State v. Suchor

953 N.W.2d 678, 2021 S.D. 2
South Dakota Supreme Court·Decided January 6, 2021·No. 28993·Published

Opinion

#28993-r-PJD 2021 S.D. 2

IN THE SUPREME COURT

OF THE

STATE OF SOUTH DAKOTA

****

STATE OF SOUTH DAKOTA, Plaintiff and Appellee, v.

ROBERT SUCHOR, Defendant and Appellant.

****

APPEAL FROM THE CIRCUIT COURT OF THE FOURTH JUDICIAL CIRCUIT LAWRENCE COUNTY, SOUTH DAKOTA

****

THE HONORABLE MICHELLE K. COMER Judge

****

JASON R. RAVNSBORG Attorney General

MATTHEW W. TEMPLAR Assistant Attorney General Pierre, South Dakota Attorneys for plaintiff and appellee.

PAUL J. ANDREWS Rapid City, South Dakota Attorney for defendant and appellant.

****

CONSIDERED ON BRIEFS

MAY 26, 2020

OPINION FILED 01/06/21

DEVANEY, Justice [¶1.] Robert Suchor appeals the jury’s verdict finding him guilty of three counts of grand theft by misappropriation of funds by a contractor. He asserts that the State failed to present sufficient evidence on one or more essential elements, and therefore, the circuit court erred in denying his motion for judgment of acquittal on each conviction. We reverse all three convictions.

Factual and Procedural Background [¶2.] Robert Suchor is a contractor from Pine Haven, Wyoming. He owned and operated New Wave Builders, and as discussed below, in 2016, he entered into three separate contracts to construct homes for three families in Spearfish, South Dakota. The Dahl Project [¶3.] In April 2016, Carole and Dennis Dahl met Suchor through their realtor, Sandy Donahue. After multiple meetings, the Dahls and Suchor executed a contract on November 30, 2016, for Suchor to build the Dahls’ home for $250,000. The contract provided that the Dahls were to pay Suchor $25,000 upon signing the contract. The contract further provided that Suchor would finish the concrete foundation and interior flatwork within 30 days after receiving the first contract payment. [¶4.] The Dahls paid Suchor $25,000 on December 1, 2016. However, construction on the home did not begin as planned, 1 and after the Dahls learned

1. According to Suchor, he could not begin digging for the foundation because the ground was frozen. The contract provided for delays due to extreme (continued . . .)

that Suchor had yet to obtain a building permit, the Dahls terminated their contract with Suchor on December 16. They requested he return the $25,000, but Suchor refused, indicating he had spent approximately 104 hours on the project (arguably worth $10,400) and had purchased Styrofoam foundation forms. Ultimately, the Dahls filed a civil suit against Suchor, which was stayed pending the resolution of this criminal proceeding. The Pavich Project [¶5.] Frank and Kit Pavich wanted to build and thereafter sell for profit what they called a “spec-house.” Sandy Donahue also introduced the Paviches to Suchor, and on July 13, 2016, the parties executed a contract whereby Suchor would build the spec-house for $332,000. Under the contract, Suchor was to be issued progress payments, and the disbursements to Suchor were to be processed through Black Hills Land and Title. Shortly after Suchor began work on the project, the Paviches decided to make the spec-house their personal residence. As a result, multiple changes were made to the construction plans. Rather than execute a new contract, the parties agreed that the Paviches would pay for any upgrades or extras. [¶6.] It is undisputed that over the course of the project, Suchor and Frank Pavich’s relationship deteriorated. Eventually the parties could no longer work together, and on May 27, 2017, before the project was finished, Suchor stopped

(. . . continued)

weather and required the contractor to notify the owner of such. Suchor sent Carole Dahl a text message on December 12, 2016, explaining he could not “open a hole” until the weather breaks, and indicating that he “hoped” he would be able to do so “around the holidays.” Carole responded, “We understand” and “thanks for checking in.”

working on it. By that time, according to Pavich, he had paid Suchor $329,000 of the $332,000 contract price and had also spent $99,000 on the change orders and upgrades. The record is not clear as to how much of this $99,000 was initially expended by Suchor and then reimbursed by Pavich, or whether some of these expenses were paid directly by Pavich after Suchor stopped working on the project. [¶7.] Pavich testified that after Suchor left the job, he learned that Suchor had not paid an invoice from Wires R Us for $16,681.66 for electrical work done on the project. Suchor maintained that he did not pay this bill because Pavich still owed him money on the project, and also because he had reached an agreement with Pavich when they parted ways as to how the remaining bills would be handled. Ultimately, Pavich paid Wires R Us $20,852.07 in December 2017, which, according to Pavich, was the total amount due after all the electrical work on the contract had been finished. The Feeser Project [¶8.] On July 29, 2016, Justin and Kristen Feeser entered into a contract with Suchor for the construction of a home for $385,000. The contract required that the home be constructed by the end of November 2016. The evidence presented at trial revealed that Suchor’s work on this project was fraught with issues. 2 Feeser

2. For example, Suchor did not start construction on the Feeser project until September 2016 because he was busy with other jobs. When he did start and poured the concrete footings, his work did not pass City inspection due to the discovery of excess backfill on the lot that was not suitable for a foundation.

In order to remedy the problem, Suchor had to remove the footings, excavate down to the native soil, and repour the concrete. This set the project timeframe back three months, and according to Suchor, he personally spent (continued . . .)

eventually became so frustrated with Suchor’s work that in July 2017, Feeser offered to sell Suchor the unfinished house. Suchor agreed; however, he could not obtain financing. The Feesers then agreed, at Suchor’s suggestion, to sell the house to Suchor’s brother. Before the scheduled closing, Feeser learned that an outstanding balance was owed to J&M Drywall for $13,184. Feeser asked Suchor about this bill on August 9, 2017, the day before the scheduled closing, and according to Feeser, Suchor confirmed that J&M Drywall had been paid in full. [¶9.] Suchor later explained that he had planned to pay J&M Drywall the amount due with funds Feeser had agreed to pay him at closing. Based on this understanding, Suchor had given J&M Drywall a check that same day (August 9) for the balance due, but after the closing did not occur as planned, Suchor’s check bounced. Ultimately, the sale fell through, and Feeser fired Suchor on August 19, 2017. According to Feeser, he had paid Suchor $330,000 of the $385,000 due under the contract. Feeser later learned that the check Suchor issued to J&M Drywall had bounced, and on September 29, 2017, Feeser paid J&M Drywall the outstanding invoice balance. Feeser then brought a civil suit against Suchor, which at the time of the criminal trial, was in arbitration. The Criminal Case [¶10.] Meanwhile, on July 11, 2017, Frank Pavich filed a complaint with the Spearfish Police Department, claiming that he gave Suchor money to pay Wires R Us but Suchor did not remit payment. During the investigation, Detective Jason De

(. . . continued)

an additional $40,000 to remedy the problem. The concrete work was not finished until January 2017.

Free access — add to your briefcase to read the full text and ask questions with AI

State v. Suchor, 953 N.W.2d 678, 2021 S.D. 2 (S.D. 2021).

953 N.W.2d 678 (State v. Suchor) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. Jensen
2007 SD 76 (South Dakota Supreme Court, 2007)
State v. Morse
2008 SD 66 (South Dakota Supreme Court, 2008)
State v. Jackson
2009 SD 29 (South Dakota Supreme Court, 2009)
State v. Brim
2010 S.D. 74 (South Dakota Supreme Court, 2010)
Bertelsen v. Allstate Insurance Co.
2013 S.D. 44 (South Dakota Supreme Court, 2013)
State v. Pierson
86 A.2d 559 (Superior Court of Delaware, 1952)
State v. Brende
2013 SD 56 (South Dakota Supreme Court, 2013)
State v. Martin
2015 SD 2 (South Dakota Supreme Court, 2015)
Commercial National Bank v. Smith
244 N.W. 521 (South Dakota Supreme Court, 1932)
State v. Ware
942 N.W.2d 269 (South Dakota Supreme Court, 2020)