State v. McConnell

266 N.W.2d 219, 201 Neb. 84, 1978 Neb. LEXIS 747
CourtNebraska Supreme Court
DecidedMay 31, 1978
Docket41535
StatusPublished
Cited by8 cases

This text of 266 N.W.2d 219 (State v. McConnell) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. McConnell, 266 N.W.2d 219, 201 Neb. 84, 1978 Neb. LEXIS 747 (Neb. 1978).

Opinion

Spencer, J. .

Defendant, Sanford W. McConnell, who is a building contractor, appeals his conviction under section 52-123, R. R. S. 1943, for failure to apply money re *85 ceived in payment of lawful claims of laborers or materialmen. Defendant assigns as error the unconstitutionality of the statute, and that he was found guilty without proof of fraud. We reverse.

In a proposal dated May 29, 1974, Urban Builders, Inc., agreed to furnish labor and materials to construct a kitchen addition to a house owned by Dominic Romeo for a total price of $9,150. Payment terms were “10% upon acceptance of proposal, 40% upon start, balance due at completion.” The proposal was signed by Sanford W. McConnell, who was the president of Urban Builders, Inc.

The proposal was delivered to the home of Romeo by John Boles, an employee of Urban Builders, Inc. He had estimated the job and was the supervisor of the project. The document does not bear the signature of Mr. Romeo for acceptance of the proposal. It does, however, contain a notation made by Boles, as follows: “$915.00 paid in cash as down payment.” This notation is signed by J. Boles, as an acknowledgment that he received it.

The cash was delivered to Richard Slezak, who was the treasurer and accountant for Urban Builders, Inc. It was deposited in the corporation’s operating fund. He drew the checks on the operating fund. These checks had another signature as well as his own. The money was used to pay a telephone bill, Boles’ wages, and 1 week’s salary for Slezak. The money was disbursed within 7 days after receipt. To his knowledge, no invoice or statement of work was ever presented by the subcontractor for the Romeo job.

Work was begun June 21, 1974, when Stier & Sons Construction, Inc., performed excavation work and laid the foundation. It ended June 28, 1974. Romeo’s architect testified this work was satisfactory and complete except for a few things which had to wait until the carpenters began work. A mechan *86 ic’s lien in the amount of $1,953 for this work was filed September 19, 1974.

When no further work was forthcoming, Romeo and his architect went to defendant’s office for a meeting. Romeo testified defendant told him the company was having financial problems and the job had been underbid. After consulting with the architect, Romeo agreed to an increase in the contract price to get the job done. An agreement to this effect was executed July 8, 1974. This agreement, so far as material herein, reads as follows: “Mr. Romeo has agreed to raise the contract price from $8,650.00 to $10,050 plus $500.00 contingency providing that Jim Windorski is the carpenter on the project to include rough and finish and to commence work on Friday, July 12 but not later than Monday, July 15th.. A written schedule is to be delivered by July 18th 1974. Work is to be completed within 45 days. Payment is to be made directly to the carpenters and Urban Builders Inc. is to pay masonry contractor.

“All other work as per contract.” This proposal is signed by Sanford W. McConnell, and like the other one bears no signature or acceptance by Romeo.

Work did not resume after the execution of this agreement. Romeo did not make any further payments. He testified his reason for not paying the 40 percent of the contract price called for in the original agreement was that defendant refused to provide a performance bond which Mr. Boles had promised at the time of contracting.

The architect, Norman Reece, was present when both of the agreements were executed. He believed that on each occasion there had been two documents and Romeo had signed the one retained by defendant. He testified Boles had stated at the time of contracting that there would be no problem in obtaining a performance bond and it “would be returned within several days, as soon as they had time to get *87 it.” Reece further testified when the contract was modified, they were promised that a performance bond would be provided the following day. After the second agreement was signed, he was unable to contact defendant because the telephone had been disconnected. He called Boles at home several times and was repeatedly assured that a performance bond would be issued. He could not recall why work did not resume by July 15, 1974. He felt the carpenter he had recommended was working on another job at that time.

Defendant testified he was informed by Boles that a performance bond had been requested. He told Romeo at the meeting in his office that he had been negotiating with the bonding company but that no performance bond could be provided. Romeo agreed to waive any performance bond requirement. Defendant testified he also informed Romeo at this meeting that the carpenter selected for the job had raised his price but that another carpenter could be used. Romeo stated he wanted the carpenter, a Mr. Windorski, to perform the carpentry work and was willing to pay more money.

As to the reason work was not resumed after June 28, 1974, defendant testified: “At the time we met in the office, I told them that the carpenter was involved with another job and I told them I thought at the time that he would be out there within a week. Evidently it took him longer to get out on the job but I have no control to go out there and physically to force him to leave the one job to start the other. In the mean time, our phone was shut off. Mr. Reece talked to John Boles and he said because of the fact that our phone was shut off that we were terminated on the job. This was related to me by Mr. Boles.”

Defendant also testified it is a common practice in the construction industry to ‘‘front load” a job by paying overhead expenses from the downpayment. He intended to pay Stier & Sons Construction, Inc., *88 when he received the payment of 40 percent of the contract price from Romeo. Defendant requested payment of this amount at the meeting in his office. He testified: “I asked him (Mr. Romeo) the day he came into the office and I told him that we could not provide the performance bond. He said at that time he was keeping all copies of the contract. I had not had a copy of the contract myself. And he said that when Windorski got on the job that he would fund additional money.”

Section 52-123, R. R. S. 1943, provides: “It shall be unlawful for any person, firm, or corporation who has taken a contract for the erection, improvement, repair, or removal of any house, mill, manufactory, or building of any kind for another, and has received payment in whole or in part upon such contract, to fail to apply the money so received, or so much thereof as may be necessary for that purpose, in payment of the lawful claims of such laborers or materialmen as could otherwise have a right to file a laborers’ or materialmen’s lien against such house or other structure, with the intent thereby to deprive or defraud the owner or person so paying the person, firm or corporation receiving payment, of his funds without discharging the liens, unless such person, firm, or corporation, taking such contract, shall have received and delivered to the owner of the property the written waiver of lien from all persons who otherwise would have a right to file a lien thereon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Fire Marshal v. Schaneman
279 N.W.2d 101 (Nebraska Supreme Court, 2009)
McElroy v. State
667 S.W.2d 856 (Court of Appeals of Texas, 1984)
State v. Hiross
318 N.W.2d 291 (Nebraska Supreme Court, 1982)
State v. Sharski
306 N.W.2d 592 (Nebraska Supreme Court, 1981)
State v. Irwin
302 N.W.2d 386 (Nebraska Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
266 N.W.2d 219, 201 Neb. 84, 1978 Neb. LEXIS 747, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-mcconnell-neb-1978.