District”) and Contractor. We affirm. 1

I. BACKGROUND

Following the flood of 1993, the United States Army Corps of Engineers (the “Corps”) awarded a construction contract to Contractor for the construction of a portion of a levee project in Ste. Genevieve County. The levee project was performed pursuant to a Project Cooperation Agreement (the “PCA”) executed by the Corps and the Ste. Genevieve County Levee Commission (the “Commission”), of which the Levee District was a member.

After the levee project was completed, the Levee District brought suit against the Contractor asserting claims of trespass and conversion based on allegations that Contractor exceeded the scope of the PCA by removing gravel and other material from the project site. The Levee District’s petition was filed on April 27, 2004.

On September 9, 2005, Emerald Loida, president of the Levee District, met with Mike Luhr, Contractor’s president, to discuss settlement. At the meeting, Loida and Luhr discussed the value of the rock allegedly removed by Contractor. Loida testified that while the Levee District had initially demanded a higher price per yard, Luhr presented an offer to settle the Levee District’s claims for $6.63 per yard, or $218,790. 2 Loida told Luhr that he would have to call a board meeting and seek approval from the majority of the Levee District’s board of directors before he could agree to settle the lawsuit. Loida and Luhr agreed to meet again following *782 Loida’s meeting with the Levee District’s board.

The Levee District’s board met on September 16, 2005, and, after much discussion, agreed to authorize Loida to settle the case for $218,790. Loida and Luhr met again on November 30, 2005. At the November 30 meeting, Loida told Luhr that the Levee District accepted Contractor’s offer; however, after Loida’s acceptance, Luhr informed Loida that the Corps rejected the proposed settlement and therefore he was not authorized to settle the case.

Following the November 30 meeting with Luhr, Loida reported back to the board’s secretary that upon accepting the offer, “Luhr backed off on it.” There is no written confirmation or documentation of a settlement. The testimony showed that the members of the Levee District’s board did not think that they could enforce the settlement. Consequently, over two years passed, and the case was set for trial.

Thereafter, Contractor filed a motion for summary judgment on the grounds that the Levee District’s claims were barred because Contractor was protected by the doctrine of governmental immunity. The trial court denied the Contractor’s motion.

The week before trial was set to commence, the Levee District filed a motion to enforce settlement. On January 30, 2008, the day the case was set for trial, the court held a hearing on the Levee District’s motion. The court asked the Levee District why it waited over two years to file its motion. Counsel for the Levee District explained that his clients only recently told him about the settlement because they did not think that they could compel its enforcement. In response to the Levee District’s motion, Contractor argued that no settlement was reached be-' tween the parties because no offer was made by Luhr and therefore no meeting of the minds could have occurred. Contractor also argued that the Levee District should be precluded, on the basis of equity, from enforcing any alleged settlement. Ultimately, the court granted the Levee District’s motion and entered judgment enforcing the terms of the settlement. Contractor appeals.

II. DISCUSSION

Contractor raises two points on appeal. However, as Contractor’s second point does not merit detailed analysis, we address it first. In Contractor’s second point on appeal, it argues that the trial court erred in denying Contractor’s motion for summary judgment. Generally, an order denying a party’s motion for summary judgment is not a final judgment and is therefore not subject to appellate review. Hussmann Corp. v. UQM Electronics, Inc., 172 S.W.3d 918, 922 (Mo.App. E.D.2005). Accordingly, Contractor’s second point is denied.

A. The Levee District’s Motion to Enforce Settlement

In the sole point subject to our review, Contractor argues that the trial court erred in entering its judgment enforcing a settlement between the parties.

1. Standard of Review

When reviewing a trial court’s judgment enforcing a settlement, we will affirm unless the judgment is against the weight of the evidence, there is no substantial evidence to support it, or the court erroneously applied or declared the law. Woods ex rel. Woods v. Cory, 192 S.W.3d 450, 458 (Mo.App. S.D.2006), citing Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976). We view the evidence in the light most favorable to the trial court’s judgment, disregarding all contrary inferences and evidence. Woods, 192 S.W.3d at 458. We “defer[ ] to the trial court’s findings of fact, recognizing the superior abili *783 ty of the trial court to judge the credibility of the witnesses.” Id. Thus, we will set aside a judgment as against the weight of the evidence only upon a firm belief that the trial court was wrong. Id.

Moreover, “[a] motion to enforce settlement adds a collateral action for specific performance of the agreement.” Kenney v. Vansittert, 277 S.W.3d 713, 720 (Mo.App. W.D.2008). Because specific performance is an equitable remedy, we will afford the trial court great deference in ruling on the motion. Id.

2. The Trial Court’s Judgment Enforcing the Settlement between Contractor and the Levee District is Supported by Substantial Evidence and does not Erroneously Apply the Law

Contractor argues that the trial court erred in entering its judgment enforcing a settlement between the parties because the evidence does not support a finding that a valid offer to settle the lawsuit was made by Contractor and accepted by the Levee District and, in the alternative, because principles of equity preclude enforcement of any settlement.

a. The Evidence Supports a Finding that an Enforceable Settlement Agreement Existed Between the Parties

A party seeking to enforce a settlement must prove the existence of a settlement by clear, convincing and satisfactory evidence. Eaton v. Mallinckrodt, Inc.,

Related

Clifton Jameson v. Alexis Still
Supreme Court of Missouri, 2022
Frame v. Garcia
E.D. Missouri, 2020
Collector of Revenue v. Wiley
529 S.W.3d 42 (Missouri Court of Appeals, 2017)
Voyles v. Voyles
388 S.W.3d 169 (Missouri Court of Appeals, 2012)
REPPY v. Winters
351 S.W.3d 717 (Missouri Court of Appeals, 2011)
Williams v. KANSAS CITY TITLE LOAN CO.
314 S.W.3d 868 (Missouri Court of Appeals, 2010)
St. Louis Union Station Holdings, Inc. v. Discovery Channel Store, Inc.
301 S.W.3d 549 (Missouri Court of Appeals, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
288 S.W.3d 779, 2009 Mo. App. LEXIS 854, 2009 WL 1659968, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ste-genevieve-county-levee-district-2-v-luhr-bros-inc-moctapp-2009.