State v. Wright

161 N.E. 839, 89 Ind. App. 244, 1928 Ind. App. LEXIS 190
CourtIndiana Court of Appeals
DecidedJune 1, 1928
DocketNo. 12,978.
StatusPublished
Cited by4 cases

This text of 161 N.E. 839 (State v. Wright) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Wright, 161 N.E. 839, 89 Ind. App. 244, 1928 Ind. App. LEXIS 190 (Ind. Ct. App. 1928).

Opinions

Remy, C. J.

Action by appellees against appellant in the Marion Superior Court sitting as a court of claims. Material averments of the complaint, briefly stated, are, in substance: John D. Williams is the director of the State Highway Commission, and, as such, is authorized to contract on behalf of the State for the construction of state roads; that on January 2, 1924, Williams, for the State, entered into a written contract with appellees for the construction of a certain highway;that the contract, which is made a part of the complaint, provides that, in consideration of $62,423.35, appellees were to construct the highway according to the proposal and bond furnished by appellees, and according to the plans, specifications, profiles and drawings of the chief engineer of the commission, which plans, specifications, etc., are made a part of the contract by reference, payments on the consideration to be made as the work progressed, upon estimates, ten per cent- of each estimate to be retained by appellant until finál acceptance of the work and all claims had been settled; that the work to be done consisted of grading and excavating the roadway, construction of head-walls and certain concrete work; that appellee’s bid was what is known as a “unit-price bid,” and was based upon estimated quantities of the different classes of work proposed to be constructed, such as earth excavation, for which Appellees were to be paid forty-five cents per cubic yard, “special borrow,” for which they were to be paid' sixty-five cents per cubic yard, and concrete work at various prices per lineal foot according to its use. Not all of the specifica *247 tions are incorporated in the complaint. Those which are incorporated provide: (1) That the engineer may order changes in the plans, or in the character or quantity of the work, as he may find necessary, not to exceed twenty per cent of the contract price, the contractor agreeing to make the changes at the unit prices bid for the items involved; that work other than that provided for in the contract be performed by the contractor whenever, in the opinion of the engineer, such work is nécessary, the work to be done as previously agreed upon by the contractor and the engineer; but “if no such agreement can be made, or, where the method of payment is impracticable, the director may order the work to be done” on what is termed a “force» account” basis, for which work the contractor is to be paid in the following manner: For all labor and teams, “the current local rate of wage, to be agreed upon in writing before starting the work,” for the time employed, plus ten per cent; for all materials furnished, the contractor shall receive the actual cost plus ten per cent; and for any machine power, tools or equipment which it may be deemed necessary or desirable to use, the contractor to be allowed “a reasonable rental price, to be agreed upon in writing before such work is begun,” the compensation thus provided “shall be received by the contractor as payment in full for all extra work done on the ‘force account’ basis.” (2) That “whenever it is necessary to obtain additional material for construction of embankments or shoulders from outside the right of way, such material shall be known as ‘special borrow.’” (3) That “rock excavation shall include all boulders of over one cubic yard in volume and all forms of solid rock not included in earth excavation; if there is no bid price for rock excavation, and solid rock is encountered, it will be paid for at three times the unit bid price for earth excavation.” The specification defining “earth *248 excavation,” as that term is used in the contract, is not set forth in the complaint.

Following the specifications set out in the complaint, it is averred that the State, through the engineer of the Highway Commission made, in writing, many changes in the plans; that among others, they changed the center line of the road which resulted in a change in the kind and character, and increased the amount of, the materials to be excavated and the work to be done; that by reason thereof certain of the changes in the class of work required to be done were of a different classification than that originally provided for, and of such a character that a previous agreement as to the amount and method of payment was impractical; that plaintiffs, by the terms of their contract, undertook to move and place, according to the engineer’s certificate, 92,727 cubic yards of earth excavation and 2,794 cubic yards of special borrow, but that, by reason of change of plans as to location of the road, plaintiffs were required to move 157,492 cubic yards of all classes of materials, and were compelled to carry on the work throughout the winter under unfavorable weather conditions at a greatly increased expense. It is further averred that, of the materials excavated and moved, 16,496 cubic yards were excavated and moved under conditions similar to those provided for in the contract, plans and specifications for earth excavation, and, at forty-five cents per cubic yard, would come to $8,229.15; that, of the additional work of excavating, 30,297 cubic yards were hauled over long distances when the ground was frozen, for which the cost, plus ten per cent, was seventy-five cents per cubic yard, or $22,722.75, the reasonable value of the services rendered; that, of this excess, 4,089 cubic yards had to be moved down from the top of a hill when the ground was frozen; that the cost and reasonable value of this work, plus ten per cent, was $1 per cubic yard; that, of the *249 extra, excavation, 9,825 cubic yards were rock, of which 6,245 cubic yards were moved under conditions similar to those provided for by the contract, specifications, the cost and reasonable value of which work, plus ten per cent, was $8,430.75; that the remainder of the rock, to wit, 3,578 cubic yards, was moved under different conditions, the expense of which was $3 per yard, or $10,734, which is a reasonable price for the work; that, during the progress of the work, appellees were paid on estimates the total sum of $77,335.06, leaving a balance due plaintiffs in the sum of $50,252.69. Then follow allegations of the estimates made from time to time and the amounts-paid on each. These averments need not be set out here, except that one in which it is averred that the estimate covering the period from April 10, 1925, to October 10, 1925, as to which appellant made a reclassification, in which all rock excavation, that had been figured at $1.35 per yard, was changed to “earth excavation,” and figured at the contract unit price of forty-five cents per cubic yard, and the earth excavation which had been calculated at forty-five cents per yard was changed to “special borrow” at sixty-five cents per cubic yard, thereby increasing the “special borrow” to $5,995, and eliminating all rock excavation. It is also averred that, according to the last statement and estimate of the Highway Commission, the Commissionconceded, and now concedes, that the balance due appellees was $5,996.56, and issued to appellees a certificate for that sum in full settlement, which certificate appellees refused to accept in full settlement. It is averred that the total balance due plaintiffs, including interest, is $52,589.06, judgment for which amount is demanded.

. A demurrer to the complaint for want of facts, and a motion to require plaintiffs to make their amended complaint more specific, having each been overruled, appellant answered by denial, and filed a counterclaim in two

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Love v. State
272 N.E.2d 456 (Indiana Supreme Court, 1971)
Wertzberger, Admr., Etc. v. Herd
140 N.E.2d 771 (Indiana Court of Appeals, 1957)
Patterson v. City of Gary
190 N.E. 320 (Indiana Court of Appeals, 1934)
State of Indiana v. Wright
175 N.E. 666 (Indiana Court of Appeals, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
161 N.E. 839, 89 Ind. App. 244, 1928 Ind. App. LEXIS 190, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-wright-indctapp-1928.