Statesboro Erectors, Inc. v. Owners Insurance Company

District Court, N.D. Georgia·Decided September 30, 2024·No. 1:23-cv-02664·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF GEORGIA ATLANTA DIVISION

STATESBORO ERECTORS, INC., Plaintiff, Civil Action No. v. 1:23-cv-02664-SDG OWNERS INSURANCE COMPANY, Defendant.

OPINION AND ORDER This case is before the Court on Defendant Owners Insurance Company’s motion for summary judgment [ECF 13]. After careful consideration, and with the benefit of oral argument, the Court DENIES the motion. I. Background This is an insurance dispute that arises out of a contract between Plaintiff Statesboro Erectors and non-party King Steel whereby King Steel engaged Statesboro as a subcontractor to perform certain construction work.1 While working on the project, an accident occurred and caused damage on the work site.2 King Steel sought payment from Statesboro in connection with the accident.3 Statesboro maintained an insurance policy issued by Owners.4 Statesboro filed

1 ECF 12, ¶ 1. 2 Id. ¶ 9. 3 Id. ¶ 11. 4 Id. ¶ 27. claims seeking coverage for the accident. Owners paid certain claims, but denied others.5 Statesboro then filed suit, contending that Owners wrongfully denied

coverage and seeking to recover the $456,874 in damages it paid to King Steel.6 The two-count complaint alleges breach of contract and bad faith penalties against Owners.7

A. The steel collapse. Non-party Griffco was the general contractor for a construction project in McDonough, Georgia. King Steel was hired as the “steel fabricator” on the project.8 King Steel subcontracted with Statesboro for Statesboro to complete certain

construction work at the site.9 Specifically, Statesboro agreed to: (1) Prepare all necessary temporary bracing drawings and/or critical lift plans; and (2) perform all work and shall furnish all supervision, management, labor, materials, tools, equipment, cranes, safety equipment and procedures, licenses and permits, supplies and all other things necessary for the complete, proper and safe erection of the structural steel in full accordance with the plans, specifications, and all work incidental . . . thereto, in strict accordance with the terms of the Subcontract; and to the satisfaction of [Griffco] and [Ken’s Foods] (“Work”).10

5 Id. ¶ 19. 6 ECF 1. 7 Id. ¶¶ 46–55. 8 ECF 12, ¶ 3. 9 Id. ¶ 1. 10 Id. ¶ 4. On October 9, 2021, there was a steel collapse at the construction site.11 According to King Steel, the collapse “appeared to have occurred due to lack of

temporary cables or bracing for steel columns.”12 Because of the collapse, King Steel was required to supply additional materials to replace the structural damage caused by the collapse.13

B. The demand letters. After the collapse, the involved entities sent various demand letters seeking to ensure that the correct entity paid for the damage. First, King Steel sent Statesboro a letter on March 1, 2022 seeking $426,291.89 in damages to allow King

Steel to “supply additional structural steel…and joists to replace the structural steel damaged in the collapse.”14 A week later, King Steel sent a second letter to Statesboro, this time demanding payment of an additional $410,385.27.15 This request was based on the deductive change order King Steel received from

Griffco.16

11 Id. ¶ 9. 12 ECF 12-1, at 2. 13 Id. 14 Id. 15 ECF 12-2, at 2. 16 ECF 12, ¶ 13. As Statesboro’s insurer, Owners responded to the letters. It denied coverage for the $426,291.89 claim, but requested additional information with respect to the

deductive change order in the amount of $410,385.27.17 Owners and King Steel ultimately reached a settlement and Owners agreed to pay a portion of this amount.18 Months later, King Steel sent a demand letter to Statesboro seeking

immediate payment of the $468,266.89 it had demanded.19 King Steel also requested that the parties mediate the dispute, which Statesboro agreed to do. Statesboro requested that Owners participate in the mediation, which Owners declined to do.20 During the mediation, Statesboro and King Steel reached a

settlement—Statesboro agreed to pay King Steel $456,874.21 Statesboro then sent Owners a letter demanding reimbursement for the $456,874.22 Owners denied this request because, according to Owners, it was

payment for items not covered by Statesboro’s insurance policy.23

17 ECF 12-3, at 3. 18 ECF 12, ¶ 19. 19 Id. ¶ 18. 20 Id. 21 Id. ¶ 25. 22 Id. 23 Id. ¶ 26. II. Legal Standard Summary judgment is appropriate when “there is no genuine dispute as to

any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). A fact is “material” only if it can affect the outcome of the lawsuit under the governing legal principles. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). A factual dispute is “genuine . . . if the evidence is such that a

reasonable jury could return a verdict for the nonmoving party.” Id. A party seeking summary judgment has the burden of informing the district court of the basis for its motion and identifying those portions of the record that

demonstrate the absence of a genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). The moving party’s burden can be discharged either by showing an absence of evidence to support an essential element of the nonmoving party’s case or by showing that the nonmoving party will be unable to prove their

case at trial. Celotex, 477 U.S. at 325; Fitzpatrick v. City of Atlanta, 2 F.3d 1112, 1115 (11th Cir. 1993). If a movant meets its burden, the party opposing summary judgment must present evidence showing either (1) a genuine issue of material

fact or (2) that the movant is not entitled to judgment as a matter of law. Id. at 324. There is no “genuine [dispute] for trial” when the record as a whole could not lead a rational trier of fact to find for the nonmoving party. Id. Statesboro did not timely file a brief opposing Owners’ motion, but “the district court cannot base the entry of summary judgment on the mere fact that the

motion was unopposed, but, rather, must consider the merits of the motion.” United States v. One Piece of Real Prop. Located at 5800 SW 7th Ave., 363 F.3d 1099, 1101–02 (11th Cir. 2004). In particular, the court must “review all of the evidentiary

materials submitted in support of the motion for summary judgment,” and “determine if there is, indeed, no genuine issue of material fact.” Id. at 1101–02 & 1103 n.6. III. Discussion

Owners moves for summary judgment arguing that the damages Statesboro seeks to recover are not covered by the policy. Its argument is two-fold. First, it contends that the $456,874 in damages does not qualify as “property damage” under the policy at all because it reflects the faulty workmanship of Statesboro.

Second, it argues that to the extent some of the damage qualifies as “property damage,” it is nonetheless excluded under various policy exclusions. As an initial matter, the Court will not consider Statesboro’s response in

opposition to the motion. It was not timely filed and the Court finds no good cause to excuse Statesboro’s tardiness.24 Regardless, the Court must consider the merits of the motion. 5800 SW 7th Ave., 363 F.3d at 1101–02.

The dearth of evidence in this case is fatal to Owners’ motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Statesboro Erectors, Inc. v. Owners Insurance Company, (N.D. Ga. 2024).

Statesboro Erectors, Inc. v. Owners Insurance Company (Statesboro Erectors, Inc. v. Owners Insurance Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Taylor Morrison Services, Inc. v. HDI-Gerling America Insurance
746 S.E.2d 587 (Supreme Court of Georgia, 2013)
Fitzpatrick v. City of Atlanta
2 F.3d 1112 (Eleventh Circuit, 1993)