State v. Suchor

953 N.W.2d 678, 2021 S.D. 2
CourtSouth Dakota Supreme Court
DecidedJanuary 6, 2021
Docket28993
StatusPublished

This text of 953 N.W.2d 678 (State v. Suchor) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Suchor, 953 N.W.2d 678, 2021 S.D. 2 (S.D. 2021).

Opinion

#28993-r-PJD 2021 S.D. 2

IN THE SUPREME COURT OF THE STATE OF SOUTH DAKOTA

****

STATE OF SOUTH DAKOTA, Plaintiff and Appellee,

v.

ROBERT SUCHOR, Defendant and Appellant.

APPEAL FROM THE CIRCUIT COURT OF THE FOURTH JUDICIAL CIRCUIT LAWRENCE COUNTY, SOUTH DAKOTA

THE HONORABLE MICHELLE K. COMER Judge

JASON R. RAVNSBORG Attorney General

MATTHEW W. TEMPLAR Assistant Attorney General Pierre, South Dakota Attorneys for plaintiff and appellee.

PAUL J. ANDREWS Rapid City, South Dakota Attorney for defendant and appellant.

CONSIDERED ON BRIEFS MAY 26, 2020 OPINION FILED 01/06/21 #28993

DEVANEY, Justice

[¶1.] Robert Suchor appeals the jury’s verdict finding him guilty of three

counts of grand theft by misappropriation of funds by a contractor. He asserts that

the State failed to present sufficient evidence on one or more essential elements,

and therefore, the circuit court erred in denying his motion for judgment of

acquittal on each conviction. We reverse all three convictions.

Factual and Procedural Background

[¶2.] Robert Suchor is a contractor from Pine Haven, Wyoming. He owned

and operated New Wave Builders, and as discussed below, in 2016, he entered into

three separate contracts to construct homes for three families in Spearfish, South

Dakota.

The Dahl Project

[¶3.] In April 2016, Carole and Dennis Dahl met Suchor through their

realtor, Sandy Donahue. After multiple meetings, the Dahls and Suchor executed a

contract on November 30, 2016, for Suchor to build the Dahls’ home for $250,000.

The contract provided that the Dahls were to pay Suchor $25,000 upon signing the

contract. The contract further provided that Suchor would finish the concrete

foundation and interior flatwork within 30 days after receiving the first contract

payment.

[¶4.] The Dahls paid Suchor $25,000 on December 1, 2016. However,

construction on the home did not begin as planned, 1 and after the Dahls learned

1. According to Suchor, he could not begin digging for the foundation because the ground was frozen. The contract provided for delays due to extreme (continued . . .) -1- #28993

that Suchor had yet to obtain a building permit, the Dahls terminated their contract

with Suchor on December 16. They requested he return the $25,000, but Suchor

refused, indicating he had spent approximately 104 hours on the project (arguably

worth $10,400) and had purchased Styrofoam foundation forms. Ultimately, the

Dahls filed a civil suit against Suchor, which was stayed pending the resolution of

this criminal proceeding.

The Pavich Project

[¶5.] Frank and Kit Pavich wanted to build and thereafter sell for profit

what they called a “spec-house.” Sandy Donahue also introduced the Paviches to

Suchor, and on July 13, 2016, the parties executed a contract whereby Suchor would

build the spec-house for $332,000. Under the contract, Suchor was to be issued

progress payments, and the disbursements to Suchor were to be processed through

Black Hills Land and Title. Shortly after Suchor began work on the project, the

Paviches decided to make the spec-house their personal residence. As a result,

multiple changes were made to the construction plans. Rather than execute a new

contract, the parties agreed that the Paviches would pay for any upgrades or extras.

[¶6.] It is undisputed that over the course of the project, Suchor and Frank

Pavich’s relationship deteriorated. Eventually the parties could no longer work

together, and on May 27, 2017, before the project was finished, Suchor stopped

________________________ (. . . continued) weather and required the contractor to notify the owner of such. Suchor sent Carole Dahl a text message on December 12, 2016, explaining he could not “open a hole” until the weather breaks, and indicating that he “hoped” he would be able to do so “around the holidays.” Carole responded, “We understand” and “thanks for checking in.”

-2- #28993

working on it. By that time, according to Pavich, he had paid Suchor $329,000 of

the $332,000 contract price and had also spent $99,000 on the change orders and

upgrades. The record is not clear as to how much of this $99,000 was initially

expended by Suchor and then reimbursed by Pavich, or whether some of these

expenses were paid directly by Pavich after Suchor stopped working on the project.

[¶7.] Pavich testified that after Suchor left the job, he learned that Suchor

had not paid an invoice from Wires R Us for $16,681.66 for electrical work done on

the project. Suchor maintained that he did not pay this bill because Pavich still

owed him money on the project, and also because he had reached an agreement

with Pavich when they parted ways as to how the remaining bills would be handled.

Ultimately, Pavich paid Wires R Us $20,852.07 in December 2017, which, according

to Pavich, was the total amount due after all the electrical work on the contract had

been finished.

The Feeser Project

[¶8.] On July 29, 2016, Justin and Kristen Feeser entered into a contract

with Suchor for the construction of a home for $385,000. The contract required that

the home be constructed by the end of November 2016. The evidence presented at

trial revealed that Suchor’s work on this project was fraught with issues. 2 Feeser

2. For example, Suchor did not start construction on the Feeser project until September 2016 because he was busy with other jobs. When he did start and poured the concrete footings, his work did not pass City inspection due to the discovery of excess backfill on the lot that was not suitable for a foundation. In order to remedy the problem, Suchor had to remove the footings, excavate down to the native soil, and repour the concrete. This set the project timeframe back three months, and according to Suchor, he personally spent (continued . . .) -3- #28993

eventually became so frustrated with Suchor’s work that in July 2017, Feeser

offered to sell Suchor the unfinished house. Suchor agreed; however, he could not

obtain financing. The Feesers then agreed, at Suchor’s suggestion, to sell the house

to Suchor’s brother. Before the scheduled closing, Feeser learned that an

outstanding balance was owed to J&M Drywall for $13,184. Feeser asked Suchor

about this bill on August 9, 2017, the day before the scheduled closing, and

according to Feeser, Suchor confirmed that J&M Drywall had been paid in full.

[¶9.] Suchor later explained that he had planned to pay J&M Drywall the

amount due with funds Feeser had agreed to pay him at closing. Based on this

understanding, Suchor had given J&M Drywall a check that same day (August 9)

for the balance due, but after the closing did not occur as planned, Suchor’s check

bounced. Ultimately, the sale fell through, and Feeser fired Suchor on August 19,

2017. According to Feeser, he had paid Suchor $330,000 of the $385,000 due under

the contract. Feeser later learned that the check Suchor issued to J&M Drywall

had bounced, and on September 29, 2017, Feeser paid J&M Drywall the

outstanding invoice balance. Feeser then brought a civil suit against Suchor, which

at the time of the criminal trial, was in arbitration.

The Criminal Case

[¶10.] Meanwhile, on July 11, 2017, Frank Pavich filed a complaint with the

Spearfish Police Department, claiming that he gave Suchor money to pay Wires R

Us but Suchor did not remit payment. During the investigation, Detective Jason De

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Jensen
2007 SD 76 (South Dakota Supreme Court, 2007)
State v. Morse
2008 SD 66 (South Dakota Supreme Court, 2008)
State v. Jackson
2009 SD 29 (South Dakota Supreme Court, 2009)
State v. Brim
2010 S.D. 74 (South Dakota Supreme Court, 2010)
Bertelsen v. Allstate Insurance Co.
2013 S.D. 44 (South Dakota Supreme Court, 2013)
State v. Pierson
86 A.2d 559 (Superior Court of Delaware, 1952)
State v. Brende
2013 SD 56 (South Dakota Supreme Court, 2013)
State v. Martin
2015 SD 2 (South Dakota Supreme Court, 2015)
Commercial National Bank v. Smith
244 N.W. 521 (South Dakota Supreme Court, 1932)
State v. Ware
942 N.W.2d 269 (South Dakota Supreme Court, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
953 N.W.2d 678, 2021 S.D. 2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-suchor-sd-2021.