Staten Island Edison Corp. v. Staten Island Rapid Transit Railway Co.

267 A.D. 152, 44 N.Y.S.2d 874, 1943 N.Y. App. Div. LEXIS 5995

This text of 267 A.D. 152 (Staten Island Edison Corp. v. Staten Island Rapid Transit Railway Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Staten Island Edison Corp. v. Staten Island Rapid Transit Railway Co., 267 A.D. 152, 44 N.Y.S.2d 874, 1943 N.Y. App. Div. LEXIS 5995 (N.Y. Ct. App. 1943).

Opinion

Callahan, J.

The question presented upon this submission of controversy is whether all or only one half of the cost of relocating certain electric transmission lines erected on defendants’ (railway companies’) rights of way is required to be met by the State of New York in connection with various grade crossing elimination proceedings.

Prior to September 4, 1940, when this dispute arose, defendants, The Staten Island Rapid Transit Railway Company and The Staten Island Railway Company (hereinafter referred to collectively as “ the railway company ”), had eliminated sixty-five grade crossings on their rights of way, and four more were in the process of elimination. The carrying out of these projects required the removal and relocation of power lines, with the supporting poles and connected wires. The power lines were owned by plaintiff (hereinafter sometimes called the electric company ”), but were used by the railway company. The cost of the work was approved, and in certain cases a final accounting was had between the railway company and the State wherein [154]*154the entire cost of relocation of the power lines was included as part of the so-called divisible cost of the elimination. With respect to those completed eliminations where no final accounting has been had, and as to those where the elimination has not been completed, the State, since September 4,1940, has refused to pay more than one half the expense of relocating those lines. This change in position by the State came about through discovery by its officers, about the date last mentioned, of the existence of a contract (hereinafter referred to in detail) which had been entered into between plaintiff and defendant, the railway company, dated May 1,1924. The date of this contract was prior to the adoption in 1925 of the first amendment to our State Constitution (art. VII, § 14) providing for the sharing by the State of the cost of eliminating railroad grade crossings.

Under statutes adopted pursuant to this constitutional amendment, the cost of such eliminations was to be shared forty-nine per cent by the State, one per cent by the city wherein the same was located, and fifty per cent by the railroád.company affected. Thereafter, by constitutional amendment effective in 1938, and by subsequent statutes, changes were made in the law so that as to all proceedings subsequent to January 1,1939, the State assumed the entire cost of elimination, including incidental improvements rendered necessary or desirable thereby. Under the new laws, there was an exception provided whereby, if benefit could be established, the railway company would be required to pay fifteen per cent of the divisible cost, but this exception is not claimed to be applicable to any of the present proceedings.

Under the agreement of May 1, 1924, above referred to, plaintiff was to construct and maintain a power line along the railway’s right of way at its own cost and expense, which was to be the source of supply for the electric energy required to operate defendant’s railroad. Plaintiff reserved the right to use the transmission lines for the purpose of supplying electricity to. other customers. There is, however, no statement in the submission that any customers, other than the railway, have ever been supplied from the line in question. Under the agreement, the railway company obtained the option to purchase the transmission line on the payment of the cost thereof, less depreciation. In case the railway company exercised this option, the electric company had the right, if it desired, to continue a line along the route for its other customers- for a period of ten years after such purchase, on paying to the railway company [155]*155half of the cost of the supporting structures and on meeting one half of the cost of maintenance. Following the foregoing provisions, the agreement states: If it becomes necessary in the opinion of the Consumer [railway company] for it to require changes in the location of said line for any reason, the Company [plaintiff] agrees to make such changes in location as may be required of it, and, in that event, the cost of making the changes in any supporting structures, or wires, shall be divided equally between the Company and the Consumer.”

It was upon learning of the existence of the above-quoted clause that the Department of Public Service of the State of New York and the Comptroller of the State of New York, on the advice of the Attorney-General, refused to pay more than half of the cost of relocating the power lines in question. It is our view that the contract referred to has no application to the relocation of transmission lines in a grade crossing elimination proceeding. This is so because the contract is expressly limited to changes required as necessary in the opinion of the railway company. In a grade crossing elimination proceeding, the changes ordered by the Department of Public Service or its predecessors were required to be effected irrespective of any opinion that the railway company might have as to the necessity therefor. The parties have stipulated that none of these lines would have been disturbed were it not for the ordering of grade crossing eliminations. Furthermore, it is clear, because of the date of its execution, that the contract mentioned was not entered into by the parties with an eye toward possible grade crossing eliminations.

The parties have stipulated, in substance, that prior to September 4, 1940, the railway company and the electric company had made it a practice to share equally that portion of the expense not paid by the State arising from relocating the power lines. Prior to the date last mentioned, the course pursued by the parties had been for the electric company to do the work of relocation at its own expense, send its bill to the railway company which, on payment of the bill, in turn billed the State for the full amount thereof. Under those proceedings, which had been initiated prior to January 1, 1939, the State, pursuant to the statutes then applicable, remitted to the railway company fifty per cent of the amount above referred to. The electric company then paid to the railway company one half of the fifty per cent which the railway company had been required to meet. The two companies by this arrangement each paid twenty-five per cent of the total cost, the State pay[156]*156ing fifty per cent thereof. After September 4, 1940, the State declined to pay more than fifty per cent of any bill for removing the transmission lines,' although the law effective at that time required it to pay, except in case of benefit to the railway company, one hundred per cent of the railway company’s expense.

We are of the opinion that the practice adopted by the two utility companies did not justify this action by the State. Why the earlier practice of sharing the cost had been followed is not revealed. There is no stipulation in the submission that it was done pursuant to any construction by the parties of the agreement above referred to. As we have said, the written contract did not require plaintiff to pay any of the cost of relocating its lines in proceedings of the present nature. Apparently the arrangement was entirely a voluntary one. We find that such voluntary arrangement would not bind the future action of the parties, and no legal advantage could be taken thereof by the State.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re the Grade Crossings of the Lehigh Valley Railroad
28 N.E.2d 409 (New York Court of Appeals, 1940)
Transit Commission v. Long Island Railroad
171 N.E. 565 (New York Court of Appeals, 1930)
In re the Proceeding, under the Grade Crossing Elimination Act
259 A.D. 141 (Appellate Division of the Supreme Court of New York, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
267 A.D. 152, 44 N.Y.S.2d 874, 1943 N.Y. App. Div. LEXIS 5995, Counsel Stack Legal Research, https://law.counselstack.com/opinion/staten-island-edison-corp-v-staten-island-rapid-transit-railway-co-nyappdiv-1943.