This text of 167 N.E. 127 (State v. Terre Haute, Indianapolis & Eastern Traction Co.) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Terre Haute, Indianapolis & Eastern Traction Co., 167 N.E. 127, 201 Ind. 346, 1929 Ind. LEXIS 48 (Ind. 1929).

Opinion

Travis, J.

This is an action by the State of Indiana against appellee electric interurban railroad company to recover the cost of improving that portion of a highway occupied by its tracks, including the space between the rails, the space between the tracks, where there were two tracks, and the space 18 inches in. width on the outside of the rails. Acts 1919, ch. 53, p. 119, §8268 et seq. Burns 1926. The highway is known as the *348 “National Road” and has been designated as “State Road No. 3.” It extends across the central part of the state, through Terre Haute, Indianapolis, Richmond and other cities and towns. This highway had been designated as a state highway by the State Highway Commission, which official designation had been approved by the Governor. The specific part of the highway occupied by appellee’s tracks began at the east corporate boundary of the city of Richmond and extended east on the highway a distance of 6,654 feet.

The State appealed from the judgment against it because it failed to plead after appellee’s demurrer to appellant’s complaint had been sustained. §368 Burns 1926. Appellant’s complaint is in two paragraphs. The first paragraph alleges that the State has under its control, through the State Highway Commission, State Road No. 3, extending from the Illinois state line near Terre Haute, through Indianapolis, to the Ohio state line, east of Richmond; that the highway east of Richmond for 6,654 feet is occupied by appellee’s tracks; that the commission, in April, 1923, undertook to pave the highway at that point, including that part occupied by the tracks; that appellee did not at any time elect to improve the part so occupied, but expressly refused to construct it; that the commission thereupon made the improvement, using the same materials and the same form of construction, at the same unit prices, as used and paid for the improvement outside the tracks, all of which is shown in the itemized bill of particulars attached to'the complaint; that appellee failed and refused to pay for the improvement so made upon its tracks, which amount is due; that the commission filed a lien therefor in the recorder’s office of Wayne County; that the principal sum, interest and attorney’s fees amount to $11,000, for which the complaint asks judgment and the foreclosure of the lien, etc.

*349 The second paragraph of complaint is like the first paragraph. Briefly stated, the paragraphs differ in this: The second paragraph sets out by exhibits the action of the highway commission in taking over State Road No. 3, and alleges that the defendant company not only failed to construct or to pay for the construction of that part of the highway occupied by its tracks, etc., but also, that it expressly refused to pay or to construct, arid denied any liability therefor; that the highway was in a bad state of repair and was disintegrated; that it was impracticable to move the tracks from the traveled way and that it would have been impracticable not to improve the portion of the highway occupied by defendant’s tracks, for the reason that the improvement required the raising of the road bed and tracks, which fact defendant knew and consented to; that, in so raising the tracks and road bed, the surface was further destroyed and broken up, and to leave the highway and road bed in that condition would have been impracticable, inconvenient, and a source of danger to the traveling public using the highway.

Appellee’s separate demurrers to each paragraph of complaint are based upon insufficient facts alleged in either paragraph to constitute a cause of action. The question for decision depends upon the construction of §26 of the act, ch. 53, supra. All facts necessary to constitute a cause of action, as pleaded in each paragraph of the complaint, are admitted by appellee, except that, to plead a cause of action by each paragraph of complaint, it is necessary to allege: That appellee had, not less than 20 days prior to the date on which the contract for the improvement of such highway was let, filed written notice with the State Highway Commission of its election to pay for the improvement of the portion of the highway occupied by its tracks as done by the highway commission; and to also allege: That, although *350 appellee had elected to pay for such improvement as done by said State Highway Commission, it has failed and refused to pay therefor.

Appellee’s proposition is that both the first and second paragraphs of complaint are based upon the theory that §26 of ch. 53 of the acts of 1919, supra, gave appellant the right, by the facts pleaded, to have and enforce a lien against the property of appellee company by reason of the improvement by appellant of that portion of the highway occupied by the tracks of appellee company, and for a distance of 18 inches on either side thereof, and observes that the first portion of §26 creates the obligation upon all electric interurban railroad companies whose tracks occupy any part of any highway which is ordered improved and maintained by the State Highway Commission, to improve and maintain, or to pay for the cost of improving, that portion thereof occupied by its tracks. Appellee obviates the obligation and liability cast upon it for the sole reason that it did not choose to elect, as provided by §26, supra, to pay for the improvement of the highway occupied by it, as done by the State Highway Commission, and concludes that the lien mentioned in §26, supra, can attach only in the event that such company (appellee) shall elect to pay for such improvement as done by the State Highway Commission.

Appellee concedes that the statute (§26, supra) casts the general obligation upon it to improve and maintain, or pay the cost of improving, that portion of the highway occupied by its tracks which has been ordered improved and maintained by the State Highway Commission; but contends that the general obligation depends upon the election provided by the law, viz., if such company shall elect to improve, it shall be done in the manner prescribed; if such company shall elect to pay for the improvement as done by the State High *351 way Commission, the cost thereof may be collected as a lien against the property, and the lien intended in the statute can attach only in- the event the company shall elect to pay for such improvement as done by said State Highway Commission. And because neither paragraph of the complaint alleges as a fact that the appellee company did, within the time specified by the law, file written notice with the State Highway Commission that it would elect to pay for the improvement as done by the commission, but, on the contrary, each paragraph of complaint alleged that appellee company did not at any time elect, etc., each paragraph of complaint fails to state a cause of action. The opinion of the court is in harmony with the assertion of appellee that the law casts a general obligation upon appellee to improve or pay for the improvement of the highway as ordered. The court goes further, and interprets the law to cast an absolute obligation upon appellee company to improve and maintain, or pay for the cost of improving, that portion of the highway occupied by its tracks, etc., when the improvement is ordered according to law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Indiana Railroad
2 N.E.2d 404 (Indiana Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
167 N.E. 127, 201 Ind. 346, 1929 Ind. LEXIS 48, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-terre-haute-indianapolis-eastern-traction-co-ind-1929.