States Improvement Co. v. State of Illinois

26 Ill. Ct. Cl. 1, 1967 Ill. Ct. Cl. LEXIS 1
CourtCourt of Claims of Illinois
DecidedJanuary 10, 1967
DocketNo. 5024
StatusPublished

This text of 26 Ill. Ct. Cl. 1 (States Improvement Co. v. State of Illinois) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
States Improvement Co. v. State of Illinois, 26 Ill. Ct. Cl. 1, 1967 Ill. Ct. Cl. LEXIS 1 (Ill. Super. Ct. 1967).

Opinion

Pezman, J.

This action arises out of a contract entered into between claimant, States Improvement Company, Inc., an Illinois Corporation, and respondent, the State of Illinois, wherein claimant agreed to erect a certain steel I-beam bridge and approaches at a point approximately one quarter of a mile from the City of Decatur, County of Macon, State of Illinois.

Claimant contends that, due to the manner specified in said contract for the installation of piles, and the soil conditions existing at the time the contract was entered into, it was impossible to perform the contract, and that the State of Illinois wrongfully defaulted claimant to the damage of the sum of $320,810.59. Respondent did not file, an answer to the complaint, so a general denial of the facts, as set forth in the complaint, prevailed.

The contract, which is the subject matter of this suit, sets forth specifications to be employed for the construction of concrete piles. Piles, which were manufactured by Raymond International, Inc., met the specifications, and were the piles used. The evidence shows that these were pre-stressed concrete piles. The contract further provided for the method of installation, which method was stated to be as follows:

“(d) Installation.
The piles shall be installed in accordance with one or more of the following procedures.
“ (1.) Driving — The piles shall be driven with a steam hammer, which shall develop not less than forty thousand (40,000) foot-pounds of energy per blow at full stroke. A solid hardwood cushion block at least six (6) inches thick shall be used in the base of the hammer to cushion the blow of the hammer ram on the follower. A laminated ring-shaped cushion block, at least six (6) inches thick, made of one (1) inch hardwood boards and cut to fit the head of the pile shall be used between the follower and the top of the pile. Both cushion blocks shall be inspected periodically during driving, and no driving shall be done with blocks that have been unduly worn and compacted with use. When the point of the pile is passing through soft soil, and there is little or no resistance to penetration, the stroke of the hammer shall be reduced to approximately twenty-four (24) inches. When the point of the pile is being driven in firm ground, the full length of the stroke of the hammer shall be used to develop final resistance, but in no case shall the strokes exceed forty-two (42) inches. Piles shall be driven to the resistance determined by the Engineer.
“(e) Jetting and Driving.
In granular soils, jetting will be permitted in conjunction with driving, except that final penetration shall be attained without the use of jets. After jetting is stopped, the pile shall be driven to the elevation designated by the Engineer. Care shall be exercised during jetting that no internal hydrostatic pressure greater than twenty (20) psi does not build up within the pile. Internal jetting will not be permitted unless specifically authorized in writing by the Engineer.”

On or about April 5,1959, claimant commenced work on this project. In the month of August, 1960, claimant was ready to commence the installation of the concrete piles. From August 1 to August 15 of that year attempts were made to drive the piles to the proper elevation, but claimant was unable to do so, even though attempts were made to overdrive the piles. The contract provided that the Resident Engineer would have sole authority to determine the maximum number of hammer strokes per inch, which could be utilized in driving the piles. Despite the prior order of the Resident Engineer that driving should not proceed beyond ten blows per inch, the Resident Engineer directed that the first pile be overdriven. After the use of twenty-eight blows per inch, only one additional inch of penetration was achieved. Claimant then requested permission to use air jets in an effort to assist the driving of the piles to a lower elevation, and such jets were put into operation. With the use of the jets there was still no noticeable improvement in the driving of the piles. Work was finally halted on this project on August 19, 1960.

Subsequent to this work stoppage, claimant requested permission to excavate within the pile, and further stated that, if the new method was more expensive, he would expect additional pay. However, the request was turned down, and finally, on September 20, 1960, the Director of Public Works and Buildings of the State of Illinois sent claimant a ten day notice to comply or a default would be taken. Claimant obtained an injunction from the Circuit Court of Cook County against the Director restraining him from defaulting the contract. This injunction remained in effect until February 27, 1961, when the injunction was dissolved. The State of Illinois then readvertised the contract, and it was relet to the C. E. Burg-ett Construction Company.

The new contractor retained the services of Raymond International, Inc., as a sub-contractor to install the piles. Raymond International, Inc., then proceeded to install the piles through the use of an airlift device, which is described by claimant as a method of internal excavation, and described by respondent as a method of internal jetting.

Claimant contends that it could not deviate from the contract’s specifications without authority from the State, and that, because of the particular soil conditions encountered in driving the piles, the piles could not be installed in accordance with the specifications of the contract. Claimant further contends that respondent, the State of Illinois, subsequently allowed Raymond International, Inc., to use a form of internal excavation in installing the concrete piles. Claimant further contends that, since the State had prepared the specifications for the installation of the piles, it had a duty, when it became apparent that the contract could not be performed in accordance with such specifications, to allow claimant to use other methods of installing the piles. In addition, claimant argues that, when the State refused to change the specifications, it was excused from further performance on the grounds of impossibility.

The pertinent questions in this case are:

1. Did the State have the legal right to terminate claimant’s contract?

2. If it did not, what damages, if any, are recoverable by claimant?

The contract in this case set forth the type of piles to be installed, and further provided for the method of installation. The State of Illinois prepared the specifications, and it is clear that claimant was required to install the piles in the manner expressly set forth in the contract. This contract is known in the Industry as the “specified manner and method” contract, rather than as an “end result” contract. From the testimony in this case, it appears that this was an unusual agreement, but nevertheless it existed in this instance.

Mr. Alexander Riff was called as a witness by respondent. Mr. Riff testified that he was an employee of Raymond International, Inc., and was well acquainted with the piles to be installed, inasmuch as his company manufactured this concrete pile. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fisher v. United State Fidelity & Guaranty Co.
39 N.E.2d 67 (Appellate Court of Illinois, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
26 Ill. Ct. Cl. 1, 1967 Ill. Ct. Cl. LEXIS 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/states-improvement-co-v-state-of-illinois-ilclaimsct-1967.