State v. Sjv Electric

CourtSuperior Court of Rhode Island
DecidedMay 15, 2008
DocketP.B. No. 01-1932
StatusPublished

This text of State v. Sjv Electric (State v. Sjv Electric) is published on Counsel Stack Legal Research, covering Superior Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Sjv Electric, (R.I. Ct. App. 2008).

Opinion

DECISION
This Court conducted a bench trial with respect to multiple claims for damages and breach arising out of a contract for electrical work at the Port of Galilee, Narragansett, Rhode Island. The State of Rhode Island ("State"), through its verified complaint, brings this action for breach of contract, negligence, breach of warranty for fitness of a particular purpose, and breach of performance bond against co-defendants, SJV Electric, Inc. ("SJV") and National Grange Mutual Insurance Co. ("National Grange"). Defendants raise a number of affirmative defenses and counterclaims, including breach of contract and negligence. During trial, SJV and National Grange moved for judgment as a matter of law pursuant to Super. R. Civ. P. 52(c), which motion is addressed in this decision.

I
Facts Travel
During trial, the Court heard testimony from a number of witnesses and received into evidence a number of exhibits including documents and sample electrical cables. The Court finds the following facts by a preponderance of the credible evidence presented at trial. The *Page 2 contractual relationship between SJV and the State, around which the matter at bar is centered, began with an October 1998 Bid Solicitation by the State for the Port of Galilee Electrical Renovation Project ("Project"). SJV submitted a timely bid and ultimately was determined to be the lowest bidder. (Verified Compl. ¶ 6.) (Compl.) SJV subsequently procured and presented the State with its surety bond, in which co-defendant National Grange agreed to serve as surety. (Ex. 6.) The contract as agreed upon by the parties called for the State to make partial payments periodically throughout the progression of the Project. (Ex. 7; Ex. 1, art. 5.)

The Project was initiated for the purpose of renovating wiring and electrical lines previously installed in the docks at Galilee, in Narragansett, Rhode Island. The individual docks, primarily used for egress and ingress of commercial fishing boats, are powered predominantly by ampere feeder cables which draw power from the two main distribution panels. The distribution panels serve as the main power hubs for the entire electrical system for docks in the Port.

SJV's contract with the State called for the installation of 200 ampere feeder cables. It is undisputed that in April of 1999 employees of SJV used a backhoe to attempt to pull the feeder cables through conduit already placed in the ground by SJV. (Ricci Test.) Specifically, the plans contemplated the use of one-inch PVC conduit to be laid in the ground. The PVC would ultimately serve as raceways to facilitate an expedited installation of the replacement cables, which proved to have a longer than expected lead time from the supplier used by SJV. The State's plans and specifications for the Project, which were developed and drawn by Powers Engineering, Inc. ("Powers"), called for the use of bronzed sheath Okonite cable. (Ex. 1.)

As a result of the delay in obtaining the Okonite cable, a series of letters and faxes were exchanged between the parties involved in the Project. SJV repeatedly expressed its concerns regarding the National Electric Code ("NEC") fill requirements once SJV was made aware of the *Page 3 dimensions of the raceways and the Okonite cable.1 The State, however, insisted throughout the course of its relationship with SJV that their engineers had determined that the original plans were not violative of the NEC fill requirements. Ultimately, the State and SJV were unable to resolve their issues surrounding the Project which prompted the State to terminate its contract with SJV. Thereafter, the Project was re-bid and ultimately awarded to K-Electric, which had been an unsuccessful bidder on the Project in the fall of 1998. Mr. Kirk, the principal of K-Electric, testified that K-Electric was given the option to use or discard any of the work already done on the Project by its predecessor, SJV. To avoid any potential liability on work that was not their own, K-Electric opted to replace the cables installed by SJV costing the State an additional $20,000. The State also contracted with Powers once again to develop Addenda No. 2, which altered the original plan specifications. (Trial Ex. 10.) Addenda No. 2 instructed the replacement contractor, K-Electric, to employ a direct burial method2 when laying the Okonite cable, rather than use the PVC conduit raceways previously laid by SJV. (Trial Ex. 10.)

Subsequent to K-Electric's take-over of the Project, National Grange Insurance Company ("National Grange"), a co-defendant in this litigation, in its capacity as surety under the SJV Performance Bond, requested that Megger Testing3 be performed at the project site. The tests were performed in October of 2000. PI Associates, agents of National Grange, hired James J. *Page 4 O'Rourke, Inc. ("O'Rourke") to conduct the testing. The tests were subsequently performed by Joe Walsh, Jr. of O'Rourke, who testified to the results of the testing at trial. As will be discussed in greater detail below, 11 wires failed the Megger Testing. (Trial Ex. 34.)

At the request of the Court, the State, following trial, filed proposed findings of fact and conclusions of law in addition to their written closing arguments. SJV has also filed its written closing argument. The Court notes that the facts presented and proposed in the various filings appear to mirror each other and are generally undisputed. Finally, the above-stated introductory facts will be supplemented with additional, specific findings of fact as they relate to the Court's decision herein.

II
Standard of Review
The court decides non-jury trials pursuant to its power under Super. R. Civ. P. Rule 52. The R.I. Rules of Civil Procedure provide that "in all actions tried upon the facts without a jury or without an advisory jury, the court shall find the facts specially and state separately its conclusions of law thereon." Super. R. Civ. P. Rule 52. Under Rule 52, the Court sits not only as trier of law, but also as trier of fact.See Hood v. Hawkins, 478 A.2d 181, 184 (R.I. 1984). When sitting as the trier of facts, the trial justice determines the credibility of witnesses and ultimately may draw proper inferences from the evidence. (See Id.) Finally, an extensive analysis and discussion of the evidence and testimony is not required to comport with the mandates of Rule 52. (Id.) *Page 5

III
The Written Agreements
The rights and obligations of the parties are governed by two primary documents: (1) the Construction Contract ("Contract") and the conditions thereto4, which consists of both AIA Document A101-1997 and AIA Document A201-199, and (2) the Performance Bond. The form of each of these documents was provided to SJV as Part of the Project manual.

A. The Contract and Conditions

The controversy among the parties centers primarily on the State's termination of the Contract with SJV.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hood v. Hawkins
478 A.2d 181 (Supreme Court of Rhode Island, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
State v. Sjv Electric, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-sjv-electric-risuperct-2008.