State v. Malone Service Co.

853 S.W.2d 82, 1993 Tex. App. LEXIS 810, 1993 WL 81231
CourtCourt of Appeals of Texas
DecidedMarch 25, 1993
DocketA14-89-01132-CV
StatusPublished
Cited by6 cases

This text of 853 S.W.2d 82 (State v. Malone Service Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Malone Service Co., 853 S.W.2d 82, 1993 Tex. App. LEXIS 810, 1993 WL 81231 (Tex. Ct. App. 1993).

Opinion

OPINION ON REMAND

J. CURTISS BROWN, Chief Justice.

This environmental enforcement action sought by the attorney general’s office against the operators of a hazardous waste disposal plant comes to this Court on remand from the supreme court, 829 S.W.2d 763 (Tex.1992), cert. denied — U.S. -, 113 S.Ct. 464, 121 L.Ed.2d 372. At trial, the jury assessed more than $3 million in penalties against Malone Service Company, its president and plant manager (collectively “MSC”), for groundwater contamination and unauthorized hazardous waste dumping. The State appealed our holding that the trial court improperly excluded evidence relating to MSC’s defense of discriminatory enforcement. 804 S.W.2d 174. The supreme court, however, concluded that MSC failed to “show a clear intentional discrimination” by the State in taking strong enforcement action against Malone while taking little or no action against a quasi-governmental agency that was MSC’s direct competitor. 829 S.W.2d at 767. We are bound by the supreme court’s opinion as the law of the case. Upon consideration of issues not previously addressed, we affirm.

On August 17, 1977, the Texas Water Quality Board issued an order amending a deep well injection permit held by MSC. The amendment required that

*84 [a] concrete separator shall be constructed for pretreatment of the waste to replace the existing earthen pit and placed in service within nine months after issuance of the amendment. The Company shall discontinue use of the earthen pit upon completion of the separator and close-out the earthen pit as described in the application within 18 months after issuance of this Amendment (emphasis added).

The Texas Department of Water Resources, predecessor agency of the Texas Water Commission (“TWC”), twice extended the deadline, but on September 19, 1979, it ordered MSC to cease receiving any waste materials into the earthen pit and to close the pit within nine months. A number of current and former MSC employees testified they continued to pump sludge into the pit, covertly. To conceal the activity from outsiders, they would write code phrases such as “pumping sludge ... over the levy [sic]” in their logbooks, and they shut down the pumps whenever inspectors came. When MSG entered into a compliance agreement with the State to close the pit with a tarpoleum, employees cut tears in the fabric so they could continue to pump waste into the pit. At TWC’s request, the attorney general’s office brought this action.

In its first point of error, MSC contends there is no evidence or insufficient evidence to support the jury’s finding that MSC unlawfully used the earthen pit on 417 occasions because (1) as a matter of law, replacement is not a “use,” and (2) there is direct evidence of only one alleged violation, presumably the day state officials raided MSC with a search warrant. Jurors disbelieved MSC’s claim that the only hazardous waste pumped into the pit was material that had been removed from the pit along with rainwater in an effort to clean the pit. To the contrary, Mike Givens, MSC’s plant manager from 1980-1984, attributed very little sludge from rainwater removal because rainwater was drawn off through a pipe that floated on the surface on the pit.

Further, Givens explained that trucks were unloaded into separators adjacent to the pit, solids would settle, and the resulting sludge would be pumped into the pit. So much more sludge was put into the earthen pit than was removed that the levee around the pit had to be built up; shift supervisor Art Sanders estimated that sludge from the separators caused the level of the pit to rise ten to fifteen feet. In addition, workers testified, waste from incoming trucks was occasionally dumped directly into the pit. MSC logbooks document the routine dumping of hazardous waste into the pit. We overrule point of error number one.

Next, MSC contends there is no evidence of 360 violations occurring before September 17, 1984 because, under law, MSC was a “permitted facility” for on-site storage of hazardous waste until that date. However, the State responds that MSC was not entitled to on-site exclusion because wastes generated on-site were commingled with waste from other sources. The jury specifically found that MSC did not conduct only on-site storage, processing or disposal of hazardous waste, and the evidence supports that finding. Moreover, other permits held by MSC explicitly prohibited continued use of the earthen pit. Point of error number two is overruled.

In its third point of error, MSC contends there can be no individual liability for its president or plant manager because they did not own the permit. The Texas Water Code states that:

[a] person who violates any provision of a permit issued under this chapter shall be subject to a civil penalty in any sum not exceeding $5,000 for each day of noncompliance and for each act of noncompliance. Tex. Water Code Ann. § 27.101(a) (Vernon 1988).

A “person” is defined as “a corporation ... and any other legal entity,” which includes natural persons. Tex. Gov’t Code Ann. § 311.005(2) (Vernon 1988). However, appellants compare Section 27.101 liability with similar language limiting civil penalties for usury:

*85 [a]ny person who contracts for, charges or receives interest which is greater than the amount authorized by this Subtitle, shall forfeit to the obligor three times the amount of usurious interest contracted for, charged or received_ Tex.Rev. Civ.Stat.Ann. art. 5069-1.06 (Vernon 1988).

That statute has been interpreted to limit liability to a principal only. Wartman v. Empire Loan Co., 45 Tex.Civ.App. 469, 101 S.W. 499 (1909, no writ). Accordingly, appellants conclude that Section 27.101 does not impose liability for a “person” who does not own the permit, although he or she acts as agent, aider or abettor in violating the act. The State distinguishes Wartman by noting that its controlling issue was whether the collection agents’ receipt of usurious interest was tortious. 101 S.W. at 500. WTiile usury “has a contractual flavor,” an environmental tort is more analogous to a situation in which a corporate officer who participates in or directs the commission of a tort may be held personally liable. See, e.g., Leyendecker & Assoc., Inc. v. Wechter, 683 S.W.2d 369, 375 (Tex.1984). Liability is based on the agent’s own actions, not his status as agent. Id. Indeed, in federal environmental cases, courts have applied the personal participation doctrine to “persons” who are not permit holders. E.g., U.S. v. Johnson & Towers, Inc., 741 F.2d 662 (3rd Cir.1984), cert. denied, Angel v. U.S., 469 U.S. 1208, 105 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
853 S.W.2d 82, 1993 Tex. App. LEXIS 810, 1993 WL 81231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-malone-service-co-texapp-1993.