State v. Paskewitz

47 N.W.2d 199, 233 Minn. 452, 1951 Minn. LEXIS 659
CourtSupreme Court of Minnesota
DecidedMarch 30, 1951
DocketNo. 35,291
StatusPublished
Cited by10 cases

This text of 47 N.W.2d 199 (State v. Paskewitz) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Paskewitz, 47 N.W.2d 199, 233 Minn. 452, 1951 Minn. LEXIS 659 (Mich. 1951).

Opinion

Frank T. Gallagher, Justice.

The state of Minnesota brought this action against Alfred A. Paskewitz, a common carrier for hire, Badger Machine Company, the owner of a trench digger, and Henry Niemeyer, an employe of the machine company, to recover for damage to a bridge on trunk highway No. 19 near Henderson, Minnesota. The common carrier is alleged to have accepted the trench digger for shipment via his truck from a farm near Faribault, Minnesota, to Belview, Minnesota. The digger never arrived at its destination, but was wrecked as a result of an entanglement with the bridge near Henderson, causing considerable damage to the bridge. The jury returned a verdict for the state against all the defendants. Niemeyer and the machine company have appealed from an order denying their motion for judgment notwithstanding the verdict or for a new trial. Paskewitz has not appealed, although he has appeared, urging that the verdict of the jury be allowed to stand. The sole question is whether the state has a right to recover against all the defendants.

Paskewitz owned a 1%-ton Dodge truck. It was the cab-over-engine type, with an ordinary stock rack about 16 feet long, the [454]*454wheel base' of the truck being about 160 inches. On the steel frame of the truck were wood stringers which extended 4 or 5 feet beyond the steel frame. The height of the platform truck was 3 feet 8 inches from the ground. The rack floor was constructed of wood, and there were no planks on the rack when the machine was driven onto it. The truck rack was about 8 feet wide.

The trench digger operated on tracks and weighed about 7,600 pounds. The over-all length of the machine, including the boom extended out, was approximately 31 feet, the width 7% feet, and the length of the boom about 15 feet. The intricacies of the construction of the machine are not important here. Mounted to the machine by heavy brackets on each side is the boom, over and under which shovels mounted on a chain driven by a heavy-duty chain operate by means of a combination of sprockets and gears. Above the boom was a sight, which, looking from the top thereof, is described by the designer as being “rectangular, forty to forty-eight inches long, and thirty to thirty-two inches wide, and looking from a side elevation or the side view it would be a sort of a wedge shape approximately on one and coming to a point on the other end.” When the boom was raised to its most extreme height, the top part of the sight was approximately 11 feet from the ground. The only portion of the machine which could reach a height of over 12 feet was the sight. The boom itself could not be raised higher than the hood of the trench digger without raising the machine itself and the hood over it.

Paskewitz drove to the farm near Faribault, where the machine had been in operation. It was there that he saw the digger for the first time. Niemeyer was sent by the machine company for the specific purpose of loading the machine onto the truck. The loading was accomplished by Paskewitz backing the truck up to a road approach and Niemeyer then backing the machine onto the truck bed. Prior to the loading, Paskewitz had observed Niemeyer raise the boom in order to clean the shovels. He saw the machine as it was being driven on its own track over to where his truck was parked. To load the machine, it was necessary to raise the boom [455]*455in order to get the boom over the cab of the truck. When the machine was resting on the bed of the truck, the boom was again lowered so that it sloped downward slightly, and the highest part of the boom itself was lower than the top of the hood of the machine. The sight extended above the boom. Niemeyer climbed up on the machine and, with the aid of a wrench, loosened two bolts and lowered the sight onto the boom so that it was parallel with the boom and below the top of the hood of the machine, whereupon he retightened the bolts. There was a clearance of about 5 or 6 inches between the lower part of the boom and the roof of the truck cab. The boom extended over the front of the truck cab and rode in a straight line across the center of the cab. The boom could be seen by Paskewitz from where he sat in the cab of the truck. The top of the hood of the trench digger was the highest part of the load, and the height of the machine was 8 feet. Since the height of the bed of the truck was 3 feet 8 inches, this would make a total height of 11 feet 8 inches. Niemeyer testified that the boom could go up and down but not sideways. The boom was not fastened in any way. It was allowed to rest on the cables, but the winch to which the cables were attached was locked. Niemeyer then locked the transmission and engaged the four transmissions. At the front end of the digger and extending about a foot to a foot and a half over the end of the tru'ck was a motor or engine. The center of weight of the digger was slightly forward of the rear axle of the truck, or 10% to 11 feet from the motor end of the digger.

Niemeyer testified that he had loaded a number of diggers before without removing the sight or boom, although it is admitted that the boom could have been removed for transportation purposes. Other than locking the transmission and putting the transmissions into gear, there was nothing else done to prevent the machine from moving on the bed of the truck. The designer testified that the machine could not move while the transmission was in super-low and that the sight could go up and down if the brackets securing it were loose. The designer of the machine, testifying on his own behalf on cross-examination, said that he could not see how the [456]*456nuts securing the sight to the boom could become loosened, either by vibration or by action of the truck. Paskewitz testified that he had nothing to do with the loading other than to tie a rope across the back end of the side racks in order to keep them from swaying, because there was no end gate.

Paskewitz proceeded uneventfully with his load after leaving the farm near Faribault. He made one stop at Montgomery, where he checked his tires and observed that the machine seemed to be in the same position as when loaded. At the outskirts of Faribault he passed through a railroad underpass without any mishap. During the course of his trip, he observed that the machine seemed to be maintaining its position on the truck and that there was no unusual swaying. He testified that he maintained a speed of about 85 miles an hour on the trip. Coming toward Henderson, about 45 miles from Faribault, he drove down a long, steep hill, where the road also curves. The road levels off at the bottom of the hill, and the east approach to the bridge is on this level. Paskewitz testified that he traveled down the grade at about 25 miles an hour and that the road was level for about half a mile before reaching the bridge, but that there was a slight curve about 200 feet from the east approach to the bridge. The highway patrolman who investigated the accident testified that Paskewitz told him that his normal speed up to the time of the accident was 35 miles per hour. The road is divided from the bridge by a slight rise or bump, according to Paskewitz, who testified that he felt the wheels of his truck go over this rise, the front wheels first and then the rear, and that the truck rocked from that bump. We quote his testimony:

“Q. It was smooth up to the time you hit that. Then what happened when you hit this approach to this bridge?
“A. Well, the truck rocked from that bump.
“Q. It rocked some. Well, how did it rock?
“A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. HEDGES MOTOR COMPANY
164 N.W.2d 364 (Supreme Court of Minnesota, 1969)
Johnson v. Lorraine Park Apts. Inc.
128 N.W.2d 758 (Supreme Court of Minnesota, 1964)
Jones v. Harris
224 F. Supp. 630 (D. Minnesota, 1963)
Frank Altrichter v. Shell Oil Company, a Corporation
263 F.2d 377 (Eighth Circuit, 1959)
Altrichter v. Shell Oil Co.
170 F. Supp. 851 (D. Minnesota, 1957)
Best v. Fedo
153 F. Supp. 79 (D. Minnesota, 1957)
Segal v. Bloom Brothers Co.
82 N.W.2d 359 (Supreme Court of Minnesota, 1957)
Sundeen v. Barthel
63 N.W.2d 267 (Supreme Court of Minnesota, 1954)
Whitman v. Speckel
53 N.W.2d 558 (Supreme Court of Minnesota, 1952)
Anderson v. Northern States Power Co.
52 N.W.2d 434 (Supreme Court of Minnesota, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
47 N.W.2d 199, 233 Minn. 452, 1951 Minn. LEXIS 659, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-paskewitz-minn-1951.